Laserfiche WebLink
DAVID G. ROMANO, PE <br /> installation for flushing and testing, backfill and compaction following FDOT specifications. The project also included the <br /> removal and replacement of two driveways connecting a shopping center with Pines Boulevard, striping and ADA sidewalk <br /> ramps. This project was executed as time and material, therefore a meticulous tracking of all contractor activities and final <br /> cost estimates was required. <br /> 1.75/Pines Boulevard Bridge Deck Repair, City of Pembroke Pines, Florida—FDOT District 4 <br /> Senior Project Engineer/Project Manager responsible for overseeing the demolition and reconstruction of the concrete <br /> bridge deck on Pines Boulevard (SR-820)over the 1-75 (SR-93) Interchange within the City of Pembroke Pines. <br /> The improvements under this contract consist of the removal and demolition of the existing concrete bridge deck on Pines <br /> Boulevard to a depth of 3.5 inches, or 1/2 inch below the top mat of reinforcing steel, cleaning all exposed reinforcing steel <br /> members of all rust and corrosion, concrete fragments, oil, dirt scale and other coating via means of sandblasting;verify and <br /> check condition of all exposed reinforcing bars to determine if any significant deterioration has occurred,and re-install/splice <br /> new reinforcing steel as necessary; and final placement,casting, and curing of the new concrete overlay deck. <br /> Atlantic Boulevard at Rock Island Road Intersection Improvements, Construction Engineering Inspection — <br /> Broward County, Florida <br /> Senior Project Engineer in charge of the improvements of Atlantic Boulevard at Rock Island Road. The Atlantic Boulevard <br /> and Rock Island Road intersection project consists of the construction of a westbound left turn lane, westbound right tum <br /> lane, and dual left-turn lanes on all four legs of the intersection. In addition, both intersection projects include drainage, <br /> sidewalks, curb &gutter, signalization, signals, roadway widening, milling/resurfacing, and signing and pavement markings, <br /> landscaping, and irrigation improvements. Project length: 0.5 miles. <br /> Hillsboro Boulevard at Military Trail Intersection Improvements, Construction Engineering Inspection (CEI) — <br /> Broward County, Florida <br /> Senior Project Engineer-The Hillsboro Boulevard and Military Trail intersection project consists of widening Military Trail by <br /> the addition of northbound and southbound through lanes. In addition, both intersection projects include drainage, <br /> sidewalks, curb and gutter, signalization, signals, roadway widening, milling/resurfacing, and signing and pavement <br /> markings, landscaping, and irrigation improvements. Project length: 0.8 miles. <br /> Construction Engineering Inspection Oversight for, American Recovery & Reinvestment Act and Local Agency <br /> Projects—Broward County, Florida <br /> Senior Project Engineer for Florida Department of Transportation's Broward Operation Center. The project consists of <br /> monitoring various local agencies throughout Broward County for EEO/AA/DBE compliance to ensure adherence to the <br /> Federal,American Recovery&Reinvestment Act requirements and FDOT Local Agency Program(LAP)specifications. <br /> W. 36th Avenue (from West 76th Street to West 84th Street) Construction Engineering Inspection — City of Hialeah, <br /> Florida; American Recovery&Reinvestment Act <br /> Project Manager— Responsible for overseeing the reconstruction of West 36th Avenue, from West 76th Street to West 84th <br /> Street within the City of Hialeah. The general overview and scope of the project comprised of the complete reconstruction <br /> of West 36th Avenue, including new sidewalk, curb and gutter drainage, improvements - new drainage inlets, 18" storm <br /> sewer cross drainage pipe, 1,271 LF of 18"exfiltration trench (French drain). The project scope also included pavement <br /> milling and resurfacing, signing and pavement markings, street lighting, tree removal, and grading of the adjacent swale <br /> areas and sod restoration with Performance Turf. Project length: 0.5 miles <br /> Pembroke Road and NW 196th Avenue Sidewalk Improvements, Construction Engineering Inspection — City of <br /> Pembroke Pines, Florida;American Recovery& Reinvestment Act <br /> Senior Project Engineer in charge of the City of Pembroke Pines Sidewalk Improvements Project. This project included the <br /> addition of approximately 22,600 LF of sidewalk adjacent to the right-of-way, milling and resurfacing, signing and pavement <br /> markings, and new ADA ramps with detectable warning surfaces. In addition, thickened edge sidewalks with pedestrian <br /> handrails are to be installed where drop off conditions warrant. The project also consisted of drainage improvements, new <br /> curb installation,guardrail removal,grading of adjacent swales and sod restoration, and new landscaping. <br /> W. 53rd Street (from W. 4th Avenue to W. 16th Avenue) Construction Engineering Inspection — City of Hialeah, <br /> Florida; American Recovery& Reinvestment Act <br /> Project Manager/Senior Project Engineer — He was responsible for the West 53rd Street ARRA-Funded reconstruction <br /> projects within the City of Hialeah. The general overview and scope for this project comprised the complete reconstruction <br /> of West 531d Street(from W. 4th Avenue to W. 8th Avenue)including new sidewalk,curb and gutter, drainage improvements- <br /> ® new drainage inlets,18" storm sewer cross drainage pipe, 18" exfiltration trench (French Drain). Proposed in the project <br /> scope are pavement milling and resurfacing, signing and pavement markings, and grading of the adjacent swale areas and <br /> sod restoration with Performance Turf. Project length: 0.5 miles. <br /> HID R.J.Behar SECTION 3 • PAGE j 28 <br /> (MIN PROrn94Nu xeIIIICTUAI a Beall%EMVIW mnrt 4N1Y ROW <br /> I1 Harm wo 4runHLA114N7 NO.124442 <br />