<br />3.2.16.8
<br />
<br />3.2.16.9
<br />
<br />3.2.16.10
<br />
<br />3.2.16.11
<br />
<br />3.2.16.12
<br />
<br />3.2.16.13
<br />
<br />The Contractor is responsible for the proper packing,' shipping, handling
<br />and storage (including but not limited to shipment or storage at the
<br />proper temperature and humidity) of materials to be incorporated in the
<br />Work, so as to insure the preservation of the quality and fitness of the
<br />material for proper installation and incorporation in the Work. For
<br />example, but not by way of limitation, Contractor shall,' when:'necessary,
<br />place material on wooden platforms or other hard and clean surfaces
<br />and not on the ground, and place material under cover in any appropriate
<br />shelter or facility. Stored materials or equipment sr~1I be located so as to
<br />facilitate proper inspection. Material and equipment, which is delivered
<br />crated, shall remain crated until ready for installation. Lawns, -grass plots
<br />or other private property shall not be used for storage purposes without
<br />written permission of City or lessee unless otherwise within terms of the
<br />easements obtained by the City.
<br />
<br />The Contractor shall give notice in writing at least 48 hours before
<br />breaking ground, to all persons, Public Utility Companies, public
<br />agencies, government agencies owners of property having structures or
<br />improvements in proximity to site of the Work, superintendents,
<br />inspectors, or those otherwise in charge of propertv, streets, water pipes,
<br />gas pipes, sewer pipes, telephone cables, electric cables, railroads or
<br />otherwise, who may be affected by the Contractor's operation, in order
<br />that they may remove any obstruction for which they are responsible and
<br />have representative on site to see that their property is properly
<br />protected.
<br />
<br />Contractor shall field locate all utilities and acknowledges that all utilities
<br />are not necessarily shown in the Contract Documents, or may be
<br />incorrectly located thereon. The Contractor shall protect all utilities
<br />encountered while performing its work, whether indicated on the Contract
<br />Drawings or not. The Contractor shall maintain utilities in service until
<br />moved or abandoned. The Contractor shall exercise due care when
<br />excavating around utilities and shall restore any damaged utilities to the
<br />same condition or better as existed prior to starting the Work, at no cost
<br />to the City. The Contractor shall maintain operCiting- utilities or other
<br />services, even if they are shown to be abandoned, on the Contract
<br />Drawings, in service until new facilities are provider!, .tested and ready for
<br />use.
<br />
<br />The Contractor shall return all improvements on r;r about the site and
<br />adjacent property which are not shown to be altered, removed or
<br />otherwise changed to conditions which existed prior 1.0 starting work.
<br />
<br />The Contractor shall protect the Work, including uut not limited to, the
<br />site, stored materials and equipment, excavations, and excavated or
<br />stockpiled soil or other material, intended for use in the Work, and shall
<br />take all necessary precautions to prevent or minimize damage to same
<br />or detrimental effect upon performance caused by or due to rain, snow,
<br />ice, run off, floods, temperature, wind, dust, sand alld flying debris.
<br />
<br />The Contractor's superintendent shall take u:: .steps reasonably
<br />necessary to prevent accidents and protect workers, material, equipment
<br />and property.