Article 3, CONTRACT TIMES, <br />3.1. The work must be substantially completed within 270 calendar days after the date when the <br />Contract Times commence to run pursuant to paragraph 2.03 of the General Conditions. Pursuant <br />to Article 14 of the General Conditions, the Work must be completed and ready for final payment <br />within 300 calendar days after the date when the Contract Times commence to run. The Contract <br />Times will commence to run on the thirtieth (30th) day after the Effective Date of the Agreement or, if <br />a Notice to Proceed is given, on the day indicated in the Notice to Proceed. Pursuant to paragraph <br />2.04 of the General Conditions, the Contractor shall start to perform the Work on date when the <br />Contract Times commence to run. <br />3.1.A. Within Twenty four (24) hours of Adoption of the Resolution awarding the bid and <br />entering into the Agreement with the Contractor, the Owner shall issue a Notice to <br />Proceed authorizing Owner to erect a construction sign for the Work. Within <br />forty -eight (48) hours thereof, the Contractor must erect the construction sign and <br />apply for construction sign payment. Owner shall issue a Notice to Proceed <br />authorizing Contractor to complete the remainder of the Work within thirty (30) <br />days of Adoption of the Resolution. <br />3.2. LIQUIDATED DAMAGES. OWNER and CONTRACTOR recognize that time is of the essence <br />of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the <br />times specified in paragraph 3.1 above, plus any extensions thereof allowed in accordance with <br />Article 12 of the General Conditions. They also recognize the delays, expense and difficulties <br />involved in proving the actual loss suffered by OWNER if the Work is not completed on time. <br />Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as <br />liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER One <br />Thousand Five Hundred and 00/100 dollars ($1500.00) for each day that expires after the time <br />specified in paragraph 3.1 for each Substantial Completion date until the Work is substantially <br />complete. If CONTRACTOR shall neglect, refuse or fail to complete the project by the project <br />completion date within the time specified in paragraph 3.1 for completion and readiness for final <br />payment or any proper extension thereof granted by OWNER, CONTRACTOR shall pay OWNER <br />One Thousand and 00/100 dollars ($1000.00) for each day that expires after the time specified in <br />paragraph 3.1 for completion and readiness for final payment. <br />Article 4. CONTRACT PRICE. <br />OWNER shall pay CONTRACTOR for completion of the Work in accordance with the Contract <br />Documents an amount in current funds equal to the sum of the amounts determined pursuant to <br />paragraphs 4.1 below: <br />FOR A LUMP SUM CONTRACT OF: <br />TOTAL BASE BID (Lump sum, Unit prices, and contingency items) <br />Two Million Eight Hundred Sixty Three Thousands Nine Hundred Fifty Eight and 70/100 <br />cents <br />(use words) ($ 2,863,958.70 ) <br />figures <br />As provided in paragraph 11.03 of the General Conditions estimated quantities are not guaranteed, and <br />determinations of actual quantities and classification are to be made by ENGINEER as provided in <br />paragraph 9.08 of the General Conditions. Unit prices have been computed as provided in paragraph <br />11.03.6 of the General Conditions. <br />Article 5. PAYMENT PROCEDURES. <br />CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General <br />Conditions. Applications for Payment will be processed by ENGINEER as provided in the Genera <br />Conditions. �. <br />March 2007 00500 -2 03- 4122.D ,� <br />