1.5.4. The words "include", "includes", or "including", as used in this Contract, shall be
<br />deemed to be followed by the phrase, "without limitation".
<br />1.5.5. The specification herein of any act, failure, refusal, omission, event, occurrence or
<br />condition as constituting a material breach of this Contract shall not imply that any other, non-
<br />specified act, failure, refusal, omission, event, occurrence or condition shall be deemed not to
<br />constitute a material breach of this Contract.
<br />1.5.6. Words or terms used as nouns in this Contract shall be inclusive of their singular and
<br />plural forms, unless the context of their usage clearly requires a contrary meaning.
<br />1.5.7. The Contractor shall have a continuing duty to read, carefully study and compare
<br />each of the Contract Documents, the Shop Drawings and the Product Data and shall give written
<br />notice to the City of any inconsistency, ambiguity, error, or omission which the Contractor may
<br />discover with respect to these documents before proceeding with the affected Work. The issuance,
<br />or the express or implied approval by the City or the Engineer/ Architect of the Contract Documents,
<br />Shop Drawings or Product Data shall not relieve the Contractor of the continuing duties imposed
<br />hereby, nor shall any such approval be evidence of the Contractor's compliance with this Contract.
<br />The City has requested the Engineer /Architect to only prepare documents for the Project, including
<br />the Drawings and Specifications for the Project, which are accurate, adequate, consistent,
<br />coordinated, and sufficient for construction. HOWEVER, THE CITY MAKES NO
<br />REPRESENTATION OR WARRANTY OF ANY NATURE WHATSOEVER TO THE
<br />CONTRACTOR CONCERNING SUCH DOCUMENTS. By the execution hereof, the Contractor
<br />acknowledges and represents that it has received, reviewed and carefully examined such documents,
<br />has found them to be complete, accurate, adequate, consistent, coordinated and sufficient for
<br />construction, and that the Contractor has not, does not, and will not rely upon any representation or
<br />warranties by the City concerning such documents as no such representation or warranties have been
<br />or are hereby made. The Contractor further acknowledges and represents that it has made a thorough
<br />and careful examination and inspection of existing conditions on the Project site, both surface and
<br />subsurface, and the Contractor expressly acknowledges and agrees that it shall make no claim for
<br />additional compensation due to existing site conditions including, but not limited to, rock, surface
<br />and subsurface water, existing structures, and deficient soil, provided said conditions could be
<br />determined or ascertained from a thorough and careful examination and inspection of the site.
<br />1.5.8. Neither the organization of any of the Contract Documents into divisions, sections,
<br />paragraphs, articles, (or other categories), nor the organization or arrangement of the Design, shall
<br />control the Contractor in dividing the Work or in establishing the extent or scope of the Work to be
<br />performed by Subcontractors.
<br />1.5.9. Whenever the word "days" is used, it shall mean calendar days and not working days
<br />unless otherwise specified.
<br />1.5.10. Contractor shall comply with Section 255.04, Florida Statutes, in selecting
<br />subcontractors, materials and suppliers.
<br />1.6 Ownership of Contract Documents
<br />1.6.1. The Contract Documents, and each of them, shall remain the property of the City
<br />unless the City has agreed otherwise with the Engineer / Architect. The Contractor shall have the
<br />MBR CONSTRUCTION, INC. Page 3 of 41