the Contract Times will be extended in an amount ARTICLE 13 - TESTS AND INSPECTIONS. <br /> equal to the time lost due to such delay if a Claim is CORRECTION, REMOVAL OR ACCEPTANCE OF <br /> made therefor as provided in Paragraph 12,02.A. DEFECTIVE WORK <br /> Delays beyond the control of Contractor shall <br /> include, but not be limited to, acts or neglect by <br /> Owner, acts or neglect of utility owners or other 13.01 Notice of Defects <br /> contractors performing other work as contemplated <br /> by Article 7, fires, floods, epidemics, abnormal A Prompt notice of all defective Work of <br /> weather conditions,or acts of God. which Owner or Engineer has actual knowledge will <br /> be given to Contractor. All defective Work may be <br /> B. If Owner, Engineer, or other contractors rejected, corrected, or accepted as provided in this <br /> or utility owners performing other work for Owner as Article 13. <br /> contemplated by Article 7, or anyone for whom <br /> Owner is responsible, delays, disrupts, or interferes 13.02 Access to Worn <br /> with the performance or progress of the Work, then <br /> Contractor shall be entitled to an equitable A. Owner, Engineer, their consultants and <br /> adjustment in the Contract Price or the Contract other representatives and personnel of Owner, <br /> Times or both. Contractors entitlement to an independent testing laboratories, and governmental <br /> adjustment of the Contract Times is conditioned on agencies with jurisdictional interests will have access <br /> such adjustment being essential to Contractor's to the Site and the Work at reasonable times for <br /> ability to complete the Work within the Contract their observation, inspecting, and testing Contractor <br /> Times shall provide them proper and safe conditions for <br /> such access and advise them of Contractor's Site <br /> C If Contractor is delayed in the safety procedures and programs so that they may <br /> performance or progress of the Work by fire, flood, comply therewith as applicable. <br /> epidemic, abnormal weather conditions, acts of God. <br /> acts or failures to act of utility owners not under the 13.03 Tests and inspections <br /> control of Owner,or other causes not the fault of and <br /> beyond control of Owner and Contractor, then A. Contractor shall give Engineer timely <br /> Contractor shall be entitled to an equitable notice of readiness of the Work for all required <br /> adjustment in Contract Times, if such adjustment is inspections, tests, or approvals and shall cooperate <br /> essential to Contractors ability to complete the Work with inspection and testing personnel to facilitate <br /> within the Contract Times, Such an adjustment shall required inspections or tests. <br /> be Contractor's sole and exclusive remedy for the <br /> delays described in this Paragraph 12.03.0 B. Owner shall employ and pay for the <br /> services of an independent testing laboratory to <br /> D. Owner.Engineer and the Related Entities perform all inspections, tests, or approvals required <br /> of each of them shall not be liable to Contractor for by the Contract Documents except: <br /> any claims, costs, losses. or damages (including but <br /> not limited to all fees and charges of Engineers, 1, for inspections, tests or approvals <br /> architects, attorneys, and other professionals and all covered by Paragraphs 13 03 C and 13 03 below, <br /> court or arbitration or other dispute resolution costs) <br /> sustained by Contractor on or in connection with any 2. that costs incurred in connection with <br /> other project or anticipated project tests or inspections conducted pursuant to <br /> Paragraph 13 04.8 shall be paid as provided in said <br /> E. Contractor shall not be entitled to an Paragraph 13.04.0,and <br /> adjustment in Contract Price or Contract Times for <br /> delays within the control of Contractor, Delays 3. as otherwise specifically provided in the <br /> attributable to and within the control of a Contract Documents. <br /> Subcontractor or Supplier shall be deemed to be <br /> delays within the control of Contractor C. If Laws or Regulations of any public body <br /> having jurisdiction require any Work (or part thereof) <br /> specifically to be inspected, tested, or approved by <br /> an employee or other representative of such public <br /> body, Contractor shall assume full responsibility for <br /> arranging and obtaining such inspections, tests. or <br /> approvals, pay all costs in connection therewith, and <br /> furnish Engineer the required certificates of inspec- <br /> tion or approval. <br /> EJCDC C-700 Standard General Conditions oil he Construction Contract <br /> Copyright t 2002 National Society of Professional Engineers for EJCi C. 411 rights resen'ed. <br /> 00700.3$ <br /> 03/12 114179 <br />