i] <br />11 <br />2.07 Initial Acceptance of Schedules <br />A. At least 10 days before submission of the first <br />Application for Payment a conference attended by <br />Contractor, Engineer, and others as appropriate will be <br />held to review for acceptability to Engineer as provided <br />below the schedules submitted in accordance with <br />Paragraph 2.05.A. Contractor shall have an additional 10 <br />days to make corrections and adjustments and to complete <br />and resubmit the schedules. No progress payment shall be <br />made to Contractor until acceptable schedules are <br />submitted to Engineer. <br />1. The Progress Schedule will be acceptable to <br />Engineer if it provides an orderly progression of the Work <br />to completion within the Contract Times. Such acceptance <br />will not impose on Engineer responsibility for the <br />Progress Schedule, for sequencing, scheduling, or <br />progress of the Work nor interfere with or relieve <br />Contractor from Contractor's frill responsibility therefor. <br />2. Contractor's Schedule of Submittals will be <br />acceptable to Engineer if it provides a workable <br />arrangement for reviewing and processing the required <br />submittals. <br />3. Contractor's Schedule of Values will be <br />acceptable to Engineer as to form and substance if it <br />provides a reasonable allocation of the Contract Price to <br />component parts of the Work. <br />ARTICLE 3 - CONTRACT DOCUMENTS: INTENT, <br />AMENDING, REUSE <br />1 3.01 Intent <br />F� <br />fl <br />A. The Contract Documents are complementary; <br />what is required by one is as binding as if required by all. <br />B. It is the intent of the Contract Documents to <br />describe a functionally complete Project (or part thereof) <br />to be constructed in accordance with the Contract Docu- <br />ments. Any labor, documentation, services, materials, or <br />equipment that may reasonably be inferred from the <br />Contract Documents or from prevailing custom or trade <br />usage as being required to produce the intended result will <br />be provided whether or not specifically called for at no <br />additional cost to Owner. <br />C. Clarifications and interpretations of the <br />Contract Documents shall be issued by Engineer as <br />provided in Article 9. <br />3.02 Reference Standards <br />A. Standards, Specifications, Codes, Laws, and <br />Regulations <br />1. Reference to standards, specifications, <br />manuals, or codes of any technical society, organization, <br />or association, or to Laws or Regulations, whether such <br />reference be specific or by implication, shall mean the <br />standard, specification, manual, code, or Laws or Regula- <br />tions in effect at the time of opening of Bids (or on the <br />Effective Date of the Agreement if there were no Bids), <br />except as may be otherwise specifically stated in the <br />Contract Documents. <br />2. No provision of any such standard, <br />specification, manual or code, or any instruction of a <br />Supplier shall be effective to change the duties or <br />responsibilities of Owner, Contractor, or Engineer, or any <br />of their subcontractors, consultants, agents, or employees <br />from those set forth in the Contract Documents. No such <br />provision or instruction shall be effective to assign to <br />Owner, or Engineer, or any of, their Related Entities, any <br />duty or authority to supervise or direct the performance of <br />the Work or any duty or authority to undertake respon- <br />sibility inconsistent with the provisions of the Contract <br />Documents. <br />3.03 Reporting and Resolving Discrepancies <br />A. Reporting Discrepancies <br />1. Contractor's Review of Contract Documents <br />Before Starting Work: Before undertaking each part of the <br />Work, Contractor shall carefully study and compare the <br />Contract Documents and check and verify pertinent <br />figures therein and all applicable field measurements. <br />Contractor shall promptly report in writing to Engineer <br />any conflict, error, ambiguity, or discrepancy which <br />Contractor may discover and shall obtain a written <br />interpretation or clarification from Engineer before <br />proceeding with any Work affected thereby. <br />2. Contractor's Review of Contract Documents <br />During Performance of Work: If, during the performance <br />of the Work, Contractor discovers any conflict, error, <br />ambiguity, or discrepancy within the Contract Documents <br />or between the Contract Documents and any provision of <br />any Law or Regulation applicable to the performance of <br />the Work or of any standard, specification, manual or <br />code, or of any instruction of any Supplier, Contractor <br />shall promptly report it to Engineer in writing. Contractor <br />shall not proceed with the Work affected thereby (except <br />in an emergency as required by Paragraph 6.16.A) until <br />an amendment or supplement to the Contract Documents <br />has been issued by one of the methods indicated in <br />Paragraph 3.04. <br />EJCDC C -700 Standard General Conditions of the Construction Contract. <br />Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. <br />00700- 10 <br />IDecember 2006 06 -5723 <br />