TREE PROTECTION AND RELOCATION NOTES <br />1.1 WORK TO BE PERFORMED AND WORK INCLUDED <br />A. Provd. the following <br />Prepare and relocate trees and palms designated for relocation within the project <br />boundaries into holding areas, to include all aspects of preparation, acclimatization, hoeing, <br />relocation, protection, and maintenance. <br />Protection and care of existing trees and palms to remain within the project boundaries. <br />3. Inslalbtlon and operation of temporary imitation system and hand watering as <br />required by these specifications. <br />4. Establishment of holding areas as necessary to support the phasing of the project. <br />5. Folbw -up maintenance as required by thaw specifications. <br />6. Labor, materials, equipment and services to complete all preparation, relocations, <br />and protection work as indicated on the drawings, as spectled herein, or both. <br />PART 11- PRODUCTS <br />2.1 PLANTING SOIL MIXES <br />A. Planting Sol Mixture A to be placed in St. Augustine sod areas, shrub and ground cover <br />beds and In broadleaf tree pits, both new and transplanted: <br />' <br />20% Topsoil <br />10 % Peat or compost <br />70 %Sand <br />B. Planting Sall Mixture B to be placed as backlll around the roof balls of palms shall be: <br />90% "alive sand from on site or approved source <br />' 10 % topsoil. <br />22 Soil Amendments <br />A. See written specification 02920. <br />PART III - EXECUTION <br />3.1 PREPARATION FOR RELOCATION OF TREES AND PALMS <br />A. Crown Pruning <br />1. Broadleaf Trees -All bees are to be trimmed by thinning the crown only, and not by <br />reducing crown dimensions. Trim to conform to NAA and ISA standards, including removal <br />of dead wood. Repair any existing injuries to trees including caysbs and machinery marks. <br />2. Palms - Remove all seed pods and lowest fronds, leaving 9.11 youngest fronds. For <br />Swat Palms only, cut back all fronds in a'hunicane cul' prior to transplanting unless specified <br />otherwise In the field by the landscape architect. <br />B. Fertilization and Watering <br />1. Preparation <br />a. All Trees and Palms lobe relocated shall be treated with walling agents, fertilizers, <br />fool stimulants, and sail conditioners at the lime of relocation. See speeHlcation 02920. <br />b. Form and maintain an earth berm 6' high outads the proposed root bell prior to <br />watering and apply 3- approved mulch within saucer. Water application shall <br />saturate the root ball to its entire depth. <br />C. Root Pruning <br />1. Wearing <br />All Imes and palms to be relocated are to be provided with an oulomatle irrigation <br />syslem which provides 2 bubbler heads to each bee and palm. prior to root pruning. <br />Provide urgalion timer, or battery powered valve to water trees to be relocated. Hand <br />watering in lieu of automatic system shall not be allowed, however hand misting shall be <br />performed to avoid lapses should the automatic system be inoparablo for mono than 24 <br />hours and during the initial planting period as specified. <br />2. Barricades <br />Barricade all existing bees and palms with six fool (61 chain link fence or other barricade <br />approved by Owner. <br />Root Pruning Technique -Ali trees shall be mmated bydgging a trench 36' deep, <br />olther by hand or with a trenching machine designed for this purpose. Hand cut broadleaf <br />tree roots agar trenching to produce clean cuts with no spite or tears. Trees to be root <br />pruned shall have a minimum root ball size of 10' per 1' of caliper measured at DBH for <br />broad leer Imes, 30" for Sabal Palms, 42' for Coconut Palma, Sabal palms shall not require <br />roof pruning. <br />Timing -AII broadleaf trees are to be relocated shall be maintained fora minimum of item <br />(10) weeks after rapt pruning prior to reocaton. All palms except Sabal Palms, shall be: <br />maintained a minimum of four (4) weeks prior to mocatan. <br />3.2 RELOCATION OF TREES AND PALMS <br />A. Preparation - Trees and palms shall be thoroughly soaked to the full depth of the root <br />ball daily for seven consecutive days prior to relocation. Accurately locate position and <br />elevation where all trees are intended to be planted, for verification by Landscape <br />Architect. Verily that no overhead or underground utilities, existing or proposed, conllicl <br />with proposed krcalions. <br />B. Digging and Handling <br />Determine line of previous root pruning and excavale around root mass to leave area <br />outside line of root pruning undisturbed. Digging shall be accomplished was to <br />produce clean cuts on all roots without tearing or splitting. Trenching shall be a minimum of <br />48' deep. <br />Trees shall be handled in such a way as to avoid damage to bark and limbs subject to <br />support cables or chains. Attach padded support cables or chains at multiple points <br />where possible. <br />Root balls shall be undercut prior to lifting. Do not force tree from ground prior to <br />undercutting. Ball depth to be determined upon assessing conditions at time of trenching, <br />to keep intact the entire root ball. <br />Trees shall be properly wrapped during moving so trunks will not be scarred and damaged <br />and to avoid broken limbs. Broken limbs or scarred trunks shat cause time to be <br />unacceptable and rejected at the Owner's option. Root balls and foliage shall be kept <br />moist during all phases of relocation. <br />Partially backfill tree pits with IT of approved planting soil prior to selling tree. This <br />layer of soil to be thoroughly drenched prier to relocation to achieve a stable platform <br />al the correct elevation so that the lop of root ball is V above proposed grade. <br />Backfilling - Flood bottom foil layer to settle tree into best position and to remove air <br />pockets. Continue to flood root ball as planting soil is deposited to insure removal of all <br />air pockets. Produce saucer to retain water per drawings. <br />Bracing - Support tree with machinery until bracing is complete. Buttresses may support <br />separate bunks on multiple trunk trees. Maintain braces until completion of project. <br />Irrigation - Install bubbler heads on all trees and palms. Connect each free's system <br />Immediately to water source. Additionally, all transplanted Imes and palms shall be hand <br />watered daily for - period of six (6) weeks after transplanting. The irrigation system is <br />designed for mainfaining plant material only, and does not provide the volume of water <br />required immediately after transplanting. Set time to run daily, to provide an equNalenl of <br />V of rain per week for 30 days, then reduce to equivalent of 3' per week. <br />C. Holding Are. <br />A holding area shall be provided specifically designated for storage and acclimatization <br />of relocated trees and palms that are to be relocated in later project phases, or in the <br />current phase. The holding area shall be of sufficient size to allow for temporary planting <br />of Imes and palms without undue crowding. <br />Holding area shall be provided with a temporary automatic Irrigation system, and shall be <br />excavated and provided with a soil layer a minimum of 30' deep. Irrigation shall be <br />monitored and supplemented as necessary to provide water in volumes sufficient for <br />growth. <br />3 PROTECTION AND CARE OF EXISTING TREES AND PALMS TO REMAIN <br />Watering - Existing irrigation shall remain operable to the greatest extent possible during <br />construction. All on site trees to remain shall be supplied with temporary irrigation (.remain <br />operable until permanent irrigation is operable. Existing irrigation system to be demolished mr <br />be utilized as the temporary irrigation system. <br />Barricading - Barricade all existing trees and palms with six foot (6') chain link fence or other <br />barricade approved by Owner. Barricades shall be installed at an offset distance two feel (2') <br />outside the tree drip linatedge of tree canopy to the extent practical, prior to any construction <br />activity. <br />TREE DISPOSITION *SEE SHEET L-3.01 FOR LANDSCAPE PLAN <br />OPALM, TO RELOCATE <br />00 <br />PALM, TO REMOVE <br />00 <br />OPALM, TO PROTECT IN PLACE <br />00 <br />TREE, TO REMOVE <br />00 <br />*TREE DISPOSITION RATING (1 THROUGH 5) <br />1 VALUE= POOR CONDITION / INVASIVE SPECIES <br />5 VALUE = SPECIMEN TREE / HEALTHY <br />Estates at Acqualina <br />Sunny Isles, Florida <br />Owner: <br />GSF Acquisition, LLC. <br />A Delaware Limited Liability Company <br />Development Office <br />17780 Collins Avenue Sunny Isles, FL <br />33180 Telephone 305933 -8301 <br />Consultants: <br />I Architect: <br />Cohen Freedman Encinosa & Associates <br />8085 NW 155 Street, Miami Lakes, FL <br />33016 305.826.3999 <br />Planners and Landscape Architect- <br />i ® ereaawumeasavxro,amsrro <br />' wafwroBOUEatX'lMmm rat <br />axax�asss <br />awaea . twaxnrewaar cnas . uawosaau . ov»coesou <br />Civil Engineer: <br />THOMAS CHECCA, P. E. <br />Environmental Consultant <br />11368 NW 73rd Manor, Parkland, FL 33076 <br />Office: 954-344 -6664 <br />Rev: <br />Date: <br />101 1 6 �2 <br />F <br />By: <br />Removed <br />Relocated <br />Palms <br />235 <br />5 <br />Trees' <br />25 <br />0 <br />Estates at Acqualina <br />Sunny Isles, Florida <br />Owner: <br />GSF Acquisition, LLC. <br />A Delaware Limited Liability Company <br />Development Office <br />17780 Collins Avenue Sunny Isles, FL <br />33180 Telephone 305933 -8301 <br />Consultants: <br />I Architect: <br />Cohen Freedman Encinosa & Associates <br />8085 NW 155 Street, Miami Lakes, FL <br />33016 305.826.3999 <br />Planners and Landscape Architect- <br />i ® ereaawumeasavxro,amsrro <br />' wafwroBOUEatX'lMmm rat <br />axax�asss <br />awaea . twaxnrewaar cnas . uawosaau . ov»coesou <br />Civil Engineer: <br />THOMAS CHECCA, P. E. <br />Environmental Consultant <br />11368 NW 73rd Manor, Parkland, FL 33076 <br />Office: 954-344 -6664 <br />Rev: <br />Date: <br />Description: <br />By: <br />,�1 S <br />2014.08Z <br />Response to City Comments <br />MG <br />2 <br />014.08.2E <br />Response to Final Cily Comments <br />MG <br />3 <br />20111 <br />Site Plan Revisions <br />MG <br />4 <br />015.03.2 <br />Response to Initial Comments tar <br />Site Plan Resubmlttal <br />MG <br />5 <br />Sheet Title: <br />TREE DISPOSITION <br />LIST AND <br />RELOCATION NOTES <br />Date: 2014.08.14 Project #: 113158 <br />Drawn By: MGG Scale: AS SHOWN <br />Approved By: <br />c EOSA. Mc <br />Sheet Number: <br />L -1.02 <br />