Laserfiche WebLink
• <br /> CONSTRUCTION <br /> MANAGEMENT <br /> Date: 12/31/15 <br /> Request for Change Order (RCO) #30 <br /> Project: Sunny Isles Government Center Repairs - 143915 <br /> • <br /> Scope: Doors' Thresholds at Gov. Center Garage <br /> 1. Provide labor, material, and equipment to perform the following work: <br /> a. Replacement of damaged or improperly installed and/or missing thresholds at <br /> single swing doors and one (1) set of double swing doors at parking garage that <br /> are exposed to the elements. <br /> b. Provide and install new Pemco perimeter silicone seal at all swing doors exposed <br /> to the elements at the parking garage. <br /> c. Provide and install new Pemco bottom seal/sweep at all swing doors exposed to <br /> the elements at parking garage. <br /> d. Provide and install new astragal at double swing doors at west end on 4th floor of <br /> parking garage. <br /> Description Unit Q uantity Unit Cost Total <br /> Installation of New Door Hardware LS 1 $5,952.00 $5,952.00 <br /> General Conditions LS 1 $3,991.00 $3,991.00 <br /> Subtotal $9,943.00 <br /> 15%OH&P $1,491.45 <br /> 1.2% Liability Insurance $0.00 <br /> 1.0% Bond $0.00 <br /> Total Change Order $11,434.45 <br /> GC reserves the right to request an equitable time extension for rescheduling delays, disruption, <br /> acceleration and/or impact in the event this modification changes the construction sequence <br /> and/or time of completion. <br /> The total amount of this change order request is: $11,434.45 <br /> Acceptance to this proposal will enable Contractor to incorporate into prime contract. <br /> SUBMITTED BY: APPROVED BY: <br /> Dan Sanger <br /> • <br /> Lynx Construction Management, LLC. Date Accepted to Proceed <br /> • <br /> J .:J <br />