DEMOLITION/CONSTRUCTION STAGING AND TRAFFIC MANAGEMENT PLANS <br /> h. Tower Crane <br /> Concrete pumps and placement boom <br /> j. Street sweepers <br /> k. Generators and light stands <br /> Truck Route: <br /> • <br /> Material and equipment delivery access will be arriving from Interstate 95 and or US <br /> Highway 1; then along Route 826 East to 163rd Street; turning right on Collins avenue <br /> on to Kings Point Drive. See attached Truck Route as Exhibit A. It is anticipated that all <br /> materials can be stored on the property prior to incorporation into the project. There will <br /> - need to be some coordination of deliveries along Kings Point drive which will be <br /> conducted in accordance with the appropriate permits and approvals procured by the <br /> contractor(s) selected for the project. <br /> In addition, we will have OSHA compliant certified flagmen, (Gate Attendants) at each <br /> gate that will ensure the entering and exiting of all trucks from the site minimizes <br /> disruption to traffic. <br /> Material Storage Location: <br /> We will store materials onsite and within the confines of our construction fence and <br /> within the building throughout the course of the project. <br /> Construction Trailers: <br /> We will have Construction Offices/Trailers onsite. See enclosed Exhibit B, Phased <br /> Logistics Plan, for the proposed location. <br /> Traffic Control: <br /> Sidewalk and lane closures will be required for certain key activities, such as: the <br /> delivery, erection, dismantling, and removal of the tower crane, utility work and <br /> connections. We will follow the required guidelines and submit proper MOT plans and <br /> obtain permits as required during the course of the project. <br /> Parking: <br /> The number of workers will vary during the course of the project, but at peak, we <br /> estimate that we will have approximately 200 individual workers. We will emphasize and <br /> encourage the need to carpool to ensure that there is minimal impact to the areas <br /> available for public parking. We have set aside parking in each phase for construction <br /> .{40589215;1} 7 <br />