My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Reso 2010-1658
SIBFL
>
City Clerk
>
Resolutions
>
Regular
>
2010
>
Reso 2010-1658
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
6/3/2015 11:22:15 AM
Creation date
12/22/2010 11:09:07 AM
Metadata
Fields
Template:
CityClerk-Resolutions
Resolution Type
Resolution
Resolution Number
2010-1658
Date (mm/dd/yyyy)
12/16/2010
Description
Ground Lease/Dev Agmt/DesignBuild Agmt 4M Inv. Upscale Lifestyle Ctr
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
114
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
<br />15.4 <br /> <br />Final Payment and Acceptance: <br /> <br />15.4.1 If, on the basis of Public Services Director's observation of the Work during <br />construction and final inspection, and Public Services Director's review of the final Application for <br />Payment and accompanying documentation, Public Services Director is satisfied that the Work has <br />been completed in accordance with the Contract Documents and CONTRACTOR'S other <br />obligations under the Contract Documents have been fulfilled, Public Services Director will, within <br />ten (10) days after receipt of the final Application for Payment, indicate in writing Public Services <br />Director's recommendation of payment and present the Application to CITY for payment. <br />Thereupon Public Services Director will give written notice to CITY and CONTRACTOR that the <br />Work is acceptable. Otherwise, Public Services Director will return the Application to <br />CONTRACTOR, indicating in writing the reasons for refusing to recommend final payment, in <br />which case CONTRACTOR shall make the necessary corrections and resubmit the Application. <br />Fifteen (15) days after presentation to CITY of the Application and accompanying documentation, <br />in appropriate form and substance, and with engineer's recommendation and notice of acceptability, <br />the amount recommended by Public Services Director will become due and will be paid by CITY to <br />CONTRACTOR. Payment shall be wire transferred as set forth above. <br /> <br />15.4.2 If, through no fault of CONTRACTOR, final completion of the Work is <br />significantly delayed and if Public Services Director so confirms, CITY shall, upon receipt of <br />CONTRACTOR'S final Application for Payment and recommendation of Public Services Director, <br />and without terminating the Agreement, make payment of the balance due for that portion of the <br />Work fully completed and accepted. If the remaining balance to be held by CITY for Work not <br />fully completed or corrected is less than the retainage stipulated in the Agreement, and if bonds <br />have been furnished as required, the written consent of the surety to the payment of the balance due <br />for that portion of the Work fully completed and accepted shall be submitted by CONTRACTOR to <br />Public Services Director with the Application for such payment. Such payment shall be made <br />under the terms and conditions governing final payment, except that it shall not constitute a waiver <br />of claims. <br /> <br />15.5 Final payment. Final payment, constituting the entire unpaid balance of the <br />Guaranteed Maximum Price, shall be paid by the CITY to the CONTRACTOR when the Work has <br />been completed in accordance with the Contract Documents, this Agreement fully performed, and a <br />final certificate for payment has been issued by the Public Services Director. The making of final <br />payment shall constitute a waiver of claims by CITY except those arising from: <br /> <br />15.5.1 Liens, claims, security interests or encumbrances arising out of this Agreement and <br />unsettled. <br /> <br />15.5.2 Faulty or defective work and latent defects discovered after acceptance. <br /> <br />15.5.3 Failure of the work to comply with the requirements of the Contract Documents. <br /> <br />15.5.4 Terms of special warranties required by the Contract Documents. <br /> <br />29 <br />
The URL can be used to link to this page
Your browser does not support the video tag.