Change Order or Written Amendment approved by the City Commission. <br />13.4 Proposed Change Orders shall be prepared by the CONTRACTOR. <br />13.5 The CONTRACTOR shall not be entitled to an increase in the Guaranteed <br />Maximum Price or an extension of the Contract Time with respect to any work performed that is <br />not required by the Contract Documents as amended, modified and supplemented <br />13.6 If notice of any change affecting the general scope of the work or the provisions of <br />the Contract Documents is required by the provisions of any bond to be given to a surety, the giving <br />of any such notice will be CONTRACTOR'S responsibility and the amount of each applicable bond <br />shall be adjusted accordingly. <br />13.7 Any claim for adjustment in the Guaranteed Maximum Price or time shall be based <br />upon written notice delivered by the party making the claim to the other Parties not later than ten <br />(10) days after the occurrence or event giving rise to the claims and stating the general nature of the <br />claim. No claim for an adjustment in the Guaranteed Maximum Price or an extension of the <br />contract time will be valid if not submitted in accordance with this Paragraph. <br />13.8 CONTRACTOR understands and agrees that any information provided to it by the <br />CITY, at any time, as to any aspect of the Project is not guaranteed. The CONTRACTOR is solely <br />liable for all site conditions, including those that are subsurface or otherwise concealed physical <br />conditions which may differ, materially or not, from those the CONTRACTOR encountered during <br />its initial site inspection. Upon identifying subsurface physical conditions that do differ materially <br />from those identified during the CONTRACTOR'S initial inspection, the CONTRACTOR shall <br />notify CITY immediately. The CONTRACTOR shall promptly investigate such conditions and, if <br />the CITY agrees that the concealed physical conditions could trot have been detected through a <br />reasonable inspection, then the CONTRACTOR shall be entitled to an extension of time for the <br />completion of the Project as its sole remedy. The CONTRACTOR accepts that any costs or <br />expense associated with any differing site conditions encountered shall be the responsibility of the <br />CONTRACTOR and included in the Guaranteed Maximum Price. <br />ARTICLE 14 — NO CHANGES IN GUARANTEED MAXIMUM PRICE <br />14.1 The Guaranteed Maximum Price constitutes the total compensation (subject to <br />authorized adjustments) payable to CONTRACTOR for performing the Work. All duties, <br />responsibilities and obligations assigned to or undertaken by CONTRACTOR shall be at its <br />expense without change in the Guaranteed Maximum Price. <br />14.2 The Guaranteed Maximum Price may only be changed by a Change Order or by a <br />Written Amendment. Any claim for an increase or decrease in the Guaranteed Maximum Price <br />shall be based on written notice delivered to the other Party (but in no event later than ten (10) days) <br />after the occurrence of the event giving rise to the amount of the claim, along with supporting data <br />which shall be delivered within twenty (20) days after the occurrence of the event giving rise to the <br />amount of the claim and shall be accompanied by claimant's written statement that the amount <br />claimed covers all known amounts (direct, indirect and consequential) to which the claimant is <br />27 <br />SIB t ) <br />vr� <br />