HomeMy WebLinkAbout4 - 2.3 ScheduleActivity ID Activity Name Performance % Complete Original Duration Early Start Early Finish Late Start Late Finish Total Float RYDER TRAUMA CENTER FORTIFICATION - Update 3RYDER TRAUMA CENTER FORTIFICATION - Update 37.29%561d 21-Nov-14 11-Feb-16 30-Sep-14 11-Feb-16 0d 01400.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d 01401.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d 01402.00 ADVERSE WEATHER DAYS 100%2d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d 01403.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d 01404.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d 01405.00 ADVERSE WEATHER DAYS 100%2d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d 01406.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d 01407.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d 01408.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d 09200.00 FRAMING MATERIALS DELIVERED 100%1d 21-Nov-14 20-Nov-14 09-Oct-14 08-Oct-14 -31d 09202.00 FRAMING DELAY 100%23d 21-Nov-14 11-Feb-16 09-Oct-14 11-Feb-16 0d 06210.00 REPLACEMENT OF DAMAGED SHEATHING 100%5d 04-Dec-14 03-Dec-14 09-Oct-14 08-Oct-14 -38d 07200.00 INSTALLATION OF VISQUEEN 100%5d 04-Dec-14 03-Dec-14 09-Oct-14 08-Oct-14 -38d 09900.00 PREP/PAINT STEEL ANGLES 100%5d 04-Dec-14 03-Dec-14 09-Oct-14 08-Oct-14 -38d 09201.00 READY TO COMMENCE FRAMING 100%0d COMMENCEMENTCOMMENCEMENT 33.47%557d 21-Nov-14 11-Feb-16 30-Sep-14 11-Feb-16 0d 01000.00 OBTAIN EXECUTED CONTRACT 100%5d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d 01005.00 BUY-OUTS & SUBCONTRACTS 100%39d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d 01010.00 OBTAIN PERMIT 100%44d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d 01015.00 RE-LOCATE HELI-PAD TO GROUND (BY OTHERS) 100%44d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d 01030.00 CHANGE ORDERS 15.95%370d 21-Nov-14 11-Feb-16 30-Sep-14 11-Feb-16 0d 01050.00 MOBILIZATION 100%5d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d 01020.00 NOTICE TO PROCEED 100%0d SUBMITTALS & PROCUREMENTSUBMITTALS & PROCUREMENT 10.24%294d 21-Nov-14 17-Apr-15 30-Sep-14 11-Sep-15 105d PREPARE/SUBMITPREPARE/SUBMIT 75.79%214d 21-Nov-14 22-Dec-14 30-Sep-14 17-Aug-15 168d 01800-A PREPARE/SUBMIT - SITE PLAN 100%10d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d 02810-A PREPARE/SUBMIT - LAWN IRRIGATION 70%10d 21-Nov-14 25-Nov-14 05-Aug-15 07-Aug-15 175d 02820-A PREPARE/SUBMIT - FENCING 0%10d 21-Nov-14 08-Dec-14 04-Aug-15 17-Aug-15 174d 02900-A PREPARE/SUBMIT - LANDSCAPING 0%10d 21-Nov-14 08-Dec-14 16-Jul-15 29-Jul-15 161d 03300-A PREPARE/SUBMIT - CONCRETE 100%10d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d 03310-A PREPARE/SUBMIT - REBAR 100%20d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d 04200-A PREPARE/SUBMIT - MASONRY 100%10d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d 05200-A PREPARE/SUBMIT - STRUCTURAL STEEL 80%20d 21-Nov-14 26-Nov-14 08-Apr-15 13-Apr-15 92d Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F MarApr 2014 2015 2016 12-Feb-16, RYDER TRAUMA CENTER FORTIFICATION - Update 3 ADVERSE WEATHER DAY ADVERSE WEATHER DAY ADVERSE WEATHER DAYS ADVERSE WEATHER DAY ADVERSE WEATHER DAY ADVERSE WEATHER DAYS ADVERSE WEATHER DAY ADVERSE WEATHER DAY ADVERSE WEATHER DAY FRAMING MATERIALS DELIVERED FRAMING DELAY REPLACEMENT OF DAMAGED SHEATHING INSTALLATION OF VISQUEEN PREP/PAINT STEEL ANGLES READY TO COMMENCE FRAMING, 15-Oct-14 A, 04-Feb-16, COMMENCEMENT OBTAIN EXECUTED CONTRACT BUY-OUTS & SUBCONTRACTS OBTAIN PERMIT RE-LOCATE HELI-PAD TO GROUND (BY OTHERS) CHANGE ORDERS MOBILIZATION NOTICE TO PROCEED, 01-Sep-14 A, 15-Apr-15, SUBMITTALS & PROCUREMENT 22-Dec-14, PREPARE/SUBMIT PREPARE/SUBMIT - SITE PLAN PREPARE/SUBMIT - LAWN IRRIGATION PREPARE/SUBMIT - FENCING PREPARE/SUBMIT - LANDSCAPING PREPARE/SUBMIT - CONCRETE PREPARE/SUBMIT - REBAR PREPARE/SUBMIT - MASONRY PREPARE/SUBMIT - STRUCTURAL STEEL Actual Level of Effort Actual Work Remaining Work Critical Remaining Work START DATE 06-Dec-13, FINISH DATE 12-Feb-16 DATA DATE 21-Nov-14, RUN DATE 25-Aug-17 PAGE 1 OF 26 Activity ID Activity Name Performance % Complete Original Duration Early Start Early Finish Late Start Late Finish Total Float 05400-A PREPARE/SUBMIT - MISC. METALS 90%20d 21-Nov-14 24-Nov-14 13-Apr-15 14-Apr-15 95d 07240-A PREPARE/SUBMIT - EIFS 100%10d 21-Nov-14 20-Nov-14 01-Oct-14 30-Sep-14 -37d 07410-A PREPARE/SUBMIT - METAL PANELS 0%20d 21-Nov-14 22-Dec-14 05-Mar-15 01-Apr-15 68d 07500-A PREPARE/SUBMIT - ROOFING 30%20d 21-Nov-14 12-Dec-14 13-Apr-15 30-Apr-15 95d 08200-A PREPARE/SUBMIT - H.M. DOORS & FRAMES 100%10d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d 08300-A PREPARE/SUBMIT - OVERHEAD DOORS 100%10d 21-Nov-14 20-Nov-14 30-Jul-15 29-Jul-15 171d 08400-A PREPARE/SUBMIT - AUTOMATIC DOORS 100%10d 21-Nov-14 20-Nov-14 14-May-15 13-May-15 118d 08500-A PREPARE/SUBMIT - GLASS & GLAZING 100%10d 21-Nov-14 20-Nov-14 15-Oct-14 14-Oct-14 -27d 08700-A PREPARE/SUBMIT - FINISH HARDWARE 100%10d 21-Nov-14 20-Nov-14 13-Oct-14 10-Oct-14 -29d 09100-A PREPARE/SUBMIT - PLASTER & STUCCO 100%10d 21-Nov-14 20-Nov-14 08-Oct-14 07-Oct-14 -32d 09250-A PREPARE/SUBMIT - DRYWALL 100%10d 21-Nov-14 20-Nov-14 13-Nov-14 12-Nov-14 -6d 09300-A PREPARE/SUBMIT - TILE 100%10d 21-Nov-14 20-Nov-14 14-May-15 13-May-15 118d 09510-A PREPARE/SUBMIT - ACOUSTICAL CEILINGS 0%10d 21-Nov-14 08-Dec-14 29-Jan-15 11-Feb-15 43d 09650-A PREPARE/SUBMIT - RESILIENT FLOORING 100%10d 21-Nov-14 20-Nov-14 23-Jul-15 22-Jul-15 166d 09900-A PREPARE/SUBMIT - PAINTING 90%10d 21-Nov-14 21-Nov-14 14-Nov-14 14-Nov-14 -5d 10400-A PREPARE/SUBMIT - SIGNS 100%10d 21-Nov-14 20-Nov-14 01-Oct-14 30-Sep-14 -37d 10700-A PREPARE/SUBMIT - LOUVERS 100%10d 21-Nov-14 20-Nov-14 24-Oct-14 23-Oct-14 -20d 12490-A PREPARE/SUBMIT - BLINDS 100%10d 21-Nov-14 20-Nov-14 15-Oct-14 14-Oct-14 -27d 13200-A PREPARE/SUBMIT - SAFETY NET (HELI-PAD)0%20d 21-Nov-14 22-Dec-14 13-May-15 10-Jun-15 117d 15300-A PREPARE/SUBMIT - FIRE PROTECTION 100%20d 21-Nov-14 20-Nov-14 29-Dec-14 24-Dec-14 22d 15400-A PREPARE/SUBMIT - PLUMBING 100%20d 21-Nov-14 20-Nov-14 08-Oct-14 07-Oct-14 -32d 15800-A PREPARE/SUBMIT - HVAC 100%20d 21-Nov-14 20-Nov-14 09-Jan-15 08-Jan-15 29d 16100-A PREPARE/SUBMIT - ELECTRICAL 100%20d 21-Nov-14 20-Nov-14 28-Jan-15 27-Jan-15 42d ARCHITECT - REVIEW/APPROVEARCHITECT - REVIEW/APPROVE 97.61%224d 21-Nov-14 09-Jan-15 30-Sep-14 31-Aug-15 166d 01800-B ARCHITECT REVIEW/APPROVE - SITE PLAN 100%10d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d 03300-B ARCHITECT REVIEW/APPROVE - CONCRETE 100%15d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d 03310-B ARCHITECT REVIEW/APPROVE - REBAR 100%15d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d 04200-B ARCHITECT REVIEW/APPROVE - MASONRY 100%10d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d 07240-B ARCHITECT REVIEW/APPROVE - EIFS 100%10d 21-Nov-14 20-Nov-14 01-Oct-14 30-Sep-14 -37d 08200-B ARCHITECT REVIEW/APPROVE - H.M. DOORS & FRAMES 90%10d 21-Nov-14 21-Nov-14 30-Sep-14 30-Sep-14 -38d 08300-B ARCHITECT REVIEW/APPROVE - OVERHEAD DOORS 90%10d 21-Nov-14 21-Nov-14 30-Jul-15 30-Jul-15 171d 08400-B ARCHITECT REVIEW/APPROVE - AUTOMATIC DOORS 100%10d 21-Nov-14 20-Nov-14 14-May-15 13-May-15 118d 08500-B ARCHITECT REVIEW/APPROVE - GLASS & GLAZING 100%10d 21-Nov-14 20-Nov-14 15-Oct-14 14-Oct-14 -27d 08700-B ARCHITECT REVIEW/APPROVE - FINISH HARDWARE 90%10d 21-Nov-14 21-Nov-14 13-Oct-14 13-Oct-14 -29d Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F MarApr 2014 2015 2016 PREPARE/SUBMIT - MISC. METALS PREPARE/SUBMIT - EIFS PREPARE/SUBMIT - METAL PANELS PREPARE/SUBMIT - ROOFING PREPARE/SUBMIT - H.M. DOORS & FRAMES PREPARE/SUBMIT - OVERHEAD DOORS PREPARE/SUBMIT - AUTOMATIC DOORS PREPARE/SUBMIT - GLASS & GLAZING PREPARE/SUBMIT - FINISH HARDWARE PREPARE/SUBMIT - PLASTER & STUCCO PREPARE/SUBMIT - DRYWALL PREPARE/SUBMIT - TILE PREPARE/SUBMIT - ACOUSTICAL CEILINGS PREPARE/SUBMIT - RESILIENT FLOORING PREPARE/SUBMIT - PAINTING PREPARE/SUBMIT - SIGNS PREPARE/SUBMIT - LOUVERS PREPARE/SUBMIT - BLINDS PREPARE/SUBMIT - SAFETY NET (HELI-PAD) PREPARE/SUBMIT - FIRE PROTECTION PREPARE/SUBMIT - PLUMBING PREPARE/SUBMIT - HVAC PREPARE/SUBMIT - ELECTRICAL 07-Jan-15, ARCHITECT - REVIEW/APPROVE ARCHITECT REVIEW/APPROVE - SITE PLAN ARCHITECT REVIEW/APPROVE - CONCRETE ARCHITECT REVIEW/APPROVE - REBAR ARCHITECT REVIEW/APPROVE - MASONRY ARCHITECT REVIEW/APPROVE - EIFS ARCHITECT REVIEW/APPROVE - H.M. DOORS & FRAMES ARCHITECT REVIEW/APPROVE - OVERHEAD DOORS ARCHITECT REVIEW/APPROVE - AUTOMATIC DOORS ARCHITECT REVIEW/APPROVE - GLASS & GLAZING ARCHITECT REVIEW/APPROVE - FINISH HARDWARE Actual Level of Effort Actual Work Remaining Work Critical Remaining Work START DATE 06-Dec-13, FINISH DATE 12-Feb-16 DATA DATE 21-Nov-14, RUN DATE 25-Aug-17 PAGE 2 OF 26 Activity ID Activity Name Performance % Complete Original Duration Early Start Early Finish Late Start Late Finish Total Float 09100-B ARCHITECT REVIEW/APPROVE - PLASTER & STUCCO 60%10d 21-Nov-14 26-Nov-14 08-Oct-14 13-Oct-14 -32d 09250-B ARCHITECT REVIEW/APPROVE - DRYWALL 100%10d 21-Nov-14 20-Nov-14 13-Nov-14 12-Nov-14 -6d 09300-B ARCHITECT REVIEW/APPROVE - TILE 50%10d 21-Nov-14 01-Dec-14 14-May-15 20-May-15 118d 09650-B ARCHITECT REVIEW/APPROVE - RESILIENT FLOORING 50%10d 21-Nov-14 01-Dec-14 23-Jul-15 29-Jul-15 166d 10400-B ARCHITECT REVIEW/APPROVE - SIGNS 100%10d 21-Nov-14 20-Nov-14 01-Oct-14 30-Sep-14 -37d 10700-B ARCHITECT REVIEW/APPROVE - LOUVERS 100%10d 21-Nov-14 20-Nov-14 24-Oct-14 23-Oct-14 -20d 12490-B ARCHITECT REVIEW/APPROVE - BLINDS 100%10d 21-Nov-14 20-Nov-14 15-Oct-14 14-Oct-14 -27d 15300-B ARCHITECT REVIEW/APPROVE - FIRE PROTECTION 100%15d 21-Nov-14 20-Nov-14 29-Dec-14 24-Dec-14 22d 15400-B ARCHITECT REVIEW/APPROVE - PLUMBING 100%15d 21-Nov-14 20-Nov-14 08-Oct-14 07-Oct-14 -32d 15800-B ARCHITECT REVIEW/APPROVE - HVAC 100%15d 21-Nov-14 20-Nov-14 09-Jan-15 08-Jan-15 29d 16100-B ARCHITECT REVIEW/APPROVE - ELECTRICAL 100%15d 21-Nov-14 20-Nov-14 28-Jan-15 27-Jan-15 42d 09900-B ARCHITECT REVIEW/APPROVE - PAINTING 90%10d 24-Nov-14 24-Nov-14 17-Nov-14 17-Nov-14 -5d 02810-B ARCHITECT REVIEW/APPROVE - LAWN IRRIGATION 70%10d 26-Nov-14 02-Dec-14 10-Aug-15 12-Aug-15 175d 05400-B ARCHITECT REVIEW/APPROVE - MISC. METALS 86.67%15d 03-Dec-14 04-Dec-14 21-Apr-15 22-Apr-15 95d 05200-B ARCHITECT REVIEW/APPROVE - STRUCTURAL STEEL 80%15d 05-Dec-14 09-Dec-14 20-Apr-15 22-Apr-15 92d 02820-B ARCHITECT REVIEW/APPROVE - FENCING 0%10d 09-Dec-14 22-Dec-14 18-Aug-15 31-Aug-15 174d 02900-B ARCHITECT REVIEW/APPROVE - LANDSCAPING 0%10d 09-Dec-14 22-Dec-14 30-Jul-15 12-Aug-15 161d 09510-B ARCHITECT REVIEW/APPROVE - ACOUSTICAL CEILINGS 0%10d 09-Dec-14 22-Dec-14 12-Feb-15 25-Feb-15 43d 07500-B ARCHITECT REVIEW/APPROVE - ROOFING 26.67%15d 16-Dec-14 05-Jan-15 04-May-15 18-May-15 95d 07410-B ARCHITECT REVIEW/APPROVE - METAL PANELS 0%10d 23-Dec-14 09-Jan-15 02-Apr-15 15-Apr-15 68d 13200-B ARCHITECT REVIEW/APPROVE - SAFETY NET (HELI-PAD) 0%10d 23-Dec-14 09-Jan-15 11-Jun-15 24-Jun-15 117d CONSULTANT - REVIEW/APPROVECONSULTANT - REVIEW/APPROVE 0%147d 21-Nov-14 23-Dec-14 02-Oct-14 20-May-15 104d 03300-C CONSULTANT REVIEW/APPROVE - CONCRETE 100%10d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d 03310-C CONSULTANT REVIEW/APPROVE - REBAR 100%10d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d 04200-C CONSULTANT REVIEW/APPROVE - MASONRY 100%10d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d 15300-C CONSULTANT REVIEW/APPROVE - FIRE PROTECTION 100%10d 21-Nov-14 20-Nov-14 29-Dec-14 24-Dec-14 22d 15400-C CONSULTANT REVIEW/APPROVE - PLUMBING 100%10d 21-Nov-14 20-Nov-14 08-Oct-14 07-Oct-14 -32d 15800-C CONSULTANT REVIEW/APPROVE - HVAC 100%10d 21-Nov-14 20-Nov-14 09-Jan-15 08-Jan-15 29d 16100-C CONSULTANT REVIEW/APPROVE - ELECTRICAL 100%10d 21-Nov-14 20-Nov-14 28-Jan-15 27-Jan-15 42d 05400-C CONSULTANT REVIEW/APPROVE - MISC. METALS 90%10d 25-Nov-14 25-Nov-14 15-Apr-15 15-Apr-15 95d 05200-C CONSULTANT REVIEW/APPROVE - STRUCTURAL STEEL 80%10d 01-Dec-14 02-Dec-14 14-Apr-15 15-Apr-15 92d 07500-C CONSULTANT REVIEW/APPROVE - ROOFING 30%10d 15-Dec-14 23-Dec-14 01-May-15 11-May-15 95d FAB/DELIVERFAB/DELIVER 6.8%201d 21-Nov-14 17-Apr-15 01-Oct-14 11-Sep-15 105d 03300-D FAB/DELIVER - CONCRETE 100%1d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F MarApr 2014 2015 2016 ARCHITECT REVIEW/APPROVE - PLASTER & STUCCO ARCHITECT REVIEW/APPROVE - DRYWALL ARCHITECT REVIEW/APPROVE - TILE ARCHITECT REVIEW/APPROVE - RESILIENT FLOORING ARCHITECT REVIEW/APPROVE - SIGNS ARCHITECT REVIEW/APPROVE - LOUVERS ARCHITECT REVIEW/APPROVE - BLINDS ARCHITECT REVIEW/APPROVE - FIRE PROTECTION ARCHITECT REVIEW/APPROVE - PLUMBING ARCHITECT REVIEW/APPROVE - HVAC ARCHITECT REVIEW/APPROVE - ELECTRICAL ARCHITECT REVIEW/APPROVE - PAINTING ARCHITECT REVIEW/APPROVE - LAWN IRRIGATION ARCHITECT REVIEW/APPROVE - MISC. METALS ARCHITECT REVIEW/APPROVE - STRUCTURAL STEEL ARCHITECT REVIEW/APPROVE - FENCING ARCHITECT REVIEW/APPROVE - LANDSCAPING ARCHITECT REVIEW/APPROVE - ACOUSTICAL CEILINGS ARCHITECT REVIEW/APPROVE - ROOFING ARCHITECT REVIEW/APPROVE - METAL PANELS ARCHITECT REVIEW/APPROVE - SAFETY NET (HELI-PAD) 23-Dec-14, CONSULTANT - REVIEW/APPROVE CONSULTANT REVIEW/APPROVE - CONCRETE CONSULTANT REVIEW/APPROVE - REBAR CONSULTANT REVIEW/APPROVE - MASONRY CONSULTANT REVIEW/APPROVE - FIRE PROTECTION CONSULTANT REVIEW/APPROVE - PLUMBING CONSULTANT REVIEW/APPROVE - HVAC CONSULTANT REVIEW/APPROVE - ELECTRICAL CONSULTANT REVIEW/APPROVE - MISC. METALS CONSULTANT REVIEW/APPROVE - STRUCTURAL STEEL CONSULTANT REVIEW/APPROVE - ROOFING 15-Apr-15, FAB/DELIVER FAB/DELIVER - CONCRETE Actual Level of Effort Actual Work Remaining Work Critical Remaining Work START DATE 06-Dec-13, FINISH DATE 12-Feb-16 DATA DATE 21-Nov-14, RUN DATE 25-Aug-17 PAGE 3 OF 26 Activity ID Activity Name Performance % Complete Original Duration Early Start Early Finish Late Start Late Finish Total Float 03310-D FAB/DELIVER - REBAR 100%15d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d 04200-D FAB/DELIVER - MASONRY 100%5d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d 07240-D FAB/DELIVER - EIFS 0%10d 21-Nov-14 08-Dec-14 01-Oct-14 14-Oct-14 -37d 08400-D FAB/DELIVER - AUTOMATIC DOORS 0%60d 21-Nov-14 20-Feb-15 14-May-15 07-Aug-15 118d 08500-D FAB/DELIVER - GLASS & GLAZING 100%60d 21-Nov-14 20-Nov-14 15-Oct-14 14-Oct-14 -27d 09250-D FAB/DELIVER - DRYWALL 0%5d 21-Nov-14 01-Dec-14 13-Nov-14 19-Nov-14 -6d 10400-D FAB/DELIVER - SIGNS 0%100d 21-Nov-14 17-Apr-15 01-Oct-14 25-Feb-15 -37d 10700-D FAB/DELIVER - LOUVERS 60%30d 21-Nov-14 10-Dec-14 24-Oct-14 10-Nov-14 -20d 12490-D FAB/DELIVER - BLINDS 0%30d 21-Nov-14 09-Jan-15 15-Oct-14 25-Nov-14 -27d 15300-D FAB/DELIVER - FIRE PROTECTION 0%40d 21-Nov-14 23-Jan-15 29-Dec-14 24-Feb-15 22d 15400-D FAB/DELIVER - PLUMBING 5%40d 21-Nov-14 21-Jan-15 08-Oct-14 02-Dec-14 -32d 15800-D FAB/DELIVER - HVAC 0%30d 21-Nov-14 09-Jan-15 09-Jan-15 19-Feb-15 29d 16100-D FAB/DELIVER - ELECTRICAL 50%40d 21-Nov-14 22-Dec-14 28-Jan-15 24-Feb-15 42d 08200-D FAB/DELIVER - H.M. DOORS & FRAMES 0%18d 24-Nov-14 19-Dec-14 01-Oct-14 24-Oct-14 -38d 08300-D FAB/DELIVER - OVERHEAD DOORS 0%30d 24-Nov-14 12-Jan-15 31-Jul-15 11-Sep-15 171d 08700-D FAB/DELIVER - FINISH HARDWARE 0%20d 24-Nov-14 23-Dec-14 14-Oct-14 10-Nov-14 -29d 09900-D FAB/DELIVER - PAINTING 0%5d 25-Nov-14 03-Dec-14 18-Nov-14 24-Nov-14 -5d 09100-D FAB/DELIVER - PLASTER & STUCCO 0%10d 01-Dec-14 12-Dec-14 14-Oct-14 27-Oct-14 -32d 09300-D FAB/DELIVER - TILE 0%10d 02-Dec-14 15-Dec-14 21-May-15 04-Jun-15 118d 09650-D FAB/DELIVER - RESILIENT FLOORING 0%10d 02-Dec-14 15-Dec-14 30-Jul-15 12-Aug-15 166d 02810-D FAB/DELIVER - LAWN IRRIGATION 0%10d 03-Dec-14 16-Dec-14 13-Aug-15 26-Aug-15 175d 05400-D FAB/DELIVER - MISC. METALS 0%25d 05-Dec-14 14-Jan-15 23-Apr-15 28-May-15 95d 05200-D FAB/DELIVER - STRUCTURAL STEEL 0%25d 10-Dec-14 19-Jan-15 23-Apr-15 28-May-15 92d 02820-D FAB/DELIVER - FENCING 0%5d 23-Dec-14 02-Jan-15 01-Sep-15 08-Sep-15 174d 02900-D FAB/DELIVER - LANDSCAPING 0%10d 23-Dec-14 09-Jan-15 13-Aug-15 26-Aug-15 161d 09510-D FAB/DELIVER - ACOUSTICAL CEILINGS 0%5d 23-Dec-14 02-Jan-15 26-Feb-15 04-Mar-15 43d 07500-D FAB/DELIVER - ROOFING 0%15d 06-Jan-15 26-Jan-15 19-May-15 09-Jun-15 95d 07410-D FAB/DELIVER - METAL PANELS 0%50d 12-Jan-15 20-Mar-15 16-Apr-15 25-Jun-15 68d 13200-D FAB/DELIVER - SAFETY NET (HELI-PAD)0%5d 12-Jan-15 16-Jan-15 25-Jun-15 01-Jul-15 117d CONSTRUCTION CONFERENCESCONSTRUCTION CONFERENCES 0%312d 21-Nov-14 19-Nov-15 01-Oct-14 28-Sep-15 -38d 01600.00 WASTE MANAGEMENT CONFERENCE 100%1d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d 02000.00 DEMOLITION CONFERENCE 100%1d 21-Nov-14 20-Nov-14 01-Oct-14 30-Sep-14 -37d 03000.00 CUTTING & PATCHING CONFERENCE 0%1d 21-Nov-14 21-Nov-14 01-Oct-14 01-Oct-14 -37d 08500.00 GLAZING & AUTO DOORS CONFERENCE 0%1d 21-Nov-14 21-Nov-14 14-Oct-14 14-Oct-14 -28d Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F MarApr 2014 2015 2016 FAB/DELIVER - REBAR FAB/DELIVER - MASONRY FAB/DELIVER - EIFS FAB/DELIVER - AUTOMATIC DOORS FAB/DELIVER - GLASS & GLAZING FAB/DELIVER - DRYWALL FAB/DELIVER - SIGNS FAB/DELIVER - LOUVERS FAB/DELIVER - BLINDS FAB/DELIVER - FIRE PROTECTION FAB/DELIVER - PLUMBING FAB/DELIVER - HVAC FAB/DELIVER - ELECTRICAL FAB/DELIVER - H.M. DOORS & FRAMES FAB/DELIVER - OVERHEAD DOORS FAB/DELIVER - FINISH HARDWARE FAB/DELIVER - PAINTING FAB/DELIVER - PLASTER & STUCCO FAB/DELIVER - TILE FAB/DELIVER - RESILIENT FLOORING FAB/DELIVER - LAWN IRRIGATION FAB/DELIVER - MISC. METALS FAB/DELIVER - STRUCTURAL STEEL FAB/DELIVER - FENCING FAB/DELIVER - LANDSCAPING FAB/DELIVER - ACOUSTICAL CEILINGS FAB/DELIVER - ROOFING FAB/DELIVER - METAL PANELS FAB/DELIVER - SAFETY NET (HELI-PAD) 19-Nov-15, CONSTRUCTION CONFERENCES WASTE MANAGEMENT CONFERENCE DEMOLITION CONFERENCE CUTTING & PATCHING CONFERENCE GLAZING & AUTO DOORS CONFERENCE Actual Level of Effort Actual Work Remaining Work Critical Remaining Work START DATE 06-Dec-13, FINISH DATE 12-Feb-16 DATA DATE 21-Nov-14, RUN DATE 25-Aug-17 PAGE 4 OF 26 Activity ID Activity Name Performance % Complete Original Duration Early Start Early Finish Late Start Late Finish Total Float 09250.00 GYPSUM ASSEMBLIES CONFERENCE 0%1d 02-Dec-14 02-Dec-14 20-Nov-14 20-Nov-14 -6d 07900.00 FIREPROOFING CONFERENCE 0%1d 05-Dec-14 05-Dec-14 10-Nov-14 10-Nov-14 -17d 07240.00 EIFS CONFERENCE 0%1d 09-Dec-14 09-Dec-14 15-Oct-14 15-Oct-14 -37d 08200.00 DOOR/FRAME & HARDWARE CONFERENCE 0%1d 19-Dec-14 19-Dec-14 24-Oct-14 24-Oct-14 -38d 15000.00 MEP CONFERENCE 0%1d 22-Jan-15 22-Jan-15 03-Dec-14 03-Dec-14 -32d 07500.00 ROOFING CONFERENCE 0%1d 27-Jan-15 27-Jan-15 10-Jun-15 10-Jun-15 95d 07410.00 COMPOSITE WALL PANELS CONFERENCE 0%1d 23-Mar-15 23-Mar-15 26-Jun-15 26-Jun-15 68d 02100.00 SITEWORK CONFERENCE 0%1d 22-Jun-15 22-Jun-15 09-Jul-15 09-Jul-15 12d 01900.00 DEMONSTRATION & TRAINING CONFERENCE 0%1d 19-Nov-15 19-Nov-15 28-Sep-15 28-Sep-15 -38d EXTERIOREXTERIOR 5.88%255d 21-Nov-14 02-Sep-15 30-Sep-14 21-Sep-15 13d PHASE 1PHASE 1 20.35%93d 21-Nov-14 19-Jan-15 30-Sep-14 18-Nov-14 -40d 01530.01PROVIDE PROTECTED PERSONNEL/GUERNEY ACCESS 100%2d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d 01540.01MOBILIZE CREWS/EQUIP. - PHASE 1 100%2d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d 01550.01INSTALL SCAFFOLDING - PHASE 1 100%10d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d 02930.01REMOVE/RELOCATE TREES - PHASE 1 40%5d 21-Nov-14 25-Nov-14 30-Sep-14 02-Oct-14 -38d 04200.01MASONRY WALL REINFORCEMENT - PHASE 1 30%10d 21-Nov-14 03-Dec-14 02-Oct-14 10-Oct-14 -36d 02000.01SELECTIVE DEMOLITION - PHASE 1 91.67%12d 25-Nov-14 25-Nov-14 02-Oct-14 02-Oct-14 -38d 15200.01MEP SAFEGUARD - PHASE 1 100%12d 25-Nov-14 24-Nov-14 13-Oct-14 10-Oct-14 -31d 03500.01LIGHTWEIGHT CONCRETE - LOWER ROOF - PHASE 1 0%5d 26-Nov-14 04-Dec-14 27-Oct-14 31-Oct-14 -22d 09200.01INSTALL FRAMING - PHASE 1 70%10d 04-Dec-14 08-Dec-14 09-Oct-14 13-Oct-14 -38d 16200.01INSTALL ELECTRICAL/SECURITY ROUGH - PHASE 1 10%10d 04-Dec-14 16-Dec-14 09-Oct-14 21-Oct-14 -38d 07500.01INSTALL NEW ROOFING SYSTEM- LOWER ROOF - PHASE 1 0%5d 05-Dec-14 11-Dec-14 03-Nov-14 07-Nov-14 -22d 09250.01EXTERIOR SHEATHING - PHASE 1 0%10d 08-Dec-14 19-Dec-14 13-Oct-14 24-Oct-14 -38d 06200.01ROUGH CARPENTRY - PHASE 1 0%10d 10-Dec-14 23-Dec-14 15-Oct-14 28-Oct-14 -38d 08500.01INSTALL WINDOWS - PHASE 1 40%10d 10-Dec-14 17-Dec-14 15-Oct-14 22-Oct-14 -38d 07240.01INSTALL EIFS SYSTEM/FIRESTOPPING - PHASE 1 0%13d 11-Dec-14 02-Jan-15 16-Oct-14 03-Nov-14 -38d 07510.01INSTALL ALUMINUM EDGE FLASHING - PHASE 1 0%4d 12-Dec-14 17-Dec-14 10-Nov-14 13-Nov-14 -22d 07520.01INSTALL PARAPET COPING - PHASE 1 0%4d 12-Dec-14 17-Dec-14 10-Nov-14 13-Nov-14 -22d 07530.01INSTALL OVERFLOW SCUPPERS - PHASE 1 0%4d 12-Dec-14 17-Dec-14 10-Nov-14 13-Nov-14 -22d 08200.01INSTALL DOORS - PHASE 1 0%5d 22-Dec-14 30-Dec-14 27-Oct-14 31-Oct-14 -38d 09100.01PLASTER - PHASE 1 0%5d 23-Dec-14 02-Jan-15 28-Oct-14 03-Nov-14 -38d 09910.01PAINT DOORS - PHASE 1 0%3d 02-Jan-15 06-Jan-15 06-Nov-14 10-Nov-14 -35d 07241.01INSTALL EIFS SYSTEM (CHANGE ORDER) - PHASE 1 0%5d 05-Jan-15 09-Jan-15 04-Nov-14 10-Nov-14 -38d 09110.01SYNTHETIC FINISH - PHASE 1 0%7d 05-Jan-15 13-Jan-15 04-Nov-14 12-Nov-14 -38d Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F MarApr 2014 2015 2016 GYPSUM ASSEMBLIES CONFERENCE FIREPROOFING CONFERENCE EIFS CONFERENCE DOOR/FRAME & HARDWARE CONFERENCE MEP CONFERENCE ROOFING CONFERENCE COMPOSITE WALL PANELS CONFERENCE SITEWORK CONFERENCE DEMONSTRATION & TRAINING CONFERENCE 03-Sep-15, EXTERIOR 20-Jan-15, PHASE 1 PROVIDE PROTECTED PERSONNEL/GUERNEY ACCESS MOBILIZE CREWS/EQUIP. - PHASE 1 INSTALL SCAFFOLDING - PHASE 1 REMOVE/RELOCATE TREES - PHASE 1 MASONRY WALL REINFORCEMENT - PHASE 1 SELECTIVE DEMOLITION - PHASE 1 MEP SAFEGUARD - PHASE 1 LIGHTWEIGHT CONCRETE - LOWER ROOF - PHASE 1 INSTALL FRAMING - PHASE 1 INSTALL ELECTRICAL/SECURITY ROUGH - PHASE 1 INSTALL NEW ROOFING SYSTEM- LOWER ROOF - PHASE 1 EXTERIOR SHEATHING - PHASE 1 ROUGH CARPENTRY - PHASE 1 INSTALL WINDOWS - PHASE 1 INSTALL EIFS SYSTEM/FIRESTOPPING - PHASE 1 INSTALL ALUMINUM EDGE FLASHING - PHASE 1 INSTALL PARAPET COPING - PHASE 1 INSTALL OVERFLOW SCUPPERS - PHASE 1 INSTALL DOORS - PHASE 1 PLASTER - PHASE 1 PAINT DOORS - PHASE 1 INSTALL EIFS SYSTEM (CHANGE ORDER) - PHASE 1 SYNTHETIC FINISH - PHASE 1 Actual Level of Effort Actual Work Remaining Work Critical Remaining Work START DATE 06-Dec-13, FINISH DATE 12-Feb-16 DATA DATE 21-Nov-14, RUN DATE 25-Aug-17 PAGE 5 OF 26