Laserfiche WebLink
RFP 18-11-02 Bus Shelter Relocation and Refurbishing <br /> • . <br /> BASE BID SCHEDULE <br /> Item Quantity Unit Unit Price Total Price <br /> Remove Shelters-7 locations,(Heritage Park 2 extra shelters) 9 EA $ 3,000.00 $ 27,000.00 <br /> Clean and repaint shelters 9 EA $ 1,000.00 $ 9,000.00 <br /> Relocate Benches 10 EA $ 400.00 $ 4,000.00 <br /> Relocate Trash Can 7 EA $ 300.00 $ 2,100.00 <br /> Remove pavers and landscape 9 EA $ 1,000.00 $ 9,000.00 <br /> Excavate Pads 21'x5'(6) 630 SF $ 20.00 $ 12,600.00 <br /> Excavate pads 45'x5'(1) 225 SF $ 20.00 $ 4,500.00 <br /> Modifiy Irrigation and Electric lighting 9 EA $ 1,250.00 $ 11,250.00 <br /> Form and pour 21'x5'pads 630 SF $ 25.00 $ 15,750.00 <br /> Form and pour 45'x5'pad(Heritage park,3 shelters combined) 225 SF $ 20.00 $ 4,500.00 <br /> Repair landscaping,mulch and sod as needed 9 EA $ 700.00 $ 6,300.00 <br /> Reinstall Shelters 9 EA $ 5,000.00 $ 45,000.00 <br /> Reinstall benches 10 EA $ 400.00 $ 4,000.00 <br /> Reinstall trash can 7 EA $ 300.00 $ 2,100.00 <br /> Reset Pavers on top of pad(additional pavers supplied by City) 9 EA $ 1,000.00 $ 9,000.00 <br /> Adjust Bus Stop signs as needed 7 EA $ 600.00 $ 4,200.00 <br /> MOT 5%Max. 1 LS $ 10,000.00 $ 10,000.00 <br /> Mobilization 5%Max. 1 LS $ 9,000.00 $ 9,000.00 <br /> Overhead and Profit 1 LS $ 28,000.00 $ 28,000.00 <br /> Restoration of all disturbed areas as a result of the bus shelter removal 9 EA $ 600.00 $ 5,400.00 <br /> TOTAL $ 222,700.00 <br /> 0 <br /> ALTERNATE BID SCHEDULE <br /> Item Quantity Unit Unit Price Total Price <br /> Remove Shelters-6 locations 5 EA $ 3,000.00 $ 15,000.00 <br /> Clean and repaint shelters 5 EA $ 1,000.00 $ 5,000.00 <br /> Relocate Benches 6 EA $ 400.00 $ 2,400.00 <br /> Relocate Trash Can 6 EA $ 300.00 $ 1,800.00 <br /> Remove pavers and landscape 6 EA $ 1,500.00 $ 9,000.00 <br /> Remove 2'retaining wall 25 LF $ 180.00 $ 4,500.00 <br /> Modifiy Irrigation and Electric lighting 2 EA $ 2,500.00 $ 5,000.00 <br /> Construct 2'concrete block retainage wall with 12"x 8"footer 30 LF $ 150.00 $ 4,500.00 <br /> Excavate Pads 21'x5'(6) 630 SF $ 20.00 $ 12,600.00 <br /> Form and pour 21'x5'pads 630 SF $ 25.00 $ 15,750.00 <br /> Repair landscaping,mulch and sod as needed 6 EA $ 700.00 $ 4,200.00 <br /> Reinstall Shelters 5 EA $ 5,000.00 $ , 25,000.00 <br /> Install new shelter(supplied by City) 1 EA $ 5,650.00 $ 5,650.00 <br /> Reinstall benches 6 EA $ 400.00 $ 2,400.00 <br /> Reinstall trash can 6 EA $ 300.00 $ 1,800.00 <br /> Reset Pavers on top of pad(additional pavers supplied by City) 6 EA $ 1,000.00 $ 6,000.00 <br /> Adjust Bus Stop signs as needed 1 EA $ 600.00 $ 600.00 <br /> MOT 5%Max. 1 LS $ 7,000.00 $ 7,000.00 <br /> Mobilization 5%Max. 1 LS $ 7,000.00 $ 7,000.00 <br /> Overhead and Profit 1 LS $ 24,000.00 $ 24,000.00 <br /> )ration of all disturbed areas as a result of the bus shelter removal 5 EA TOTAL $ 159,200.00 <br />