|
<br />Miami-Dade Branch
<br />6600 NW 32 Ave
<br />Miami, FL 33147
<br />
<br />Ph: (305) 696-7902
<br />Fax: (305) 696-7903
<br />e-mail: cg@jvaengineering.com
<br />Cesar Gonzalez
<br />Experience
<br />
<br />2009-Present JVA Engineering Contractor, Inc.
<br />Project Manager
<br />2013 City of Miami- Citywide Sewer Repair Contract, M-0083 Installation and
<br />Repair of the Storm Sewer system at locations citywide
<br />2013 City of Miami- Miami River Greenway NW 5th Bridge Extension
<br />Furnishing all materials, labor, and equipment, necessary for road
<br />improvements, drainage system installations, milling and resurfacing, new
<br />sidewalks replacement, striping, signs, landscaping, hardscape, decorative
<br />street and pedestrian lighting, and ADA compliant ramps
<br />2012 City of Opa-Locka- 143rd Street Distribution Piping Project, Roadway
<br />Reconstruction
<br />2012 City of Hollywood- Distribution Piping Upgrade for Existing Condition N
<br />56th Ave from Douglas Street to Stirling Road to N 58th Avenue , Furnish and
<br />Install 8-inch D.I. Pipe and all D.I. Fittings
<br />2012 Miami-Dade Water & Sewer Improvements-Furnish & Install 36-Inch D.I.
<br />Water Main in NW 87th Avenue, Approximately 1,905 LF of 36-Inch and 25
<br />LF of 6-inch ductile iron pipe and fittings for a water main in NW 87th Avenue
<br />from NW 154 Street to NW 186 Street, Section 10, 15, and 16
<br />2011 Miami-Dade Water & Sewer Improvements-Perrine/Cutler Ridge Water
<br />& Sewer Improvements Basin A P0067- 4,991 LF of Water Main Installation,
<br />5,035 LF of Sanitary Sewer Installation and 848 LF of 12” Gravity Sewer
<br />Installation, Sewer Lateral Installations and Restoration
<br />2011 Miami-Dade Aviation Department- MIA NW 67th Ave and NW 36th Street
<br />Intersection Improvements, Land Clearing, Excavation, Earthwork, Pre-
<br />Stressed Concrete Pipe Storm Sewer Distribution, Subgrade, Base and
<br />Asphalt Pavement
<br />2011 City of Miami- Kinloch Storm Sewer and Road Construction Project,
<br />Storm Drainage Distribution, Asphalt Pavement, and Concrete Work
<br />2010 Marlins Ballpark, Storm Water Distribution
<br />2009 Miami-Dade Water & Sewer- 8” Water Main Extension, Excavation Water
<br />Main Distribution, Restoration including Asphalt Pavement, and Concrete
<br />work
<br />2009 Miami-Dade County Water & Sewer Department, NAP Misc. 12” Sanitary
<br />Sewer and Force Main Improvements, sanitary sewer and force main
<br />replacements, asphalt restoration, concrete restoration.
<br />2009 Miami-Dade County Water & Sewer Department, Pump Station No. 57
<br />Upgrade Sewage Pump Station including place suitable backfill material;
<br />refurbish wet well; electrical work, concrete sidewalk; and restoration
<br />2009 Miami-Dade County Water & Sewer Department, Pump Station No. 46
<br />Upgrade Sewage Pump Station including place suitable backfill material;
<br />refurbish wet well; electrical work, concrete sidewalk; and restoration
<br />2009 Port of Miami, Cruise Terminal D&E Runway Extension for PBB and
<br />Mooring Bollards Construction of reinforced concrete runway and wheel
<br />pad slabs; compression auger cast piles; mooring bollards foundation
<br />concrete caps; tension auger cast piles; procurement and installation of six
<br />mooring bollards and demolition of abandoned electrical bays
|