Laserfiche WebLink
Gateway Park Center PERKINS+WILL <br /> 810495.000 <br /> 12/06/18 <br /> <br /> <br />CONSTRUCTION PROGRESS DOCUMENTATION <br /> 01 32 00 - 7 <br /> <br /> <br />1. In first list, tabulate activity number, early finish date, dollar value, and <br />cumulative dollar value. <br />2. In second list, tabulate activity number, late finish date, dollar value, and <br />cumulative dollar value. <br />3. In subsequent issues of both lists, substitute actual finish dates for activities <br />completed as of list date. <br />4. Prepare list for ease of comparison with payment requests; coordinate timing <br />with progress meetings. <br />a. In both value summary lists, tabulate "actual percent complete" and <br />"cumulative value completed" with total at bottom. <br />b. Submit value summary printouts one day before each regularly <br />scheduled progress meeting. <br />1.8 REPORTS <br />A. Daily Construction Reports: Prepare a daily construction report recording the <br />following information concerning events at Project site: <br />1. List of subcontractors at Project site. <br />2. List of separate contractors at Project site. <br />3. Approximate count of personnel at Project site. <br />4. Equipment at Project site. <br />5. Material deliveries. <br />6. High and low temperatures and general weather conditions, including <br />presence of rain or snow. <br />7. Testing and inspection. <br />8. Accidents. <br />9. Meetings and significant decisions. <br />10. Stoppages, delays, shortages, and losses. <br />11. Meter readings and similar recordings. <br />12. Emergency procedures. <br />13. Orders and requests of authorities having jurisdiction. <br />14. Change Orders received and implemented. <br />15. Construction Change Directives received and implemented. <br />16. Services connected and disconnected. <br />17. Equipment or system tests and startups. <br />18. Partial completions and occupancies. <br />19. Substantial Completions authorized. <br />B. Site Condition Reports: Immediately on discovery of a difference between site <br />conditions and the Contract Documents, prepare and submit a detailed report. <br />Submit with a Request for Information. Include a detailed description of the <br />differing conditions, together with recommendations for changing the Contract <br />Documents.