reducing the amount of the contract by $211,553.00, bringing the total contract amount not to
<br />exceed $16,350,856.45; and
<br />WHEREAS, on February 20, 2020, via Resolution No. 2020-3055, the City Commission
<br />approved Change Order No. 28 for unforeseen obstructions, alternate spread footings, addition
<br />of power supply for low voltage outlets on streetlights, additional conduit and wire for revised
<br />streetlight locations, and additional material testing requirements mandated by FDOT, in an
<br />amount not to exceed $2,213,489.96, bringing the total contract amount not to exceed
<br />$18,564,346.41; and
<br />WHEREAS, on October 15, 2020, via Resolution No. 2020-3126, the City Commission
<br />approved Change Order No. 29 for additional scope of services for the streetlight project,
<br />including additional fixtures, modified spread footings, increased conduit installation, extended
<br />general conditions, miscellaneous FDOT requirements, unforeseen underground conditions,
<br />and adding a total of 92 days to the length of the original contract, thereby extending the
<br />completion date to December 31, 2020, in an amount not to exceed $889,633.41, bringing the
<br />total contract amount not to exceed $19,453,979.82; and
<br />WHEREAS, on December 9, 2020, via Resolution No. 2021-3174, the City Commission
<br />ratified Change Order No. 30 adding a total of 181 days to the length of the original contract,
<br />thereby extending the completion date to June 30, 2021 ; and
<br />WHEREAS, on June 17th, 2021, via Resolution No. 2021-3203, the City Commission
<br />ratified Change Order No. 31, which extended the project completion date by additional 184
<br />days to December 31, 2021; and
<br />WHEREAS, the Contractor has submitted Change Order No. 32, requesting an additional
<br />365 days to achieve project completion, and including a General Conditions costs of $10,000.00
<br />per month, for a total not to exceed $120,000.00; and
<br />WHEREAS, the City Commission now wishes to approve Change Order No. 32 to the
<br />Agreement with ROHL Global Networks, LP extending the project completion date to December
<br />31, 2022, and to include a General Conditions costs in an amount not to exceed $120,000.00,
<br />bringing the total contract amount not to exceed Nineteen Million Five Hundred Seventy -Three
<br />Thousand Nine Hundred Seventy -Nine Dollars and Eighty -Two Cents ($19,573,979.82), attached
<br />hereto as Exhibit "A".
<br />NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF SUNNY
<br />ISLES BEACH, FLORIDA, AS FOLLOWS:
<br />Section 1. Ratification of Change Order No. 32. The City Commission hereby ratifies Change
<br />Order No. 32 to the Agreement with ROHL Global Networks, LP extending the project
<br />completion date to December 31, 2021, and to include a General Conditions costs in an amount
<br />not to exceed $120,000.00, bringing the total contract amount not to exceed Nineteen Million
<br />Five Hundred Seventy -Three Thousand Nine Hundred Seventy -Nine Dollars and Eighty -Two
<br />Cents ($19,573,979.82), attached hereto as Exhibit "A".