ill ( HEWETT-KIER CONSTRUCTION, INC. GENERAL CONTRACTORS <br /> JOBSITE SCHEDULING CONTROL <br /> Project Planner, by Primavera software, is used for Hewett-Kier Construction, Inc's schedule <br /> presentation and control. Our scheduling activities for a project include Preliminary Schedules as <br /> well as the more traditional Critical Path Method of construction phase scheduling. Hewett-Kier <br /> Construction Inc. implements a series of scheduling activities which include the Preliminary <br /> Activities Schedule,the Master Project Schedule,Project Cash Flow Schedule, Early Start Schedule, <br /> Responsibility Schedule,Near Critical Activities Schedule and Three-week Lookahead Schedule. <br /> Ultimately,the detailed Critical Path Method Construction Schedule will incorporate all decisions <br /> and activities made during the early phases of the project and will be supplemented by additional <br /> tracking of shop drawings and s.mple submittals via our Submission and Material Control Schedule. <br /> Some features and advantages of our scheduling activities are described as follows. <br /> Preliminary Activities Schedule <br /> ® This schedule identifies the tasks required of the individual project team members and other <br /> consultants and agencies having impact on the related project It establishes the start and completion <br /> dates necessary to have an uninterrupted work flow relative to document development and timely <br /> incorporation of value engineering and constructability reviews into the process. Also, all issues <br /> relating to permits and approvals, financing requirements, long lead time items and special <br /> conditions or requirements of the Owner are addressed to ensure that the start date for construction <br /> is met. <br /> This schedule is used for the purposes: <br /> • As a planning tool to identify all tasks that must be accomplished in order for <br /> construction to begin. <br /> • As a means for identifying ways to reduce the pre-construction time. <br /> • As a way to tell project team members their responsibilities and the date they must <br /> be completed in order for construction to begin without delay. <br /> Master Milestone Schedule <br /> This schedule incorporates preliminary and construction phase scheduling activities into an overall <br /> view of the project based on major milestone events. This format provides an easily understood <br /> overview of progress of the project and is very useful as a management tool for Hewett-Kier <br /> Construction, Inc. and the Owner. It allows Hewett-Kier Construction, Inc. and its subcontractors <br /> to evaluate alternate schemes and approaches to determine their effect on the overall project <br /> duration.Also,on-going schedule analysis allows field management personnel to consider action that <br /> will benefit the project. <br />