Laserfiche WebLink
<br />( <br /> <br />Project Phases <br /> <br />Each project will commence upon receipt of an engineering deposit of $22, 680. <br /> <br />Each project will consist of the following phases. <br /> <br />PHASE' <br /> <br />Estimated time frame: 2 months <br /> <br />> Field work <br />> Submit proposed easement areas to the city. The city is responsible to <br />communicate with the property owners and describe and secure the <br />easements from the property owners. <br />> Ballpark estimate provided to the city. <br /> <br />PHASE II <br /> <br />Estimated time frame: 4 months <br /> <br />> City to commence Outreach Plan with Residents <br />> City to submit all Recorded Easements <br />> City to collect customer approval letters <br />> Communication between City and FPL is key in case design changes based <br />on customer requests. <br />> Detail design is performed <br />> Finn estimate provided to the City <br />> Permits obtained (DOT I City) <br /> <br />PHASE III <br /> <br />Estimated time frame: 1 months <br /> <br />> FPL begins Outreach Plan with Customers <br /> <br />PHASE IV <br /> <br />Estimated time frame: 4 months <br /> <br />> Construction phase <br />> FPL Outreach Plan to continue _ <br />> Communication with City on completed sections for customer to UG <br />