City of Sunny Isles Beach 18070 Collins Avenue, Sunny Isles Beach, Florida 33160 <br />(305) 947-0606 phone (305) 949-3113 Fax <br />8.3.4 Claims for Additional Costs — Except as prohibited in Paragraph 8.3.5 herein <br />below, if the Contractor wishes to make a claim for an increase in the Contract Price, as <br />a condition precedent to any liability of the City therefore, the Contractor shall give the <br />City's Representative and the City written notice of such claim within three (3) days after <br />the occurrence of the event, or the first appearance of the condition, giving rise to such <br />claim. Such notice must be given by the Contractor before proceeding to execute any <br />additional or changed Work. The failure by the Contractor to give such notice and to give <br />such notice prior to executing the Work shall constitute a waiver of any claim for additional <br />compensation. <br />8.3.4.1 In connection with any claim by the Contractor against the City for <br />compensation in excess of the Contract Price, any liability of the City for the <br />Contractor's cost shall be strictly limited to direct costs incurred by the Contractor <br />plus a reasonable mark-up of fifteen percent (15%) for overhead and profit <br />consistent with Paragraph 10.3.3.4 below. Direct costs do not include the <br />Contractor's home office overhead, loss of efficiency, consequential damages of <br />the Contractor, or equipment costs in excess of actual equipment rental paid by the <br />Contractor to a third party. The City shall not be liable to the Contractor for claims <br />of third parties, including Subcontractors, unless and until liability of the Contractor <br />has been established therefore in a court of competent jurisdiction. <br />8.3.5 Claims for Additional Time—If the Contractor is delayed in progressing any <br />task which at the time of the delay is then critical or which during the delay becomes <br />critical, as the sole result of any act or neglect to act by the City or someone acting in the <br />City's behalf, or by changes ordered in the Work, unusual delay in transportation, <br />unusually adverse weather conditions not reasonably anticipatable, fire or any causes <br />beyond the Contractor's control, then the date for achieving Final Completion of the Work <br />shall be extended upon the written notice and claim of the Contractor to the City and the <br />City's Representative for such reasonable time as the City's Representative and the City <br />may determine plus extended, documented general conditions expenses including, among <br />other things, project management, supervision and project site overhead expenses. Claims <br />for delay can only be submitted for consideration in the event they have a direct, <br />documentable impact on the Critical Path of the project as evidenced on the (CPND <br />schedule. Concurrent delay events impacting the schedule will only be considered as a <br />single impact and will be limited to a non -compensable time extension. Any notice and <br />claim for an extension of time by the Contractor shall be made not more than three (3) days <br />after the occurrence of the event or the first appearance of the condition giving rise to the <br />claim and shall set forth in detail the Contractor's basis for requiring additional time in <br />which to complete the Project. Said claim shall specifically include, among other things, <br />an adjusted critical path (CPM) schedule reflecting precisely the delay and its claimed <br />impact upon the Contractor's future performance. In the event the delay to the Contractor <br />is a continuing one, only one notice and claim for additional time shall be necessary. If the <br />Contractor fails to make such claim as required in this Subparagraph, any claim for an <br />extension of time shall be waived. <br />8.3.5.1 In no event, and under no circumstances, shall the Contract Price be <br />increased for, nor shall the Contractor claim, recover, or receive payment for, any <br />cost, expense, damages, or compensation of any kind by reason of any delay to the <br />COMTECH ENGINEERING, INC. 23 <br />