<br />CITY OF SUNNY ISLES BEACH
<br />FOURTH AMENDMENT TO CONSULTANT AGREEMENT
<br />WITH BEISWENGER, HOCH & ASSOCIATES, INC.
<br />CONTRACT NO.: C0708-079
<br />
<br />THIS FOURTH AMENDMENT is made and entered into this _day of 2008, by and
<br />between the CITY OF SUNNY ISLES BEACH, FLORIDA, a municipal corporation of the State of
<br />Florida, (hereinafter referred to as "City") and BEISWENGER, HOCH & ASSOCIATES, INC., a
<br />Florida corporation located at 1190 N.E. 163rd Street, North Miami Beach, Florida 33162, (hereinafter
<br />referred to as "Consultant"), whose Federall.D. # is 59-0751610.
<br />
<br />WHEREAS, pursuant to Resolution No. 2003-628, adopted on December 18, 2003, the City
<br />Commission approved an Agreement with Consultant ("Consultant Agreement"), to provide stormwater
<br />system design, technical assistance and bidding process services for the City's Central Island Drainage
<br />and Street Improvement Project ("Central Island Drainage Project"), in an amount not to exceed One
<br />Hundred Sixty Seven Thousand Forty Dollars ($167,040.00); and
<br />
<br />WHEREAS, pursuant to Resolution No. 2006-1025 adopted on December 14, 2006, the City
<br />Commission approved a First Amendment to the Consultant Agreement to provide the necessary updates
<br />to the existing plans and technical assistance required to incorporate the undergrounding utilities
<br />information for the Central Island Drainage Project, in an amount not to exceed Twenty-Four Thousand
<br />Ten Dollars ($24,010.00); and
<br />
<br />WHEREAS, pursuant to Resolution No. 2008-1202 adopted on January 17, 2008, the City
<br />Commission approved a Second Amendment to the Consultant Agreement to provide additional design
<br />services for the Central Island Drainage Project in order to place curb and gutters to all of the streets for
<br />the Central Island Drainage Project, in an amount not to exceed One Hundred Sixteen Thousand Eight
<br />Hundred Forty Dollars ($116,840.00); and
<br />
<br />WHEREAS, pursuant to Resolution No. 2008-1220 adopted on February 21, 2008, the City
<br />Commission approved a Third Amendment to the Consultant Agreement to provide project management,
<br />engineering testing, and quality control services for the construction of the Central Island Drainage
<br />Project in an amount not to exceed Two Hundred Seventy-Eight Thousand Three Hundred Fifty-Five
<br />Dollars ($278,355.00); and
<br />
<br />WHEREAS, the City is now in need of additional pre-construction and construction engineering
<br />and inspection (CEI) services for the construction of the Central Island Drainage Project to include curb
<br />and guttered streets with increased parking, street lighting, landscaping, and additional improvements to
<br />Gwen Margolis Park; and
<br />
<br />WHEREAS, the Consultant has submitted a proposal dated July 9, 2008, to provide these
<br />additional services for the Central Island Drainage Project, in an amount not to exceed Four Hundred
<br />Thirty-Nine Thousand Nine Hundred Ninety-Five Dollars ($439,995.00), as more fully described in
<br />Attachment "A".
<br />
<br />NOW THEREFORE, in consideration of the premises and the mutual covenants herein stated,
<br />the pal1ies hereto agree as set forth below:
<br />
<br />1. ADDITIONAL SCOPE OF SERVICES: The Consultant shall provide additional services to
<br />include curb and guttered streets with increased parking, street lighting, landscaping, and
<br />additional improvements to Gwen Margolis Park, as more fully described in Attachment "A".
<br />
<br />I
<br />C0708-079 Fourth Amendment - Central Island Drainage
<br />
|