Rohl Global Networks, LP for credits to the City for direct material purchases and the rescinding
<br /> of Change Order No. 16, decreasing the contract value in the amount of$666,250.00, bringing
<br /> the total contract amount not to exceed $12,914,942.95; and
<br /> WHEREAS, on May 17th, 2018 via Resolution No. 2018-2816, the City Commission
<br /> approved Change Order No. 19 for the addition and relocation of Florida Power & Light and
<br /> Atlantic Broadband services equipment, revised Atlantic corridor scope of work, and other
<br /> unforeseen conditions on Collins Avenue in the amount of$899,524.00; and
<br /> WHEREAS, on September 20th, 2018 via Resolution No. 2018-2869, the City
<br /> Commission approved Change Order No. 20 crediting the City for direct material purchases in
<br /> an amount of$37,100.00, bringing the total contract amount not to exceed $13,777,366.95, and
<br /> Change Order No. 21 in an amount not to exceed $34,796.00 for work and material completed to
<br /> assure that the State of Florida RRR project did not adversely impact the work previously
<br /> completed, bringing the total contract amount not to exceed $13,812,162.95; and
<br /> WHEREAS, on October 18th, 2018 via Resolution No. 2018-2879, the City Commission
<br /> approved Change Order No. 22 to facilitate the ongoing installation of the Collins Avenue
<br /> decorative streetlight project, alternate base installation to avoid utility conflicts, removal of
<br /> abandoned bases as required by FDOT, provision of FPL power service points, and to establish a
<br /> contingency allowance to resolve unforeseen and undocumented existing conditions in an
<br /> amount not to exceed $400,000.00, bringing the total contract amount not to exceed Fourteen
<br /> $14,212,162.95; and
<br /> WHEREAS, on February 21st, 2019 via Resolution No. 2019-2918, the City
<br /> Commission approved Change Order No. 23 to continue the Collins Avenue decorative street
<br /> lighting and to replace the pedestrian crosswalk at 193rd Street in conjunction with Utility
<br /> Undergrounding Project, in an amount not to $1,399,089.50, bringing the total contract amount
<br /> not to exceed $15,611,252.45; and
<br /> WHEREAS, on October 17, 2019 via Resolution No. 2019-3004, the City Commission
<br /> approved Change Order No. 24 for credits to the City for direct material purchases, decreasing
<br /> the contract value in the amount of$31,458.00, bringing the total contract amount not to exceed
<br /> $15,579,794.45; and approved Change Order
<br /> ppNo. 25 to resolve unforeseen and
<br /> undocumented
<br /> existing conditions with the installation of the decorative street lighting and conduits along
<br /> Collins Avenue, additional survey and as-built documents required by FPL for the
<br /> undergrounding along g g o g the Atlantic Corridor, and increase in costs due to delays related to
<br /> unforeseen conditions, in an amount not to exceed $982,615.00, bringing the total contract
<br /> amount not to exceed $16,562,409.45; and
<br /> WHEREAS, on January 16th, 2020 via Resolution No. 2020-3037, the City Commission
<br /> approved Change Order Nos. 26 and 27 crediting the City for direct material purchases and
<br /> reducing the amount of the contract by $211 553.00 bringing
<br /> � the total contract amount g not to
<br /> exceed $16,350,856.45; and
<br /> WHEREAS, the Contractor has submitted Change Order No. 28 for unforeseen
<br /> obstructions, alternate spread footings, addition of power supply for low voltage outlets on
<br /> streetlights, additional conduit and wire for revised streetlight locations, and additional material
<br /> testing requirements mandated by FDOT, in an amount not to exceed $2,213,486.96, attached
<br /> hereto as Exhibit "A"; and
<br /> R2020 CO 28 w ROHL Networks Page 2 of 4
<br />
|