e.
<br />(1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br /> Hillsboro/Deerfield Beach Restoration, Broward County, FL
<br />
<br />
<br />
<br />
<br />PROFESSIONAL SERVICES CONSTRUCTION (If applicable)
<br />Ongoing 2011
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Coastal engineering and environmental permitting for 550,000 beach fill project. Performed all beach profiles,
<br />hydrographic surveys, aerial photography, magnetometer surveys, and monitoring.
<br />f.
<br />(1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br /> Miamarina at Bayside, Miami, FL
<br />
<br />
<br />
<br />
<br />
<br />PROFESSIONAL SERVICES CONSTRUCTION (If applicable)
<br />1996 1997
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Design and environmental permitting for 130-slip marina. Coastal engineering design including numerical modeling an
<br />physical model tests were conducted for the wave baffle design.
<br />g.
<br />(1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br />Peanut Island Environmental Restoration, Palm Beach County,
<br />FL
<br />
<br />
<br />
<br />
<br />PROFESSIONAL SERVICES CONSTRUCTION (If applicable)
<br />2003 2005
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Coastal/civil and marine structures design for 1.5-acre artificial reef habitat and 1.3 acre shallow seagrass lagoon.
<br />Additional features include a tidal pond and flushing channel, shallow-draft marina with floating docks, pedestrian
<br />boardwalks, and site utility upgrades.
<br />h.
<br />(1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br />Rickenbacker Causeway Recreation Area, Miami-Dade County,
<br />FL
<br />
<br />
<br />
<br />
<br />
<br />PROFESSIONAL SERVICES CONSTRUCTION (If applicable)
<br />2010 2010
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Design of shoreline stabilization and associated public recreation area improvements along 2.5-miles of shoreline of the
<br />Rickenbacker Causeway across Biscayne Bay. Marine resource and hydrographic surveys completed, and coastal
<br />engineering analysis conducted to assess design wave conditions, sediment transport and optimum shoreline
<br />stabilization methods. Design elements included landscaping, invasive species removal with native species restoration,
<br />parking improvements, stormwater management and vendor kiosks for waterfront activities.
<br />i.
<br />(1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br /> Singer Island Sediment Transport Study, Palm Beach County, FL
<br />
<br />
<br />
<br />
<br />
<br />PROFESSIONAL SERVICES CONSTRUCTION (If applicable)
<br />2002 N/A
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Coastal engineering analysis and numerical modeling of shoreline to evaluate shoreline recession/accretion trends
<br />relative to the hard bottom ridges. Utilized Danish Hydraulic Institute (DHI) LITPACK and MIKE 21 numerical
<br />models to simulate waves and sediment transport processes.
<br />
<br />j.
<br />(1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br />Village of Bal Harbour Beach Management, Bal Harbour, FL
<br />
<br />
<br />
<br />
<br />
<br />PROFESSIONAL SERVICES CONSTRUCTION (If applicable)
<br />Ongoing Ongoing
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Reviewed coastal processes and sediment budget at Bakers Haulover Inlet, including the Village shoreline. Evaluated
<br />bypassing alternatives, and prepared conceptual design of inlet bypassing options that could potentially reduce erosion
<br />at the Village, which is located downdrift of the Bakers Haulover Inlet. Additionally, evaluated feasibility of a
<br />bypassing operation with regards to regulatory approval and potential funding sources, including inlet tax district
<br />opportunities.
<br />k.
<br />(1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br />Village of Key Biscayne Beach Nourishment, FL
<br />
<br />
<br />
<br />
<br />
<br />PROFESSIONAL CONSTRUCTION (If applicable)
<br />2012 2012
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Coastal engineering and environmental permitting for 120,000 cy beach fill project. Marine resource and hydrographic
<br />surveys conducted, along with sand source search, jet probes, vibracores, and marine archeological surveys.
<br />
<br />l.
<br />(1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br />32nd Street Hot Spot Breakwaters, Miami Beach, FL
<br />
<br />
<br />
<br />
<br />PROFESSIONAL CONSTRUCTION (If applicable)
<br />2001 2002
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Coastal engineering and numerical modeling for coastal breakwaters and sand recycling project to stabilize shoreline a
<br />hot spot erosional area. Hydrographic surveys and beach profiling performed.
<br />
<br />
|