Laserfiche WebLink
CHANGE ORDER <br />No.5 <br />PROJECT: Newport Fishing Pier Demolition & Construction <br />DATE OF ISSUANCE: 4/6/12 EFFECTIVE DATE: 4/6/12 <br />OWNER: City of Sunny Isles Beach <br />OWNER CONTRACT NO.: 10 -07 -02 <br />CONTRACTOR: Shoreline Foundation, Inc <br />ENGINEER CONTRACT NO.: 11 -4239 <br />ENGINEER: Calvin, Giordano & Associates, Inc. <br />You are directed to make the following changes in the Contract Documents <br />Description: Additional Mob Charge for demo and lest pile installation equipment <br />Reason for Change Order: To expedite project commencement <br />Attachments: SFI CO #1 & #3 <br />CHANGE IN CONTRACT PRICE: <br />CHANGE IN CONTRACT TIMES: <br />Original Contract Price <br />Original Contract Times <br />$3,777,866.00 <br />Substantial Completion: 330 calendar days <br />Ready for final payment: 360 calendar days <br />da s or tlates <br />Net changes from previous Change Orders No. -0- No. -4- <br />Net change from previous Change Orders No. -0- No. -0- <br />$ (818 158.79) <br />0 <br />days <br />Contract Price prior to this Change Order <br />Contract Times prior to this Change Order <br />Substantial Completion: 330 calendar days <br />$2,959,707.21 <br />Ready for final payment: 360 calendar days <br />days or dates <br />Net increase of this Change Order <br />Net Increase of this Change Order <br />$37,605.00 <br />0 <br />days <br />Contract Price with all approved Change Orders <br />Contract Times with all approved Change Orders <br />Substantial Completion: 330 calendar days <br />$2,997,312.21 <br />Ready for final payment: 360 calendar days <br />days or dates <br />RECOMMENDED: APPRDVED: _ ACCEPTED <br />By: By: ' By: <br />Joel Wadsworth AI n Cohe Ito JQ CAIM <br />Calvin, Giordano & Associates, Inc. City of Sunny Isles BeachD Sh eline datio Inc . // <br />Date: Date: ( 0 Dale: 1. I <br />