<br />6.02 Labor; Working Hours
<br />
<br />A. CONTRACTOR shall provide competent, suitably
<br />qualified personnel to survey, layout, and construct the
<br />Work as required by the Contract Documents. CON-
<br />TRACTOR shall at all times maintain good discipline and
<br />order at the Site.
<br />
<br />B. Except as otherwise required for the safety or
<br />protection of persons or the Work or property at the Site or
<br />adjacent thereto, and except as otherwise stated in the
<br />Contract Documents, all Work attbe Site shall be performed
<br />during regular working bours, and CONTRACTOR will not
<br />permit overtime work or tile performance of Work on
<br />Saturday, Sunday, or any legal holiday without OWNER's
<br />written consent (which will not be unreasonably withheld)
<br />given after prior written notice to ENGINEER.
<br />
<br />6.03 Services, Ma1erials, aru1 Equipment
<br />
<br />A. Unless otherwise specified in the GeneraJ Re-
<br />quirements, CONTRACTOR shall provide and assume full
<br />responsibility for all services, materials. equipment, labor,
<br />transportation, construction ~ipment and machinery, tools,
<br />appliances, fuel, power, light, heat, telephone, water,
<br />sanitary facilities, temporary facilities, and all otller facilities
<br />and incidentals necessary for the performance, testing,
<br />start-up, and completion of the Work.
<br />
<br />B. All materials and equipment incorporated into the
<br />Work shall be as specified or, if not specified, shall be of
<br />good quality and new, except as otherwise provided in the
<br />Contract Documents. All warranties and guarantees
<br />specifically called for by the Specifications shall expressly
<br />nm to the benefit of OWNER. If required by ENGINEER,
<br />CONTRACfOR shall furnish satisfactory evidence
<br />(Including reports of required tests) as to the source. kind,
<br />and quality of materials and equipment. All materials and
<br />equipment shall be stored, applied, installed, connected,
<br />erected, protected, used, cleaned, and conditioned in
<br />accordance with instructions of the applicable Supplier,
<br />except as. otherwise may be provided in the Contract Docu-
<br />ments ,
<br />
<br />6.04 Progress Schedule
<br />
<br />A. CONTRACTOR shall adhere to the progress schedule
<br />established in accordance with paragraph 2.07 as it may be
<br />adjusted from time to time as provided below.
<br />
<br />1. CONTRACfOR shall &Ubmit to ENGINEER for
<br />acceptance (to the extent indicated in paragraph 2.07)
<br />proposed adjustments in the progress schedule that will
<br />not result in changing the Contract Times (or MilestoneS),
<br />Such adjustments will conform generally to the progress
<br />schedule then in effect and additionally will comply with
<br />
<br />any provisions of lhe General Requirements applicable
<br />thereto ,
<br />
<br />2. Proposed adjustments in the progress schedule
<br />that will change tile Contract Times (or Milestones) shall
<br />be submitted in accordance with the requirements of
<br />Article 12. Such adjustments may only be made by a
<br />Change Order or Wrillen Amendment in accordance with
<br />Article 12.
<br />
<br />6.05 Substitutes and . Or-Equals "
<br />
<br />A, Whenever an item of material or equipment is
<br />specified or described in the Contract Documents by using
<br />the name of a proprietary item or the name of a particular
<br />Supplier, the specification or description is intended to
<br />establish the type, function, appearance, and quality required.
<br />Unless the specification or description contains or is followed
<br />by words reading that no like, equivalent, or "or-equa1" item
<br />or no substitution is permitted, other items of material or
<br />equipment or material or equipment of other Suppliers may
<br />be submitted to ENGINEER for review under tlle circum-
<br />stances described below.
<br />
<br />1. "Or-Equal" Items: If in ENGINEER's sole
<br />discretion an item of material or equipment proposed by
<br />CONTRACTOR is functionally equal to that named and
<br />sufficiently similar so that no change in related Work will
<br />be required, it may be considered by ENGINEER as an
<br />"or-equal" item, in which case review and approval of
<br />the proposed item may, in ENGINEER's sole discretion,
<br />be accomplished without compliance with some or all of
<br />the requirements for approval of proposed substitute
<br />items. For the purposes of this paragraph 6.05.A.I, a
<br />proposed item of material or equipment will be
<br />considered functionally equal to an item so rumled if:
<br />
<br />a. in the exercise of reasonable judgment
<br />ENGINEER determines tlmt: (i) it is at least equal in
<br />quality, durability, appearance, strength, and design
<br />characteristics; (ii) it will. reliably perform at least
<br />equally. well the function imposed by the design
<br />concept of the completed Project as a functioning
<br />whole, and;
<br />
<br />b. CONTRACTOR certifies that: (i) there is no
<br />increase in cost to the OWNER; and (ii) it will
<br />conform substantially, even with deviations, to the
<br />detailed requirements of the item named in the
<br />Contract Documents.
<br />
<br />r 2. Substitute Items
<br />
<br />a. If in ENGINEER's sole discretion an item of
<br />material or equipment proposed by CONTRAcroR
<br />does not qua::fy as an "or-equa1" item under
<br />
<br />00700 p 19
<br />
|