<br />12.2 No Recovery for Early Completion. If the CONTRACTOR submits a schedule or <br />expresses an intention to complete the Work earlier than any required milestone or completion date, <br />the CITY shall not be liable to the CONTRACTOR for any costs incurred because of delay or <br />hindrance should the CONTRACTOR be unable to complete the Work before such milestone or <br />completion date. The duties, obligations and warranties of the CITY to the CONTRACTOR shall <br />be consistent with and applicable only to the completion of the Work and completion dates set forth <br />in this Agreement. <br /> <br />12.3 Liquidated Damages <br /> <br />12.3.1 The CONTRACTOR understands that ifthe Project or the Work is not substantially <br />completed within Three Hundred Ten (310) days from the date of the Notice to Proceed, then the <br />CITY will suffer damages which are difficult to determine and accurately specify. As such, <br />Liquidated Damages are hereby fixed and agreed upon between the parties, recognizing the <br />impossibility of precisely ascertaining the amount of damages that will be sustained by CITY as a <br />consequence of such delay and both parties desiring to obviate any question of dispute concerning <br />the amount of said damages and the cost and effect of the failure of CONTRACTOR to complete <br />the Contract on time. <br /> <br />12.3.2 Upon failure of CONTRACTOR to complete the Work within the time specified for <br />the substantial completion of the Project (plus approved extensions if any), CONTRACTOR shall <br />pay to CITY the sum of Two Thousand dollars ($2,000.00) for each and every calendar day beyond <br />the time specified in this Agreement for completion, as fixed and agreed liquidated damages and <br />not as a penalty. The Liquidated Damages shall apply regardless of whether or not a single Contract <br />is involved and shall apply separately to each portion of the Work for which a time of completion is <br />given. CITY shall have the right to deduct from and retain out of moneys which may be then due or <br />which may become due and payable to CONTRACTOR, the amount of such liquidated damages <br />and if the amount retained by CITY is insufficient to pay in full such liquidated damages, the <br />CONTRACTOR shall pay in full such liquidated damages. <br /> <br />12.4 Delay. <br /> <br />Any delay caused by the CITY shall extend the date for substantial completion date by the <br />number of days that resulted from the delay. <br /> <br />ARTICLE 13 - CHANGES IN THE WORK, RESTRICTIONS AND LIMITATIONS <br /> <br />13.1 After the Plans and Specifications have been approved for construction by the <br />Building Department, the CITY, without invalidating this Agreement, may order additions, <br />deletions or revisions to the Work. Such additions, deletions or revisions shall be authorized by a <br />Written Amendment or Change Order. <br /> <br />13.2 All Change Orders which, individually or when cumulatively increase the cost of <br />the work, or which extend the time for completion, must be formally authorized and approved by <br />the City Commission prior to their issuance and before work may begin. No claim against CITY <br />for Extra Work in furtherance of such Change Order shall be allowed unless prior approval has <br /> <br />26 <br /> <br />(' i') <br />u .J <br />