HomeMy WebLinkAboutSection 00700 - General conditions
00700 - 1/38
SECTION 00700 - GENERAL CONDITIONS
ARTICLE 1 -- DEFINITIONS
Wherever used in these General Conditions or in the other Contract Documents the following
terms have the meanings indicated:
Addenda - Written or graphic instruments issued prior to the opening of Bids which make
additions, deletions, or revisions to the Contract Documents.
Agreement - The written contract between the OWNER and the CONTRACTOR covering the
Work to be performed; when other documents are attached to the Agreement they become part
of the contract.
Application for Payment - The form furnished by the ENGINEER which is to be used by the
CONTRACTOR to request progress or final payment and which includes such supporting
documentation as is required by the Contract Documents.
Bid - The offer(s) submitted in response to this Invitation for Bid.
Bonds - Bid, Performance, and Payment Bonds and other instruments which protect against
loss due to inability or refusal of the CONTRACTOR to perform its Contract.
Change Order - A document recommended by the ENGINEER, which is signed by the
CONTRACTOR and the OWNER and authorizes an addition, deletion, or revision in the Work,
or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective
Date of the Agreement pursuant to Article 10.
Consultant - Architect or Engineer of Record
Contract Documents - The Notice Inviting Bids, Instructions to Bidders, Bid Forms (including the
Bid, Bid Schedule(s), Information Required of Bidder, Bid Bond, and all required certificates and
affidavits), Agreement, Performance Bond, Payment Bond, General Conditions, Supplementary
General Conditions, Technical Specifications, Drawings, and all addenda, and change orders
executed pursuant to the provisions of the Contract Documents.
Contract Price - The original amount established in the bid submittal and award by the City, as
may be amended by Change Order.
Contract Time - The original time between commencement and completion, including any
milestone dates thereof, established in the contract, as may be amended by Change Order.
CONTRACTOR - Anyone with whom the City has entered into a contractual agreement.
Day/ Calendar Day - A calendar day of 24 hours measured from midnight to the next midnight.
Defective Work - Work that is unsatisfactory, faulty, or deficient; or that does not conform to the
Contract Documents; or that does not meet the requirements of any inspection, reference
standard, test, or approval referred to in the Contract Documents; or Work that has been
damaged prior to the ENGINEER's recommendation of final payment.
00700 - 2/38
Drawings - The drawings, plans, maps, profiles, diagrams, and other graphic representations
which show the character, location, nature, extent, and scope of the Work and which have been
prepared by the ENGINEER and are referred to in the Contract Documents. Shop Drawings are
not Drawings as so defined.
Effective Date of the Agreement - The date indicated in the Agreement on which it was
executed, but if no such date is indicated it means the date on which the Agreement is signed
and delivered by the last of the two parties to sign and deliver.
ENGINEER - The OWNER's ENGINEER OR ARCHITECT.
Field Order - A written order which orders minor changes in the work but which does not involve
a change in the Contract Price or Contract Time.
Force Majeure - An act of God, including hurricanes, tornadoes, landslides, lightning,
earthquakes, fire, flood, explosion, sabotage or similar occurrence, acts of a public enemy, war,
blockage or insurrection, riot, civil disturbance, or act of terrorism.
General Requirements - Division 1 of the Technical Specifications.
Laws and Regulations; Laws or Regulations - Laws, rules, regulations, ordinances, codes,
and/or orders promulgated by a lawfully constituted body authorized to issue such Laws and
Regulations.
Notice of Intent to Award - The written notice by the OWNER to the apparent successful bidder
stating that upon compliance by the apparent successful bidder with the conditions precedent
enumerated therein within the time specified, the OWNER will consider to enter into an
Agreement.
Notice to Proceed - The written notice issued by the OWNER to the CONTRACTOR authorizing
the CONTRACTOR to proceed with the Work and establishing the date of commencement of
the Contract Time.
OWNER - The public body or authority with whom the CONTRACTOR has entered into the
Agreement and for whom the Work is to be provided.
Partial Utilization - Placing a portion of the Work in service for the purpose for which it is
intended (or a related purpose) before reaching Substantial Completion of the Work.
Project - All matters and things whether completed or partially completed, and includes all other
labor, materials, equipment and services provided or to be provided by the Successful Bidder in
accordance with the Contract.
Resident Project Representative - The authorized representative of the ENGINEER who is
assigned to the site or any part thereof.
Shop Drawings - All drawings, diagrams, illustrations, schedules and other data which are
specifically prepared by or for the CONTRACTOR and submitted by the CONTRACTOR to
illustrate some portion of Work and all illustrations, brochures, standard schedules, performance
00700 - 3/38
charts, instructions, and diagrams to illustrate material or equipment for some portion of the
Work.
Specifications - (Same definition as for Technical Specifications hereinafter).
Subcontractor - An individual, firm, or corporation having a direct contract with the
CONTRACTOR or with any other Subcontractor for the performance of a part of the Work at the
site.
Substantial Completion - Refers to the date certified by the ENGINEER to when all conditions
and requirements of permits and regulatory agencies have been satisfied, and when the Work
has progressed to the point where, in the opinion of the ENGINEER, as evidenced by the
Certificate of Substantial Completion/Notice of Completion as applicable, it is sufficiently
complete, in accordance with the Contract Documents, so that the Work is available for
beneficial occupancy and can be utilized for the purposes for which it is intended; or if there be
no such certificate issued when final payment is due in accordance with Article 14, Paragraph
14.8. A Temporary Certificate of Occupancy or Certificate of Occupancy must be issued for
Substantial Completion to be achieved, however, the issuance of a Temporary Certificate of
Occupancy or Certificate of Occupancy or the date thereof are not to be determinative of the
achievement or date of Substantial Completion. The terms "substantially complete" and
"substantially completed" can be used interchangeably as applied to any Work refer to as
“substantial completion” thereof.
Supplementary General Conditions - The part of the Contract Documents which make additions,
deletions, or revisions to these General Conditions.
Supplier - A manufacturer, fabricator, supplier, distributor, material man, or vendor.
Technical Specifications - Those portions of the Contract Documents consisting of the General
Requirements and written technical descriptions of products and execution of the Work.
Underground Utilities - All pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks,
tunnels, or other such facilities or attachments, and any encasements containing such facilities
which have been installed underground to furnish any of the following services or materials:
water, sewage and drainage removal, electricity, gases, steam, liquid petroleum products,
telephone or other communications, cable television, traffic, or other control systems.
Weather Delays - Work stoppage caused by abnormal inclement weather, where abnormal
duration and frequency of rain as compared with the Weather Bureau data and supported by
project logs, has caused the contractor to suspend critical path activities during the exceptional
adverse weather event for more than fifty percent (50%) of the work period of the day
exceptionally adverse weather. Weather delay claim can be made for work day only. No time
extension will be allowed for weekend rains.
Work - All matters and things whether completed or partially completed, and includes all other
labor, materials, equipment and services provided or to be provided by the Successful Bidder in
accordance with the Contract.
00700 - 4/38
ARTICLE 2 -- PRELIMINARY MATTERS
2.1 DELIVERY OF BONDS/INSURANCE CERTIFICATES
A. When the CONTRACTOR delivers the signed Agreements to the OWNER, the
CONTRACTOR shall also deliver to the OWNER such Bonds and Insurance
Policies and Certificates as the CONTRACTOR may be required to furnish in
accordance with the Contract Documents.
2.2 COPIES OF DOCUMENTS
A. The OWNER shall furnish to the CONTRACTOR the required number of copies
of the Contract Documents specified in the Supplementary General Conditions.
2.3 COMMENCEMENT OF CONTRACT TIME; NOTICE TO PROCEED
A. The Contract Time will start to run on the commencement date stated in the
Notice to Proceed.
2.4 STARTING THE PROJECT
A. The CONTRACTOR shall begin to perform the Work within 10 days after the
commencement date stated in the Notice to Proceed, but no Work shall be done
at the site prior to said commencement date.
2.5 BEFORE STARTING CONSTRUCTION
A. Before undertaking each part of the Work, the CONTRACTOR shall carefully
study and compare the Contract Documents and check and verify pertinent
figures shown thereon and all applicable field measurements. The
CONTRACTOR shall promptly report in writing to the ENGINEER any conflict,
error, or discrepancy which the CONTRACTOR may discover and shall obtain a
written interpretation or clarification from the ENGINEER before proceeding with
any Work affected thereby.
B. The CONTRACTOR shall submit to the ENGINEER for review those documents
called for under Section 01330 - Submittals in the General Requirements.
2.6 PRECONSTRUCTION CONFERENCE
A. A preconstruction conference attended by the CONTRACTOR, the ENGINEER
and others as appropriate will be held to discuss the Work in accordance with the
applicable procedures specified in the General Requirements.
2.7 FINALIZING SCHEDULES
A. At least seven (7) days before the first Pre-Construction Meeting, a conference
attended by the CONTRACTOR, the ENGINEER, and others as appropriate, the
CONTRACTOR will submit the following documents, if required, for the
ENGINEER’s review: Construction Schedule, Schedule of Values, MOT Plan (if
00700 - 5/38
applicable), Staging Plan, Mobilization Plan, submitted in accordance with the
General Requirements.
ARTICLE 3 -- CONTRACT DOCUMENTS: INTENT AMENDING, REUSE
3.1 INTENT
A. The Contract Documents comprise the entire agreement between the OWNER
and the CONTRACTOR concerning the Work. The Contract Documents are
complementary; what is called for by one is as binding as if called for by all. The
Contract Documents will be construed in accordance with the law of the place of
the Project.
B. It is the intent of the Contract Documents to describe the Work, functionally
complete, to be constructed in accordance with the Contract Documents. Any
Work, materials, or equipment that may reasonably be inferred from the Contract
Documents as being required to produce the intended result shall be supplied
whether or not specifically called for. When words which have a well-known
technical or trade meaning are used to describe Work, materials, or equipment
such words shall be interpreted in accordance with that meaning. Reference to
standard specifications, manuals, or codes of any technical society, organization,
or association, or to the Laws or Regulations of any governmental authority,
whether such reference be specific or by implication, shall mean the latest
standard specification, manual, code, or Laws or Regulations in effect at the time
of opening of Bids, except as may be otherwise specifically stated. However, no
provision of any referenced standard specification, manual, or code (whether or
not specifically incorporated by reference in the Contract Documents) shall be
effective to change the duties and responsibilities of the OWNER, the
CONTRACTOR, or the ENGINEER or any of their consultants, agents, or
employees from those set forth in the Contract Documents.
C. If, during the performance of the Work, the CONTRACTOR finds a conflict, error,
or discrepancy in the Contract Documents, the CONTRACTOR shall so report to
the ENGINEER in writing at once and before proceeding with the Work affected
thereby, shall obtain a written interpretation, clarification, or correction from the
ENGINEER.
3.2 ORDER OF PRECEDENCE OF CONTRACT DOCUMENTS
A. In resolving conflicts resulting from conflicts, errors, or discrepancies in any of the
Contract Documents, the order of precedence shall be as follows:
1. Change orders
2. Agreement
3. Addenda
4. Contractor's Bid (Bid Form)
5. Supplementary General Conditions
6. Notice Inviting Bids
7. Instructions to Bidders
8. General Conditions
00700 - 6/38
9. Technical Specifications
10. Referenced Standard Specifications
11. Drawings
B. With reference to the Drawings the order of precedence is as follows:
1. Figures govern over scaled dimensions
2. Detail drawings govern over general drawings
3. Addenda/change order drawings govern over Contract Drawings
4. Contract Drawings govern over standard drawings
3.3 AMENDING AND SUPPLEMENTING CONTRACT DOCUMENTS
A. The Contract Documents may be amended to provide for additions, deletions,
and revisions in the Work or to modify the terms and conditions thereof by a
Change Order (pursuant to Article 10).
3.4 REUSE OF DOCUMENTS
A. Neither the CONTRACTOR, nor any Subcontractor or Supplier, nor any other
person or organization performing any of the Work under a contract with the
OWNER shall have or acquire any title to or ownership rights in any of the
Drawings, Technical Specifications, or other documents used on the Work, and
they shall not reuse any of them on the extensions of the Project or any other
project without written consent.
ARTICLE 4 -- AVAILABILITY OF LANDS; PHYSICAL CONDITIONS; REFERENCE POINTS
4.1 AVAILABILITY OF LANDS
A. The OWNER shall furnish, as indicated in the Contract Documents, the lands
upon which the Work is to be performed, rights-of-way and easements for access
thereto, and such other lands which are designated for the use of the
CONTRACTOR. Easements for permanent structures or permanent changes in
existing facilities will be obtained and paid for by the OWNER, unless otherwise
provided in the Contract Documents. Nothing contained in the Contract
Documents shall be interpreted as giving the CONTRACTOR exclusive
occupancy of the lands or rights-of-way provided. The CONTRACTOR shall
provide for all additional lands and access thereto that may be required for
temporary construction facilities or storage of materials and equipment; provided,
that the CONTRACTOR shall not enter upon nor use any property not under the
control of the OWNER until a written temporary construction easement
agreement has been executed by the CONTRACTOR and the property owner,
and a copy of said easement furnished to the ENGINEER prior to said use; and,
neither the OWNER nor the ENGINEER shall be liable for any claims or
damages resulting from the CONTRACTOR's unauthorized trespass or use of
any such properties.
4.2 DIFFERING SITE CONDITIONS
00700 - 7/38
A. The CONTRACTOR shall notify the ENGINEER in writing of the following
unforeseen conditions, hereinafter called differing site conditions, promptly upon
their discovery (but in no event later than fourteen (14) days) and before they are
disturbed:
1. Subsurface or latent physical conditions at the site of the Work differing
materially from those indicated, described, or delineated in the Contract
Documents including; and
2. Unknown physical conditions at the site of the Work of an unusual nature
differing materially from those ordinarily encountered and generally
recognized as inherent in Work of the character provided for in the
Contract.
B. The ENGINEER will review the pertinent conditions, determine the necessity of
obtaining additional explorations or tests with respect thereto and advise the
OWNER in writing of the ENGINEER's findings and conclusions.
C. If the OWNER concludes that because of newly discovered conditions a change
in the Contract Documents is required, a Change Order will be issued as
provided in Article 10 to reflect and document the consequences of the
difference.
D. In each such case, an increase or decrease in the Contract Price or an extension
or shortening of the Contract Time, or any combination thereof, will be allowable
to the extent that they are attributable to any such difference. If the OWNER and
the CONTRACTOR are unable to agree as to the amount or length thereof, a
claim may be made therefor as provided in Articles 11 and 12.
E. The CONTRACTOR's failure to give notice of differing site conditions within
fourteen (14) days of their discovery or before they are disturbed shall constitute
a waiver of all claims in connection therewith, whether direct or consequential in
nature.
4.3 PHYSICAL CONDITIONS - UNDERGROUND UTILITIES
A. Shown or Indicated: The information and data shown or indicated in the Contract
Documents with respect to existing Underground Utilities at or contiguous to the
site are based on information and data furnished to the OWNER or the
ENGINEER by the owners of such Underground Utilities or by others. Unless it
is expressly provided in the Supplementary General Conditions and/or the
Section entitled "Protection of Existing Facilities" of the General Requirements,
the OWNER and the ENGINEER shall not be responsible for the accuracy or
completeness of any such information or data, and the CONTRACTOR shall
have full responsibility for reviewing and checking all such information and data,
and perform soft digs as required for locating all Underground Utilities shown or
indicated in the Contract Documents, for coordination of the Work with the
owners of such Underground Utilities during construction, for the safety and
protection thereof and repairing any damage thereto resulting from the Work, the
cost of which will be considered as having been included in the Contract Price.
00700 - 8/38
The contractor must be equipped with all necessary tools and parts in order to
repair damaged underground utilities in timely matter.
B. Not Shown or Indicated: If an Underground Utility is uncovered or revealed at or
contiguous to the site which was not shown or indicated in the Contract
Documents and which the CONTRACTOR could not reasonably have been
expected to be aware of, the CONTRACTOR shall identify the owner of such
Underground Utility and give written notice thereof to that owner, and shall notify
the ENGINEER in accordance with the requirements of the Supplementary
General Conditions and Section entitled "Protection of Existing Facilities" of the
General Requirements.
4.4 REFERENCE POINTS
A. The CONTRACTOR shall furnish all lines, grades, and bench marks required for
proper execution of the Work.
B. The CONTRACTOR shall preserve all bench marks, stakes, and other survey
marks, and in case of their removal or destruction by its own employees or by its
subcontractor's employees, the CONTRACTOR shall be responsible for the
accurate replacement of such reference points by professionally qualified
personnel.
4.5 ASBESTOS, HAZARDOUS WASTE, OR TOXIC OR RADIOACTIVE MATERIALS
A. If the CONTRACTOR observes, uncovers, or otherwise becomes aware of any
asbestos, hazardous waste, or toxic or radioactive material at the site to which
the CONTRACTOR or any Subcontractor, Supplier, or other person may be
exposed, the CONTRACTOR shall immediately notify the OWNER and the
ENGINEER and thereafter confirm any oral notice in writing. The OWNER will
promptly consult with the ENGINEER concerning such condition and determine
the necessity of OWNER's retaining special consultants or qualified experts to
deal therewith. The CONTRACTOR shall not perform any Work in connection
therewith prior to receipt of special written instructions from the OWNER through
the ENGINEER.
ARTICLE 5 -- BONDS AND INSURANCE
5.1 PERFORMANCE AND OTHER BONDS
A. The CONTRACTOR shall furnish Performance and Payment Bonds, each in the
amount set forth in the Supplementary General Conditions as security for the
faithful performance and payment of all the CONTRACTOR's obligations under
the Contract Documents. The Performance Bond shall remain in effect at least
until one year after the date of Substantial Completion/Notice of Completion as
applicable, except as otherwise provided by Law or Regulation or by the Contract
Documents; provided, that the amount of said Performance Bond may be
reduced to twenty-five (25) percent of the Contract Price, or $1,000, whichever is
greater or as greater as stated in the Supplemental General Conditions. The
00700 - 9/38
CONTRACTOR shall also furnish such other Bonds as are required by the
Supplementary General Conditions.
B. If the surety on any Bond furnished by the CONTRACTOR is declared a bankrupt or
becomes insolvent or its right to do business is terminated in any state where any
part of the Work is located, the CONTRACTOR shall within seven (7) days thereafter
substitute another Bond and Surety, which must be acceptable to the OWNER.
5.2 INSURANCE
A. The CONTRACTOR shall purchase and maintain the insurance required under this
Paragraph. Such insurance shall include the specific coverages set out herein and
be written for not less than the limits of liability and coverages provided in the
Supplementary General Conditions, or required by law, whichever are greater. All
insurance shall be maintained continuously during the life of the Agreement up to the
date of Substantial Completion/Notice of Completion as applicable, pursuant to
acceptance of the Work by the OWNER's governing body, but the CONTRACTOR's
liabilities under this Agreement shall not be deemed limited in any way to the
insurance coverage required.
B. The CONTRACTOR shall furnish the OWNER with certificates showing the type,
amount, class of operations covered, effective dates and dates of expiration of
policies. All of the policies of insurance so required to be purchased and
maintained (or the certificates or other evidence thereof) shall contain a provision
or endorsement that the coverage afforded will not be cancelled, materially
changed, or renewal refused until at least thirty (30) days prior written notice has
been given to the OWNER by certified mail. All such insurance shall remain in
effect until date of Substantial Completion and at all times thereafter when the
CONTRACTOR may be correcting, removing, or replacing defective Work in
accordance with Paragraph 13.6. In addition, the insurance required herein shall
name the OWNER, the ENGINEER, and their officers, directors, agents, and
employees as "additional insureds" under the policies.
1. Workers' Compensation and Employer's Liability: This insurance shall
protect the CONTRACTOR against all claims under applicable state
workers' compensation laws. The CONTRACTOR shall also be protected
against claims for injury, disease, or death of employees which, for any
reason, may not fall within the provisions of a workers' compensation law.
This policy shall include an "all states" endorsement. The
CONTRACTOR shall require each subcontractor similarly to provide
Workers' Compensation Insurance for all of the latter's employees to be
engaged in such Work unless such employees are covered by the
protection afforded by the CONTRACTOR's Workers' Compensation
Insurance. In case any class of employees is not protected, under the
Workers' Compensation Statute, the CONTRACTOR shall provide and
shall cause each subcontractor to provide adequate employer's liability
insurance for the protection of such of its employees as are not otherwise
protected.
2. Comprehensive General Liability: This insurance shall be written in
comprehensive form and shall protect the CONTRACTOR against all
00700 - 10/38
claims arising from injuries to persons other than its employees or
damage to property of the OWNER or others arising out of any act or
omission of the CONTRACTOR or its agents, employees, or
subcontractors. The policy shall also include protection against claims
insured by usual personal injury liability coverage, a "protective liability"
endorsement to insure the contractual liability assumed by the
CONTRACTOR under the indemnification provisions in the General
Conditions. To the extent that the CONTRACTOR's Work, or Work under
its direction, may require blasting, explosive conditions, or underground
operations, the comprehensive general liability coverage shall contain no
exclusion relative to blasting, explosion, collapse of buildings, or damage
to underground structures.
3. Comprehensive Automobile Liability: This insurance shall be written in
comprehensive form and shall protect the CONTRACTOR against all
claims for injuries to members of the public and damage to property of
others arising from the use of motor vehicles, and shall cover operation
on or off the site of all motor vehicles licensed for highway use, whether
they are owned, non owned, or hired.
4. Subcontractor's Public Liability and Property Damage Insurance and
Vehicle Liability Insurance: The CONTRACTOR shall either require each
of its subcontractors to procure and to maintain Subcontractor's Public
Liability and Property Damage Insurance and Vehicle Liability Insurance
of the type and in the amounts specified in the Supplementary General
Conditions or insure the activities of its subcontractors in the
CONTRACTOR's own policy, in like amount.
5. Builder's Risk: This insurance shall be of the "all risks" type, shall be
written in completed value form, and shall protect the CONTRACTOR, the
OWNER, and the ENGINEER against risks of damage to buildings,
structures, and materials and equipment. The amount of such insurance
shall be not less than the insurable value of the Work at completion.
Builder's risk insurance shall provide for losses to be payable to the
CONTRACTOR, the OWNER, and the ENGINEER as their interests may
appear. The policy shall contain a provision that in the event of payment
for any loss under the coverage provided, the insurance company shall
have no rights of recovery against the CONTRACTOR, the OWNER, and
the ENGINEER. The Builder's Risk policy shall insure against all risks of
direct physical loss or damage to property from any external cause
including windstorm, flood and earthquake. Allowable exclusions, if any,
shall be as specified in the Supplementary General Conditions.
ARTICLE 6 -- CONTRACTOR'S RESPONSIBILITIES
6.1 SUPERVISION AND SUPERINTENDENCE
A. The CONTRACTOR shall supervise and direct the Work competently and
efficiently, devoting such attention thereto and applying such skills and expertise
as may be necessary to perform the Work in accordance with the Contract
00700 - 11/38
Documents. The CONTRACTOR shall be responsible for the means, methods,
techniques, sequences, and procedures of construction and safety precautions
and programs incidental thereto. The CONTRACTOR shall be responsible to
see that the finished Work complies accurately with the Contract Documents.
B. The CONTRACTOR shall designate in writing and keep on the Work site at all
times during its progress a technically qualified, superintendent, who shall not be
replaced without written notice to the OWNER and the ENGINEER. The
superintendent will be the CONTRACTOR's representative at the site and shall
have authority to act on behalf of the CONTRACTOR. All communications given
to the superintendent shall be as binding as if given to the CONTRACTOR. The
CONTRACTOR shall issue all its communications to the OWNER through the
ENGINEER.
C. The CONTRACTOR's supervisor or superintendent shall be present at the site of
the Work at all times while Work is in progress. Failure to observe this
requirement shall be considered as suspension of the Work by the
CONTRACTOR until such time as such supervisor or superintendent is again
present at the site.
6.2 LABOR, MATERIALS, AND EQUIPMENT
A. The CONTRACTOR shall provide competent, suitably qualified personnel to
survey and lay out the Work and perform construction as required by the
Contract Documents. The CONTRACTOR shall furnish, erect, maintain, and
remove the construction plant and any temporary works as may be required.
The CONTRACTOR shall at all times maintain good discipline and order at the
site. Except in connection with the safety or protection of persons or the Work or
property at the site or adjacent thereto, and except as otherwise indicated in the
Contract Documents, all Work at the site shall be performed during regular
working hours, and the CONTRACTOR will not permit overtime Work or the
performance of Work on Saturday, Sunday, or any legal holiday without the
OWNER's written consent given after prior written notice to the ENGINEER.
B. Except as otherwise provided in this Paragraph, the CONTRACTOR shall
receive no additional compensation for overtime Work, i.e., Work in excess of
eight (8) hours in any one calendar day or forty (40) hours in any one calendar
week, even though such overtime Work may be required under emergency
conditions and may be ordered by the ENGINEER in writing. Additional
compensation will be paid the CONTRACTOR for overtime Work only in the
event extra Work is ordered by the ENGINEER and the change order specifically
authorizes the use of overtime Work and then only to such extent as overtime
wages are regularly being paid by the CONTRACTOR for overtime Work of a
similar nature in the same locality.
C. All costs of inspection and testing performed during overtime Work by the
CONTRACTOR which is allowed solely for the convenience of the
CONTRACTOR shall be borne by the CONTRACTOR. The OWNER shall have
the authority to deduct the cost of all such inspection and testing from any partial
payments otherwise due to the CONTRACTOR.
00700 - 12/38
D. Unless otherwise specified in the Contract Documents, the CONTRACTOR shall
furnish and assume full responsibility for all materials, equipment, labor,
transportation, construction equipment and machinery, instrumentation,
electronics, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, and all other facilities and incidentals necessary for the furnishing,
performance, testing, start-up, and completion of the Work.
E. All materials and equipment to be incorporated into the Work shall be of good
quality and new, except as otherwise provided in the Contract Documents. All
Suppliers' warranties and guarantees specifically called for by the Specifications
shall expressly run to the benefit of the OWNER. If required by the ENGINEER,
the CONTRACTOR shall furnish satisfactory evidence (including reports of
required tests) as to the kind and quality of materials and equipment. All
materials and equipment shall be applied, installed, connected, erected, used,
cleaned, and conditioned in accordance with the instructions of the applicable
Supplier except as otherwise provided in the Contract Documents; but no
provisions of any such instructions will be effective to assign to the ENGINEER,
or any of the ENGINEER's consultants, agents, or employees, any duty or
authority to supervise or direct the furnishing or performance of the Work or any
duty or authority to undertake responsibility contrary to the provisions of
Paragraphs 9.9C and 9.9D.
6.3 ADJUSTING PROGRESS SCHEDULE
A. The CONTRACTOR shall submit any adjustments in the progress schedule to
the ENGINEER for acceptance in accordance with the provisions for "Submittals"
in the General Requirements.
6.4 SUBSTITUTES OR "OR-EQUAL" ITEMS
A. The CONTRACTOR shall submit proposed substitutes or "or-equal" items in
accordance with the provisions for "Submittals" in the General Requirements.
6.5 CONCERNING SUBCONTRACTORS, SUPPLIERS, AND OTHERS
A. The CONTRACTOR shall be responsible to the OWNER and the ENGINEER for
the acts and omissions of its subcontractors and their employees to the same
extent as CONTRACTOR is responsible for the acts and omissions of its own
employees. Nothing contained in this Paragraph shall create any contractual
relationship between any subcontractor and the OWNER or the ENGINEER nor
relieve the CONTRACTOR of any liability or obligation under the prime Contract.
6.6 PERMITS
A. Unless otherwise provided in the Supplementary General Conditions or
Summary of Work, the CONTRACTOR shall obtain all construction permits and
licenses from the agencies having jurisdiction, including the furnishing of
insurance and bonds if required by such agencies. The enforcement of such
requirements under this Contract shall not be made the basis for claims for
additional compensation. The OWNER shall assist the CONTRACTOR, when
necessary, in obtaining such permits and licenses. The OWNER shall pay at
00700 - 13/38
cost and directly all governmental permit charges necessary for the prosecution
of the Work, which are applicable at the time of opening of Bids. The OWNER
shall pay at cost all charges of utility owners for connections to the Work. If
CONTRACTOR fails the regulatory inspections, CONTRCATOR shall pay for the
re-inspection fees necessary for the prosecution of the WORK.
CONTRACTOR shall not commence any work without the appropriate permit.
Copy of the respective permits shall be submitted to the ENGINEER prior to
commencement of work.
B. The CONTRACTOR shall pay all license fees and royalties and assume all costs
incident to the use in the performance of the Work or the incorporation in the
Work of any invention, design, process, product, or device which is the subject of
patent rights or copyrights held by others. If a particular invention, design,
process, product, or device is specified in the Contract Documents for use in the
performance of the Work and if to the actual knowledge of the OWNER or the
ENGINEER its use is subject to patent rights or copyrights calling for the
payment of any license fee or royalty to others, the existence of such rights shall
be disclosed by the OWNER in the Contract Documents. The CONTRACTOR
shall indemnify, defend and hold harmless the OWNER and the ENGINEER and
anyone directly or indirectly employed by either of them from and against all
claims, damages, losses, and expenses (including attorneys' fees and court
costs) arising out of any infringement of patent rights or copyrights incident to the
use in the performance of the Work or resulting from the incorporation in the
Work of any invention, design, process, product, or device not specified in the
Contract Documents, and shall defend all such claims in connection with any
alleged infringement of such rights.
6.7 LAWS AND REGULATIONS
A. The CONTRACTOR shall observe and comply with all federal, state, and local
laws, ordinances, codes, orders, and regulations which in any manner affect
those engaged or employed on the Work, the materials used in the Work, or the
conduct of the Work. If any discrepancy or inconsistency should be discovered
in this Contract in relation to any such law, ordinance, code, order, or regulation,
the CONTRACTOR shall report the same in writing to the ENGINEER. The
CONTRACTOR shall indemnify, defend, and hold harmless the OWNER, the
ENGINEER, and their officers, agents, and employees against all claims or
liability arising from violation of any such law, ordinance, code, order, or
regulation, whether by CONTRACTOR or by its employees or subcontractors.
Any particular law or regulation specified or referred to elsewhere in the Contract
Documents shall not in any way limit the obligation of the CONTRACTOR to
comply with all other provisions of federal, state, and local laws and regulations.
Where an individual State act on occupational safety and health standards has
been approved by Federal authority, then the provisions of said State act shall
control.
6.8 TAXES
00700 - 14/38
A. The CONTRACTOR shall pay all sales, consumer, use, and other similar taxes
required to be paid by the CONTRACTOR in accordance with the Laws and
Regulations of the place of the Project which are applicable during the
performance of the Work.
6.9 USE OF PREMISES
A. The CONTRACTOR shall confine construction equipment, the storage of
materials and equipment, and the operations of workers to (1) the Project site, (2)
the land and areas identified in and permitted by the Contract Documents, and
(3) the other land and areas permitted by Laws and Regulations, rights-of-way,
permits, and easements. The CONTRACTOR shall assume full responsibility for
any damage to any such land or area, or to the owner or occupant thereof or of
any land or areas contiguous thereto, resulting from the performance of the
Work. Should any claim be made against the OWNER or the ENGINEER by any
such owner or occupant because of the performance of the Work, the
CONTRACTOR shall promptly attempt to settle with such other party by
agreement or otherwise resolve the claim through litigation. The CONTRACTOR
shall, to the fullest extent permitted by Laws and Regulations, indemnify, defend,
and hold the OWNER and the ENGINEER harmless from and against all claims,
damages, losses, and expenses (including, but not limited to, fees of engineers,
architects, attorneys, and other professionals and court costs) arising directly,
indirectly, or consequentially out of any action, legal or equitable, brought by any
such other party against the OWNER or the ENGINEER to the extent based on a
claim arising out of the CONTRACTOR's performance of the Work.
6.10 SAFETY AND PROTECTION
A. The CONTRACTOR shall be responsible for initiating, maintaining, and
supervising all safety precautions and programs in connection with the Work.
The CONTRACTOR shall take all necessary precautions for the safety of, and
shall provide the necessary protection to prevent damage, injury or loss to:
1. all employees on the Work and other persons and organizations who may
be affected thereby;
2. all the Work and materials and equipment to be incorporated therein,
whether in storage on or off the site; and
3. other property at the site or adjacent thereto, including trees, shrubs,
lawns, walks, pavements, roadways, structures, mechanical equipment,
electronics, instrumentation, and utilities not designated for removal,
relocation, or replacement in the course of construction.
B. The CONTRACTOR shall comply with all applicable Laws and Regulations
(whether referred to herein or not) of any public body having jurisdiction for the
safety of persons or property or to protect them from damage, injury, or loss and
shall erect and maintain all necessary safeguards for such safety and protection.
The CONTRACTOR shall notify owners of adjacent property and utilities when
prosecution of the Work may affect them, and shall cooperate with them in the
protection, removal, relocation, and replacement of their property.
00700 - 15/38
C. The CONTRACTOR shall designate a responsible representative at the site
whose duty shall be the prevention of accidents. This person shall be the
CONTRACTOR's superintendent unless otherwise designated in writing by the
CONTRACTOR to the OWNER.
6.11 SHOP DRAWINGS AND SAMPLES
A. The CONTRACTOR shall submit shop drawings and samples in accordance with
the provision for "Submittals" in the General Requirements.
6.12 CONTINUING THE WORK
A. The CONTRACTOR shall carry on the Work and adhere to the progress
schedule during all disputes or disagreements with the OWNER. No Work shall
be delayed or postponed pending resolution of any disputes or disagreements,
except as the CONTRACTOR and the OWNER may otherwise agree in writing.
6.13 INDEMNIFICATION
A. To the fullest extent permitted by Laws and Regulations, the CONTRACTOR
shall indemnify, defend, and hold harmless the OWNER; the CONSULTANT; and
their officers, directors, agents, and employees, against and from all claims and
liability arising under, by reason of or incidentally to the Contract or any
performance of the Work, but not from the sole negligence or willful misconduct
of the OWNER and/or the CONSULTANT. Such indemnification by the
CONTRACTOR shall include but not be limited to the following:
1. Liability or claims resulting directly or indirectly from the negligence or
carelessness of the CONTRACTOR, its employees, or agents in the
performance of the Work, or in guarding or maintaining the same, or from
any improper materials, implements, or appliances used in its
construction, or by or on account of any act or omission of the
CONTRACTOR, its employees, or agents;
2. Liability or claims arising directly or indirectly from bodily injury,
occupational sickness or disease, or death of the CONTRACTOR's or
Subcontractor's own employees engaged in the Work resulting in actions
brought by or on behalf of such employees against the OWNER and/or
the CONSULTANT;
3. Liability or claims arising directly or indirectly from or based on the
violation of any law, ordinance, regulation, order, or decree, whether by
the CONTRACTOR, its employees, or agents;
4. Liability or claims arising directly or indirectly from the use or manufacture
by the CONTRACTOR, its employees, or agents in the performance of
this Contract of any copyrighted or uncopyrighted composition, secret
process, patented or unpatented invention, article, or appliance, unless
otherwise specifically stipulated in this Contract;
00700 - 16/38
5. Liability or claims arising directly or indirectly from the breach of any
warranties, whether express or implied, made to the OWNER or any other
parties by the CONTRACTOR, its employees, or agents;
6. Liabilities or claims arising directly or indirectly from the willful misconduct
of the CONTRACTOR, its employees, or agents; and,
7. Liabilities or claims arising directly or indirectly from any breach of the
obligations assumed herein by the CONTRACTOR.
B. The CONTRACTOR shall reimburse the OWNER, and the CONSULTANT for all
costs and expenses, (including but not limited to fees and charges of engineers,
architects, attorneys, and other professionals and court costs) incurred by said
OWNER, and the ENGINEER/CONSULTANT in enforcing the provisions of this
Paragraph 6.13.
C. The indemnification obligation under this Paragraph 6.13 shall not be limited in
any way by any limitation of the amount or type of damages, compensation, or
benefits payable by or for the CONTRACTOR or any such subcontractor or other
person or organization under workers' compensation acts, disability benefit acts,
or other employee benefit acts.
6.14 CONTRACTOR'S DAILY REPORTS
A. The CONTRACTOR shall complete a daily report indicating manpower, major
equipment, subcontractors, weather conditions, etc., involved in the performance
of the Work. The daily report shall be completed on forms prepared by the
CONTRACTOR and acceptable to the ENGINEER. A copy of the daily reports,
for the period covered, will be submitted to the owner with each pay request.
6.15 ASSIGNMENT OF CONTRACT
A. The CONTRACTOR shall not assign, sublet, sell, transfer, or otherwise dispose
of the Contract or any portion thereof, or its right, title, or interest therein, or
obligations thereunder, without the written consent of the OWNER except as
imposed by law. If the CONTRACTOR violates this provision, the Contract may
be terminated at the option of the OWNER. In such event, the OWNER shall be
relieved of all liability and obligations to the CONTRACTOR and to its assignee
or transferee, growing out of such termination.
ARTICLE 7 -- OTHER WORK
7.1 RELATED WORK AT SITE
A. The OWNER may perform other Work related to the Project at the site by the
OWNER's own forces, have other Work performed by utility owners, or let other
direct contracts therefor which may contain General Conditions similar to these.
If the fact that such other Work is to be performed was not noted in the Contract
00700 - 17/38
Documents, written notice thereof will be given to the CONTRACTOR prior to
starting any such other Work.
B. The CONTRACTOR shall afford each utility owner and other contractor who is a
party to such a direct contract (or the OWNER, if the OWNER is performing the
additional Work with the OWNER's employees) proper and safe access to the
site and a reasonable opportunity for the introduction and storage of materials
and equipment and the execution of such Work, and shall properly connect and
coordinate the Work with theirs. The CONTRACTOR shall do all cutting, fitting,
and patching of the Work that may be required to make its several parts come
together properly and integrate with such other Work. The CONTRACTOR shall
not endanger any Work of others by cutting, excavating, or otherwise altering
their Work and will only cut or alter their Work with the written consent of the
ENGINEER and the others whose Work will be affected.
C. If any part of the CONTRACTOR's Work depends for proper execution or results
upon the Work of any such other contractor or utility owner (or OWNER), the
CONTRACTOR shall inspect and report to the ENGINEER in writing any delays,
defects, or deficiencies in such Work that render it unavailable or unsuitable for such
proper execution and results. The CONTRACTOR's failure to report such delays,
defects, or deficiencies will constitute an acceptance of the other Work as fit and
proper for integration with the CONTRACTOR's Work except for latent or
nonapparent defects and deficiencies in the other Work.
7.2 COORDINATION
A. If the OWNER contracts with others for the performance of other Work on the
Project at the site, the person or organization who will have authority and
responsibility for coordination of the activities among the various prime
contractors will be identified in the Supplementary General Conditions, and the
specific matters to be covered by such authority and responsibility will be
itemized and the extent of such authority and responsibilities will be provided in
the Supplementary General Conditions. Unless otherwise provided in the
Supplementary General Conditions, neither the OWNER nor the ENGINEER
shall have any authority or responsibility in respect of such coordination.
ARTICLE 8 -- OWNER'S RESPONSIBILITIES
8.1 COMMUNICATIONS
A. The OWNER shall issue all its communications to the CONTRACTOR through
the ENGINEER.
8.2 PAYMENTS
A. The OWNER shall make payments to the CONTRACTOR as provided in
Paragraphs 14.5 and 14.8.
8.3 LANDS, EASEMENTS, AND SURVEYS
00700 - 18/38
A. The OWNER's duties in respect of providing lands and easements and providing
engineering surveys to establish reference points are set forth in Paragraphs 4.1
and 4.5. The OWNER shall identify and make available to the CONTRACTOR
copies of reports of explorations and tests of subsurface conditions at the site
and in existing structures which have been utilized by the ENGINEER in
preparing the Drawings and Technical Specifications as set forth in Paragraph
4.2.
8.4 CHANGE ORDERS
A. The OWNER shall execute Change Orders as indicated in Paragraph 10.1D.
8.5 INSPECTIONS AND TESTS
A. The OWNER's responsibility in respect of certain inspections, tests, and
approvals is set forth in Paragraph 13.3B.
8.6 SUSPENSION OF WORK
A. In connection with the OWNER's right to stop Work or suspend Work, see
Paragraphs 13.4 and 15.1. Paragraphs 15.2 and 15.3 deal with the OWNER's
right to terminate services of the CONTRACTOR under certain circumstances.
ARTICLE 9 -- ENGINEER'S STATUS DURING CONSTRUCTION
9.1 OWNER'S REPRESENTATIVE
A. The ENGINEER will be the OWNER's representative during the construction
period. The duties and responsibilities and the limitations of authority of the
ENGINEER as the OWNER's representative during construction are set forth in
the Contract Documents.
9.2 VISITS TO SITE
A. The ENGINEER will make visits to the site during construction to observe the
progress and quality of the Work and to determine, in general, if the Work is
proceeding in accordance with the Contract Documents. The ENGINEER will not
be required to make exhaustive or continuous on-site inspections to check the
quality or quantity of the Work. The ENGINEER will not, during such visits or as
a result of such observations of the CONTRACTOR's Work in progress,
supervise, direct, or have control over the CONTRACTOR's Work.
9.3 PROJECT REPRESENTATION
A. The ENGINEER may furnish a Resident Project Representative to assist in
observing the performance of the Work. The duties, responsibilities, and
limitations of authority of any such Resident Project Representative and
assistants will be as provided in the Supplementary General Conditions.
9.4 CLARIFICATIONS AND INTERPRETATIONS
00700 - 19/38
A. The ENGINEER will issue with reasonable promptness such written clarifications
or interpretations of the requirements of the Contract Documents (in the form of
Drawings or otherwise) as the ENGINEER may determine necessary, which shall
be consistent with or reasonably inferable from the overall intent of the Contract
Documents.
9.5 AUTHORIZED VARIATIONS IN WORK
A. The ENGINEER may authorize minor variations in the Work from the
requirements of the Contract Documents which do not involve an adjustment in
the Contract Price or the Contract Time and are consistent with the overall intent
of the Contract Documents. These may be accomplished by a Field Order and
will require the CONTRACTOR to perform the Work involved promptly. If the
CONTRACTOR believes that a Field Order justifies an increase in the Contract
Price or an extension of the Contract time and the parties are unable to agree as
to the amount or extent thereof, the CONTRACTOR may make a claim therefor
as provided in Article 11 or 12.
9.6 REJECTING DEFECTIVE WORK
A. The ENGINEER will have authority to reject Work which the ENGINEER believes
to be defective and will also have authority to require special inspection or testing
of the Work as provided in Paragraph 13.3G, whether or not the Work is
fabricated, installed, or completed.
9.7 CONTRACTOR SUBMITTALS, CHANGE ORDERS, AND PAYMENTS
A. In accordance with the procedures set forth in the General Requirements, the
ENGINEER will review all CONTRACTOR submittals, including shop drawings,
samples, substitutes, or "or equal" items, etc., in order to determine if the items
covered by the submittals will, after installation or incorporation in the Work,
conform to the requirements of the Contract Documents and be compatible with
the design concept of the completed project as a functioning whole as indicated
by the Contract Documents. The ENGINEER's review will not extend to means,
methods, techniques, sequences or procedures of construction or to safety
precautions or programs incident thereto.
B. In connection with the ENGINEER's responsibilities as to Change Orders, see
Articles 10, 11, and 12.
C. In connection with the ENGINEER's responsibilities in respect of Applications for
Payment, see Article 14.
9.8 DECISIONS ON DISPUTES
A. The ENGINEER will be the initial interpreter of the requirements of the Contract
Documents and judge of the acceptability of the Work thereunder. Claims,
disputes, and other matters relating to the acceptability of the Work; the
interpretation of the requirements of the Contract Documents pertaining to the
performance of the Work; and those claims under Articles 11 and 12 in respect to
00700 - 20/38
changes in the Contract Price or Contract Time will be referred initially to the
ENGINEER in writing with a request for formal decision in accordance with this
Paragraph, which the ENGINEER will render in writing within thirty (30) days of
receipt of the request. Written notice of each such claim, dispute, and other
matter will be delivered by the CONTRACTOR to the ENGINEER promptly (but
in no event later than thirty (30) days) after the occurrence of the event giving
rise thereto. Written supporting data will be submitted to the ENGINEER within
sixty (60) days after such occurrence unless the ENGINEER allows an additional
period of time to ascertain more accurate data in support of the claim.
B. When functioning as arbiter and judge, the ENGINEER will not show partiality to
the OWNER or the CONTRACTOR and will not be liable in connection with any
interpretation or decision rendered in good faith in such capacity. The rendering
of a decision by the ENGINEER with respect to any such claim, dispute, or other
matter (except any which have been waived by the making or acceptance of final
payment as provided in Paragraph 14.12) will be a condition precedent to any
exercise by the OWNER or the CONTRACTOR of such rights or remedies as
either may otherwise have under the Contract Documents or by Law or
Regulations in respect of any such claim, dispute, or other matter.
9.9 LIMITATION ON ENGINEER'S RESPONSIBILITIES
A. Neither the ENGINEER's authority to act under this Article 9 or other provisions
of the Contract Documents nor any decision made by the ENGINEER in good
faith either to exercise or not exercise such authority shall give rise to any duty or
responsibility of the ENGINEER to the CONTRACTOR, any Subcontractor, any
Supplier, any surety for any of them, or any other person or organization
performing any of the Work.
B. Whenever in the Contract Documents the terms "as ordered," "as directed," "as
required," "as allowed," "as reviewed," "as approved," or terms of like effect or
import are used, or the adjectives "reasonable," "suitable," "acceptable," "proper,"
or "satisfactory" or adjectives of like effect or import are used to describe a
requirement, direction, review, or judgment of the ENGINEER as to the Work, it
is intended that such requirement, direction, review, or judgment will be solely to
evaluate the Work for compliance with the requirements of the Contract
Documents, and conformance with the design concept of the completed Project
as a functioning whole as indicated by the Contract Documents, unless there is a
specific statement indicating otherwise. The use of any such term or adjective
shall not be effective to assign to the ENGINEER any duty or authority to
supervise or direct the performance of the Work or any duty or authority to
undertake responsibility contrary to the provisions of Paragraph 9.9C or 9.9D.
C. The ENGINEER will not have authority over or be responsible for the
CONTRACTOR's means, methods, techniques, sequences, or procedures of
construction, or the safety precautions and programs incident thereto, or for any
failure of the CONTRACTOR to comply with Laws and Regulations, applicable to
the performance of the Work. The ENGINEER will not be responsible for the
CONTRACTOR's failure to perform the Work in accordance with the Contract
Documents.
00700 - 21/38
D. The ENGINEER will not be responsible for the acts or omissions of the
CONTRACTOR nor of any subcontractor, supplier, or any other person or
organization performing any of the Work.
ARTICLE 10 -- CHANGES IN THE WORK
10.1 GENERAL
A. Without invalidating the Agreement and without notice to any surety, the OWNER
may at any time or from time to time, order additions, deletions, or revisions in
the Work; these will be authorized by a written Field Order and/or a Change
Order issued by the ENGINEER. Upon receipt of any such document, the
CONTRACTOR shall promptly proceed with the Work involved which will be
performed under the applicable conditions of the Contract Documents.
B. If the OWNER and the CONTRACTOR are unable to agree as to the extent, if
any, of an increase or decrease in the Contract Price or an extension or
shortening of the Contract Time that should be allowed as a result of a Field
Order, a claim may be made therefor as provided in Articles 11 or 12.
C. The CONTRACTOR shall not be entitled to an increase in the Contract Price nor
an extension of the Contract Time with respect to any Work performed that is not
required by the Contract Documents as amended, modified, supplemented by
Change Order, except in the case of an emergency and except in the case of
uncovering Work as provided in Paragraph 13.3G.
D. The OWNER and the CONTRACTOR shall execute appropriate Change Orders
covering:
1. changes in the Work which are ordered by the OWNER pursuant to
Paragraph 10.1A;
2. changes required because of acceptance of defective Work under
Paragraph 13.7;
3. changes in the Contract Price or Contract Time which are agreed to by
the parties; or
4. any other changes agreed to by the parties.
E. If notice of any change is required by the provisions of any Bond to be given to a
surety, the giving of any such notice will be the CONTRACTOR's responsibility,
and the amount of each applicable Bond shall be adjusted accordingly.
10.2 ALLOWABLE QUANTITY VARIATIONS
A. In the event of an increase or decrease in bid item quantity of a unit price
contract, the total amount of Work actually done or materials or equipment
furnished shall be paid for according to the unit price established for such Work
under the Contract Documents, wherever such unit price has been established;
00700 - 22/38
provided, that an adjustment in the Contract Price may be made for changes
which result in an increase or decrease in the quantity of any unit price bid item
of the Work in excess of twenty-five (25) percent. The CONTRACTOR shall
prepare a detail description of work showing quantities, pricing, and economic
and market justifications supporting the increase in price. The OWNER will
either accept or reject the price increase.
B. In the event a part of the Work is to be entirely eliminated and no lump sum or
unit price is named in the Contract Documents to cover such eliminated Work,
the price of the eliminated Work shall be agreed upon in writing by the OWNER
and the CONTRACTOR. If the OWNER and the CONTRACTOR fail to agree
upon the price of the eliminated Work, said price shall be determined in
accordance with the provisions of Article 11.
ARTICLE 11 -- CHANGE OF CONTRACT PRICE
11.1 GENERAL
A. The Contract Price constitutes the total compensation payable to the
CONTRACTOR for performing the Work. All duties, responsibilities, and
obligations assigned to or undertaken by the CONTRACTOR shall be at its
expense without change in the Contract Price.
B. The Contract Price may only be changed by a Change Order. Any claim for an
increase in the Contract Price shall be based on written notice delivered by the
CONTRACTOR to the ENGINEER promptly (but in no event later than thirty (30)
days) after the occurrence of the event giving rise to the claim and stating the
general nature of the claim. Notice of the amount of the claim with supporting
data shall be delivered within sixty (60) days after such occurrence (unless the
ENGINEER allows an additional period of time to ascertain more accurate data in
support of the claim) and shall be accompanied by the CONTRACTOR's written
statement that the amount claimed covers all known amounts (direct, indirect,
and consequential) to which the CONTRACTOR is entitled as a result of the
occurrence of said event. All claims for adjustment in the Contract Price shall be
determined by the ENGINEER in accordance with Paragraph 9.8A if the OWNER
and the CONTRACTOR cannot otherwise agree on the amount involved. No
claim for an adjustment in the Contract Price will be valid if not submitted in
accordance with this Paragraph 11.1B.
C. The value of any Work covered by a Change Order or of any claim for an
increase or decrease in the Contract Price shall be determined in one of the
following ways:
1. Where the Work involved is covered by unit prices contained in the
Contract Documents, by application of unit prices to the quantities of the
items involved.
2. By mutual acceptance of a lump sum, which may include an allowance for
overhead and profit not necessarily in accordance with Paragraph 11.4.
00700 - 23/38
3. On the basis of the cost of Work (determined as provided in Paragraphs
11.2 and 11.3) plus a CONTRACTOR's fee for overhead and profit
(determined as provided in Paragraph 11.4).
11.2 COST OF WORK (BASED ON TIME AND MATERIALS)
A. General: The term "cost of Work" means the sum of all costs necessarily
incurred and paid by the CONTRACTOR for labor, materials, and equipment in
the proper performance of extra Work. Except as otherwise may be agreed to in
writing by the OWNER, such costs shall be in amounts no higher than those
prevailing in the locality of the Project. Whenever any extra Work is in progress,
for which the definite price has not been agreed on in advance, the
CONTRACTOR shall each day, report to the ENGINEER the amount and cost of
the labor and material used, and any other expense incurred in such extra Work
on the preceding day, and no claim for compensation for such extra Work will be
allowed unless such report shall have been made.
B. Labor: The cost of labor used in performing extra Work by the CONTRACTOR, a
subcontractor, or other forces will be the sum of the following:
1. The actual wages paid plus any employer payments to, or on behalf of
workers for fringe benefits including health and welfare, pension,
vacation, and similar purposes. The cost of labor may include the wages
paid to foremen when determined by the ENGINEER that the services of
foremen do not constitute a part of the overhead allowance.
2. All payment imposed by state and federal laws including, but not limited
to, compensation insurance, and social security payments.
3. The amount paid for subsistence and travel required by collective
bargaining agreements, or in accordance with the regular practice of the
employer.
4. At the beginning of the extra Work and as later requested by the
ENGINEER, the CONTRACTOR shall furnish the ENGINEER proof of
labor compensation rates being paid.
C. Materials: The cost of materials used in performing extra Work will be the cost to
the purchaser, whether CONTRACTOR or subcontractor, from the supplier
thereof, except as the following are applicable:
1. Trade discounts available to the purchaser shall be credited to the
OWNER notwithstanding the fact that such discounts may not have been
taken by the CONTRACTOR.
2. For materials secured by other than a direct purchase and direct billing to
the purchaser, the cost shall be deemed to be the price paid to the actual
supplier as determined by the ENGINEER. Markup except for actual
costs incurred in the handling of such materials will not be allowed.
00700 - 24/38
3. Payment for materials from sources owned wholly or in part by the
purchaser shall not exceed the price paid by the purchaser for similar
materials from said sources on extra Work items or the current wholesale
price for such materials delivered to the Work site, whichever price is
lower.
4. If in the opinion of the ENGINEER the cost of material is excessive, or the
CONTRACTOR does not furnish satisfactory evidence of the cost of such
material, then the cost shall be deemed to be the lowest current
wholesale price for the quantity concerned delivered to the Work site less
trade discount. The OWNER reserves the right to furnish materials for
the extra Work and no claim shall be made by the CONTRACTOR for
costs and profit on such materials.
D. Equipment: The CONTRACTOR will be paid for the use of equipment as stated
in the latest edition of the "Compilation of Rental Rates for Construction
Equipment" by Associated Equipment Distributors. Such rental rate will be used
to compute payments for equipment whether the equipment is under the
CONTRACTOR's control through direct ownership, leasing, renting, or another
method of acquisition. The rental rate to be applied for use of each item of
equipment shall be the rate resulting in the least total cost to the OWNER for the
total period of use. The CONTRACTOR may furnish cost data which might assist
the ENGINEER in the establishment of the rental rate.
1. All equipment shall, in the opinion of the ENGINEER, be in good working
condition and suitable for the purpose for which the equipment is to be
used.
2. Before construction equipment is used on the extra Work, the
CONTRACTOR shall plainly stencil or stamp an identifying number
thereon at a conspicuous location, and shall furnish to the ENGINEER, in
duplicate, a description of the equipment and its identifying number.
3. Unless otherwise specified, manufacturer's ratings and manufacturer
approved modifications shall be used to classify equipment for the
determination of applicable rental rates. Equipment which has no direct
power unit shall be powered by a unit of at least the minimum rating
recommended by the manufacturer.
4. Individual pieces of equipment or tools having a replacement value of
$100 or less, whether or not consumed by use, shall be considered to be
small tools and no payment will be made therefor.
5. Rental time will not be allowed while equipment is inoperative due to
breakdowns.
00700 - 25/38
E. Equipment on the Work Site: The rental time to be paid for equipment on the
Work site shall be the time the equipment is in productive operation on the extra
Work being performed and, in addition, shall include the time required to move
the equipment to the location of the extra Work and return it to the original
location or to another location requiring no more time than that required to return
it to its original location; except, that moving time will not be paid if the equipment
is used on other than the extra Work, even though located at the site of the extra
Work. Loading and transporting costs will be allowed, in lieu of moving time,
when the equipment is moved by means other than its own power, except that no
payment will be made for loading and transporting costs when the equipment is
used at the site of the extra Work on other than the extra Work. The following
shall be used in computing the rental time of equipment on the Work site.
1. When hourly rates are listed, any part of an hour less than 30 minutes of
operation shall be considered to be 1/2-hour of operation, and any part of
an hour in excess of 30 minutes will be considered one hour of operation.
2. When daily rates are listed, any part of a day less than 4 hours operation
shall be considered to be 1/2-day of operation. When owner-operated
equipment is used to perform extra Work to be paid for on a time and
materials basis, the CONTRACTOR will be paid for the equipment and
operator, as set forth in Paragraphs (3), (4), and (5), following.
3. Payment for the equipment will be made in accordance with the
provisions in Paragraph 11.2D, herein.
4. Payment for the cost of labor and subsistence or travel allowance will be
made at the rates paid by the CONTRACTOR to other workers operating
similar equipment already on the Work site, or in the absence of such
labor, established by collective bargaining agreements for the type of
workmen and location of the extra Work, whether or not the operator is
actually covered by such an agreement. A labor surcharge will be added
to the cost of labor described herein in accordance with the provisions of
Paragraph 11.2B, herein, which surcharge shall constitute full
compensation for payments imposed by state and federal laws and all
other payments made to or on behalf of workers other than actual wages.
5. To the direct cost of equipment rental and labor, computed as provided
herein, will be added the allowances for equipment rental and labor as
provided in Paragraph 11.4, herein.
11.3 SPECIAL SERVICES
A. Special Work or services are defined as that Work characterized by extraordinary
complexity, sophistication, or innovation or a combination of the foregoing
attributes which are unique to the construction industry. The following may be
considered by the ENGINEER in making estimates for payment for special
services:
1. When the ENGINEER and the CONTRACTOR, by agreement, determine
that a special service or Work is required which cannot be performed by
00700 - 26/38
the forces of the CONTRACTOR or those of any of its subcontractors, the
special service or Work may be performed by an entity especially skilled
in the Work to be performed. After validation of invoices and
determination of market values by the ENGINEER, invoices for special
services or Work based upon the current fair market value thereof may be
accepted without complete itemization of labor, material, and equipment
rental costs.
2. When the CONTRACTOR is required to perform Work necessitating
special fabrication or machining process in a fabrication or a machine
shop facility away from the job site, the charges for that portion of the
Work performed at the off-site facility may, by agreement, be accepted as
a special service and accordingly, the invoices for the Work may be
accepted without detailed itemization.
3. All invoices for special services will be adjusted by deducting all trade
discounts offered or available, whether the discounts were taken or not.
In lieu of the allowances for overhead and profit specified in Paragraph
11.4, herein, an allowance of five (5) percent will be added to invoices for
special services.
B. All Work performed hereunder shall be subject to all of the provisions of the
Contract Documents and the CONTRACTOR's sureties shall be bound with
reference thereto as under the original Agreement. Copies of all amendments to
surety bonds or supplemental surety bonds shall be submitted to the OWNER for
review prior to the performance of any Work hereunder.
11.4 CONTRACTOR'S OVERHEAD AND PROFIT
A. Extra Work ordered on the basis of time and materials will be paid for at the
actual necessary cost as determined by the ENGINEER, plus allowances for
overhead and profit. For extra Work involving a combination of increases and
decreases in the Work the actual necessary cost will be the arithmetic sum of the
additive and deductive costs. The allowance for overhead and profit shall include
full compensation for superintendence, bond and insurance premiums, taxes,
office expense, and all other items of expense or cost not included in the cost of
labor, materials, or equipment provided for under Paragraphs 11.2B, C, and D,
herein including extended overhead and home office overhead. The allowance
for overhead and profit will be made in accordance with the following schedule:
Actual Necessary Cost Overhead and Profit Allowance
Labor twenty (20) percent
Materials fifteen (15) percent
00700 - 27/38
B. It is understood that labor, materials, and equipment may be furnished by the
CONTRACTOR or by the subcontractor on behalf of the CONTRACTOR. When
all or any part of the extra Work is performed by a subcontractor, the allowance
specified herein shall be applied to the labor, materials, and equipment costs of
the subcontractor, to which the CONTRACTOR may add five (5) percent of the
subcontractor's total cost for the extra Work. Regardless of the number of
hierarchical tiers of subcontractors, the five (5) percent increase above the
subcontractor's total cost which includes the allowances for overhead and profit
specified herein may be applied one time only for each separate Work
transaction.
11.5 EXCLUDED COSTS
A. The term "cost of the Work" shall not include any of the following:
1. Payroll costs and other compensation of CONTRACTOR's officers,
executives, principals (of partnership and sole proprietorships) general
managers, engineers, architects, estimators, attorneys' auditors
accountants, purchasing and contracting agents, expediters, time
keepers, clerks, and other personnel employed by CONTRACTOR
whether at the site or in CONTRACTOR's principal or a branch office for
general administration of the Work and not specifically covered by
Paragraph 11.3F all of which are to be considered administrative costs
covered by the CONTRACTOR's allowance for overhead and profit;
2. Expenses of CONTRACTOR's principal and branch offices other than
CONTRACTOR's office at the site;
3. Any part of CONTRACTOR's capital expenses, including interest on
CONTRACTOR's capital employed for the Work and charges against
CONTRACTOR for delinquent payments;
4. Cost of premiums for all Bonds and for all insurance whether or not
CONTRACTOR is required by the Contract Documents to purchase and
maintain the same (except for the cost of premiums covered by
Paragraph 11.4 above);
5. Costs due to the negligence of CONTRACTOR, any Subcontractor, or
anyone directly employed by any of them or for whose acts any of them
may be liable, including but not limited to, the correction of defective work,
disposal of materials or equipment wrongly supplied, and making good
any damage to property.
ARTICLE 12 -- CHANGE OF CONTRACT TIME
12.1 GENERAL
00700 - 28/38
A. The Contract Time may only be changed by a Change Order. Any claim for an
extension of the Contract Time shall be based on written notice delivered by the
CONTRACTOR to the ENGINEER promptly (but in no event later than thirty (30)
days) after the occurrence of the event giving rise to the claim and stating the
general nature of the claim. Notice of the extent of the claim with supporting data
shall be delivered within sixty (60) days after such occurrence (unless the
ENGINEER allows an additional period of time to ascertain more accurate data in
support of the claim) and shall be accompanied by the CONTRACTOR'S written
statement that the adjustment claimed is the entire adjustment to which the
CONTRACTOR has reason to believe it is entitled as a result of the occurrence
of said event. All claims for adjustment in the Contract Time shall be determined
by the ENGINEER in accordance with Paragraph 9.8 if the OWNER and the
CONTRACTOR cannot otherwise agree. No claim for an adjustment in the
Contract Time will be valid if not submitted in accordance with the requirements
of this Paragraph 12.1A.
B. The Contract Time will be extended in an amount equal to time lost due to delays
beyond the control of the CONTRACTOR provided that such time lost affects the
critical path as shown on the CPM schedule if a claim is made therefor as
provided in Paragraph 12.1A. Such delays shall include: acts or neglect by the
OWNER or others performing additional Work as contemplated by Article 7, or by
acts of God or of the public enemy, fire, floods, epidemics, quarantine
restrictions, strikes, labor disputes, sabotage, or freight embargoes.
C. Force Majeure: The performance of this Agreement may be suspended and the
obligations of either party excused in the event of and during the period that such
performance is prevented or delayed by a Force Majeure occurrence.
D. All time limits stated in the Contract Documents are of the essence of the
Agreement.
12.2 EXTENSIONS OF TIME FOR DELAY DUE TO INCLEMENT WEATHER
A. Contract Times may be extended by the ENGINEER because of delays in the
completion of the Work due to unusually severe weather, provided that the
CONTRACTOR shall, within ten (10) days of the beginning of any such delay,
notify the ENGINEER in writing of the cause of delay and request an extension of
Contract Times. The ENGINEER will ascertain the facts and the extent of the
delay and extend the Contract times when, in its judgment, the findings of the
fact justify such an extension.
B. The CONTRACTOR shall base its construction schedule upon the inclusion of
the number of days of inclement weather specified in paragraph entitled
"Inclement weather delays" of the Supplementary General Conditions. No
extension of the Contract Time due to inclement weather will be considered until
after the said number of days of inclement weather has been reached. However,
no reduction in Contract Time will be made if said number of days of inclement
weather is not reached.
00700 - 29/38
ARTICLE 13 -- WARRANTY AND GUARANTEE; TESTS AND INSPECTIONS; CORRECTION,
REMOVAL, OR ACCEPTANCE OF DEFECTIVE WORK
13.1 WARRANTY AND GUARANTEE
A. The CONTRACTOR warrants and guarantees to the OWNER and the
ENGINEER that all Work will be in accordance with the Contract Documents and
will not be defective. Prompt notice of defects known to the OWNER or
ENGINEER shall be given to the CONTRACTOR. All defective Work, whether or
not in place, may be rejected, corrected, or accepted as provided in this
Article 13.
13.2 ACCESS TO WORK
A. The ENGINEER, other representatives of the OWNER, testing agencies, and
governmental agencies with jurisdictional interests shall have access to the Work
at reasonable times for their observation, inspections, and testing. The
CONTRACTOR shall provide proper and safe conditions for such access.
13.3 TESTS AND INSPECTIONS
A. The CONTRACTOR shall give the ENGINEER timely notice of readiness of the
Work for all required inspections, tests, or approvals.
B. If Laws or Regulations of any public body having jurisdiction other than the
OWNER require any Work to specifically be inspected, tested, or approved, the
CONTRACTOR shall pay all costs in connection therewith. The CONTRACTOR
shall also be responsible for and shall pay all costs in connection with any
inspection or testing required in connection with the OWNER's or the
ENGINEER's acceptance of a Supplier of materials or equipment proposed as a
substitution or (or-equal) to be incorporated in the Work, or of materials or
equipment submitted for review prior to the CONTRACTOR's purchase thereof
for incorporation in the Work. The costs of all inspections, tests, and approvals in
addition to the above which are required by the Contract Documents shall be
paid by the OWNER (unless otherwise specified). The CONTRACTOR will pay
for failed tests and “stand-by time” by the Laboratory Tests personnel and others.
C. The ENGINEER will make, or have made, such inspections and test as the
ENGINEER deems necessary to see that the Work is being accomplished in
accordance with the requirements of the Contract Documents. Unless otherwise
specified in the Supplementary General Conditions, the cost of such inspection
and testing will be borne by the OWNER. In the event such inspections or tests
reveal non-compliance with the requirements of the Contract Documents, the
CONTRACTOR shall bear the cost of corrective measures deemed necessary by
the ENGINEER, as well as the cost of subsequent re-inspection and retesting.
Neither observations by the ENGINEER nor inspections, tests, or approvals by
others shall relieve the CONTRACTOR from the CONTRACTOR's obligation to
perform the Work in accordance with the Contract Documents.
00700 - 30/38
D. All inspections, tests, or approvals other than those required by Laws or
Regulations of any public body having jurisdiction shall be performed by
organizations acceptable to the ENGINEER and the CONTRACTOR.
E. If any Work (including the Work of others) that is to be inspected, tested, or
approved is covered without written concurrence of the ENGINEER, it must, if
requested by the ENGINEER, be uncovered for observation. Such uncovering
shall be at the CONTRACTOR's expense unless the CONTRACTOR has given
the ENGINEER timely notice of the CONTRACTOR's intention to perform such
test or to cover the same and the ENGINEER has not acted with reasonable
promptness in response to such notice.
F. If any Work is covered contrary to the written request of the ENGINEER, it must,
if requested by the ENGINEER, be uncovered for the ENGINEER's observation
and replaced at the CONTRACTOR's expense.
G. If the ENGINEER considers it necessary or advisable that covered Work be
observed by the ENGINEER or inspected or tested by others, the
CONTRACTOR, at the ENGINEER's request, shall uncover, expose, or
otherwise make available for observation, inspection, or testing as the
ENGINEER may require, that portion of the Work in question, furnishing all
necessary labor, material, and equipment. If it is found that such Work is
defective, the CONTRACTOR shall bear all direct, indirect, and consequential
costs and damages of such uncovering, exposure, observation, inspection, and
testing and of satisfactory reconstruction, including but not limited to fees and
charges of engineers, architects, attorneys, and other professionals. However, if
such Work is not found to be defective, the CONTRACTOR shall be allowed an
increase in the Contract Price or an extension of the Contract Time, or both,
directly attributable to such uncovering, exposure, observation, inspection,
testing, and reconstruction; and, if the parties are unable to agree as to the
amount or extent thereof, the CONTRACTOR may make a claim therefor as
provided in Articles 11 and 12.
13.4 OWNER MAY STOP THE WORK
A. If the Work is defective, or the CONTRACTOR fails to perform Work in such a
way that the completed Work will conform to the Contract Documents, the
OWNER may order the CONTRACTOR to stop the Work, or any portion thereof,
until the cause for such order has been eliminated; however, this right of the
OWNER to stop the Work shall not give rise to any duty on the part of the
OWNER to exercise this right for the benefit of the CONTRACTOR or any other
party.
13.5 CORRECTION OR REMOVAL OF DEFECTIVE WORK
A. If required by the ENGINEER, the CONTRACTOR shall promptly, either correct
all defective Work, whether or not fabricated, installed, or completed, or, if the
Work has been rejected by the ENGINEER, remove it from the site and replace it
with non-defective Work. The CONTRACTOR shall bear all direct, indirect and
consequential costs and damages of such correction or removal, including but
00700 - 31/38
not limited to fees and charges of engineers, architects, attorneys, and other
professionals made necessary thereby.
13.6 ONE YEAR CORRECTION PERIOD
A. If within one year after the date of Substantial Completion or such longer period
of time as may be prescribed by Laws or Regulations or by the terms of any
applicable special guarantee required by the Contract Documents or by any
specific provision of the Contract Documents, any Work is found to be defective,
the CONTRACTOR shall promptly, without cost to the OWNER and in
accordance with OWNER's written notification, either correct such defective
Work, or, if it has been rejected by the OWNER, remove it from the site and
replace it with non-defective Work. If the CONTRACTOR does not promptly
comply with the such notification, or in an emergency where delay would cause
serious risk of loss or damage, the OWNER may have the defective Work
corrected or the rejected Work removed and replaced, and all direct, indirect, and
consequential costs and damages of such removal and replacement including
but not limited to fees and charges of engineers, architects, attorneys and other
professionals will be paid by the CONTRACTOR.
B. Where defective Work (and damage to other Work resulting there from) has been
corrected, removed or replaced under Paragraph 13.6, the correction period
hereunder, with respect to such Work will be extended for an additional period of one
year after such correction or removal and replacement has been satisfactorily
completed.
13.7 ACCEPTANCE OF DEFECTIVE WORK
A. If, instead of requiring correction or removal and replacement of defective Work,
the OWNER prefers to accept the Work, the OWNER may do so. The
CONTRACTOR shall bear all direct, indirect, and consequential costs
attributable to the OWNER's evaluation of and determination to accept such
defective Work. If any such acceptance occurs prior to final payment, a Change
Order will be issued incorporating the necessary revisions in the Contract
Documents with respect to the Work, and the OWNER shall be entitled to an
appropriate decrease in the Contract Price.
ARTICLE 14 -- PAYMENTS TO CONTRACTOR AND COMPLETION
14.1 SCHEDULE OF VALUES (LUMP SUM PRICE BREAKDOWN)
A. The schedule of values or price breakdown established as provided in the
General Requirements shall serve as the basis for progress payments and will be
incorporated into a form of Application for Payment acceptable to the
ENGINEER.
14.2 UNIT PRICE BID SCHEDULE
A. Progress payments on account of Unit Price Work will be based on the number
of units completed.
00700 - 32/38
14.3 APPLICATION FOR PROGRESS PAYMENT
A. Unless otherwise prescribed by law, on the 25th of each month, or other agreed
upon date, the CONTRACTOR shall submit to the ENGINEER for review, an
Application for Payment filled out and signed by the CONTRACTOR covering the
Work completed as of the date of the Application and accompanied by such
supporting documentation as is required by the Contract Documents.
B. The Application for Payment shall identify, as a subtotal, the amount of the
CONTRACTOR'S Total Earnings to Date, plus the Value of Materials Stored at
the Site which have not yet been incorporated in the Work, and less a deductive
adjustment for materials installed which were not previously incorporated in the
Work, but for which payment was allowed under the provisions for payment for
Materials Stored at the Site, but not yet incorporated in the Work.
C. The Net Payment Due to the CONTRACTOR shall be the above-mentioned
subtotal from which shall be deducted the amount of retainage specified in the
Supplementary General Conditions, and the total amount of all previous
payments made to the CONTRACTOR.
D. The Value of Materials Stored at the Site shall be an amount equal to the
specified percent of the value of such materials as set forth in the Supplementary
General Conditions. Said amount shall be based upon the value of all
acceptable materials and equipment not incorporated in the Work but delivered
and suitably stored at the site or at another location agreed to in writing;
provided, each such individual item has a value of more than $5,000 and will
become a permanent part of the Work. The Application for Payment shall also
be accompanied by a bill of sale, invoice, or other documentation warranting that
the CONTRACTOR has received the materials and equipment free and clear of
all liens, charges, security interests, and encumbrances (which are hereinafter in
these General Conditions referred to as "Liens") and evidence that the materials
and equipment are covered by appropriate property insurance and other
arrangements to protect the OWNER's interest therein, all of which will be
satisfactory to the OWNER.
14.4 CONTRACTOR'S WARRANTY OF TITLE
A. The CONTRACTOR warrants and guarantees that title to all Work, materials,
and equipment covered by an Application for Payment, whether incorporated in
the Work or not, will pass to the OWNER no later than the time of final payment
free and clear of all liens.
14.5 REVIEW OF APPLICATIONS FOR PROGRESS PAYMENT
A. The ENGINEER will, within seven (7) days after receipt of each Application for
Payment, either indicate in writing a recommendation of payment and present the
Application to the OWNER, or return the Application to the CONTRACTOR
indicating in writing the ENGINEER's reasons for refusing to recommend
payment. In the later case, the CONTRACTOR may make the necessary
corrections and resubmit the Application. Thirty days after presentation of the
00700 - 33/38
Application for Payment with the ENGINEER's recommendation, the amount
recommended will (subject to the provisions of Paragraph 14.5B) become due
and when due will be paid by the OWNER to the CONTRACTOR.
B. The OWNER may refuse to make payment of the full amount recommended by
the ENGINEER because claims have been made against the OWNER on
account of the CONTRACTOR's performance of the Work or Liens have been
filed in connection with the Work or there are other items entitling the OWNER to
a credit against the amount recommended, but the OWNER must give the
CONTRACTOR written notice within seven (7) days (with a copy to the
ENGINEER) stating the reasons for such action.
14.6 PARTIAL UTILIZATION
A. The OWNER shall have the right to utilize or place into service any item of
equipment or other usable portion of the Work prior to completion of the Work.
Whenever the OWNER plans to exercise said right, the CONTRACTOR will be
notified in writing by the OWNER, identifying the specific portion or portions of
the Work to be so utilized or otherwise placed into service.
B. It shall be understood by the CONTRACTOR that until such written notification is
issued, all responsibility for care and maintenance of all items or portions of the
Work to be partially utilized shall be borne by the CONTRACTOR. Upon
issuance of said written notice of partial utilization, the OWNER will accept
responsibility for the protection and maintenance of all such items or portions of
the Work described in the written notice.
C. The CONTRACTOR shall retain full responsibility for satisfactory completion of
the Work, regardless of whether a portion thereof has been partially utilized by
the OWNER and the CONTRACTOR's one year correction period shall
commence only after the date of Substantial Completion for the Work.
14.7 SUBSTANTIAL COMPLETION
A. When the CONTRACTOR considers the Work ready for its intended use the
CONTRACTOR shall notify the OWNER and the ENGINEER in writing that the
Work is substantially complete and request that the ENGINEER prepare a
Certificate of Substantial Completion/Notice of Completion. Within a reasonable
time thereafter, the OWNER, the CONTRACTOR, and the ENGINEER shall
make an inspection of the Work to determine the status of completion. If the
ENGINEER does not consider the Work substantially complete, the ENGINEER
will notify the CONTRACTOR in writing giving the reasons therefor. If the
ENGINEER considers the Work substantially complete, the ENGINEER will
prepare and deliver to the OWNER for its execution and recordation the
Certificate of Substantial Completion/Notice of Completion signed by the
ENGINEER and CONTRACTOR, which shall fix the date of Substantial
Completion. As applicable, there shall be attached to the Certificate/Notice a list
of items to be completed or corrected before final payment.
14.8 FINAL APPLICATION FOR PAYMENT
00700 - 34/38
A. After the CONTRACTOR has completed all correction Work referred to in
Paragraph 14.7 and delivered all maintenance and operating instructions,
schedules, guarantees, Bonds, certificates of inspection, marked-up record
documents (as provided in the General Requirements) and other documents, all
as required by the Contract Documents, and after the ENGINEER has indicated
that the Work is acceptable, the CONTRACTOR may make application for final
payment following the procedure for progress payments. The final Application for
Payment shall be accompanied by all documentation called for in the Contract
Documents, together with complete and legally effective releases or waivers
(satisfactory to the OWNER) of all liens arising out of or filed in connection with
the Work.
14.9 FINAL PAYMENT AND ACCEPTANCE
A. If, on the basis of the ENGINEER's observation of the Work during construction
and final inspection, and the ENGINEER's review of the final Application for
Payment and accompanying documentation, all as required by the Contract
Documents, the ENGINEER is satisfied that the Work has been completed and
the CONTRACTOR's other obligations under the Contract Documents have been
fulfilled, the ENGINEER will, within fourteen (14) days after receipt of the final
Application for Payment, indicate in writing the ENGINEER's recommendation of
payment and present the Application to the OWNER for payment.
B. After acceptance of the Work by the OWNER's governing body, the OWNER will
make final payment to the CONTRACTOR of the amount remaining after
deducting all prior payments and all amounts to be kept or retained under the
provisions of the Contract Documents, including the following items:
1. Liquidated damages, as applicable.
2. Two times the value of outstanding items of correction Work or punch list
items indicated on the Certificate of Substantial Completion/Notice of
Completion as being yet uncompleted or uncorrected, as applicable. All
such Work shall be completed or corrected to the satisfaction of the
OWNER within the time stated on the Certificate of Substantial
Completion/Notice of Completion, otherwise the CONTRACTOR does
hereby waive any and all claims to all monies withheld by the OWNER to
cover the value of all such uncompleted or uncorrected items.
14.10 RELEASE OF RETAINAGE AND OTHER DEDUCTIONS
A. After executing the necessary documents to initiate the lien period, and not more
than forty-five (45) days thereafter (based on a 30-day lien filing period and
15-day processing time), the OWNER will release to the CONTRACTOR the
retainage funds withheld pursuant to the Agreement, less any deductions to
cover pending claims against the OWNER pursuant to Paragraph 14.5B.
B. After filing of the necessary documents to initiate the lien period, the
CONTRACTOR shall have thirty (30) days to complete any outstanding items of
correction Work remaining to be completed or corrected as listed on a final punch
list made a part of the Certificate of Substantial Completion/Notice of Completion.
00700 - 35/38
Upon expiration of the 45 days, referred to in Paragraph 14.10A, the amounts
withheld pursuant to the provisions of Paragraph 14.9B herein, for all remaining
Work items will be returned to the CONTRACTOR; provided, that said Work has
been completed or corrected to the satisfaction of the OWNER within said thirty
(30) days. Otherwise, the CONTRACTOR does hereby waive any and all claims
for all monies withheld by the OWNER under the Contract to cover two (2) times
the value of such remaining uncompleted or uncorrected items.
14.11 CONTRACTOR'S CONTINUING OBLIGATION
A. The CONTRACTOR's obligation to perform and complete the Work in
accordance with the Contract Documents shall be absolute. Neither
recommendation of any progress or final payment by the ENGINEER, nor the
issuance of a Certificate of Substantial Completion/Notice of Completion, nor any
payment by the OWNER to the CONTRACTOR under the Contract Documents,
nor any use or occupancy of the Work or any part thereof by the OWNER, nor
any act of acceptance by the OWNER nor any failure to do so, nor any review of
a Shop Drawing or sample submittal, will constitute an acceptance of Work not in
accordance with the Contract Documents or a release of the CONTRACTOR's
obligation to perform the Work in accordance with the Contract Documents.
14.12 FINAL PAYMENT TERMINATES LIABILITY OF OWNER
A. Final payment is defined as the last progress payment made to the
CONTRACTOR for earned funds, less retainage as applicable, less deductions
listed in Paragraph 14.9B herein. The acceptance by the CONTRACTOR of the
final payment referred to in Paragraph 14.9 herein, shall be a release of the
OWNER and its agents from all claims of liability to the CONTRACTOR for
anything done or furnished for, or relating to, the Work or for any act or neglect of
the OWNER or of any person relating to or affecting the Work, except demands
against the OWNER for the remainder, if any, of the amounts kept or retained
under the provisions of Paragraph 14.9 herein; and excepting pending,
unresolved claims filed prior to the date of the Certificate of Substantial
Completion/Notice of Completion.
ARTICLE 15 -- SUSPENSION OF WORK AND TERMINATION
15.1 SUSPENSION OF WORK BY OWNER
A. The OWNER, acting through the ENGINEER, may, at any time and without
cause, suspend the Work or any portion thereof for a period of not more than
ninety (90) days by notice in writing to the CONTRACTOR. The CONTRACTOR
shall resume the Work on receipt from the ENGINEER of a notice of resumption
of Work. The CONTRACTOR shall be allowed an increase in the Contract Price
or an extension of the Contract Time, or both, directly attributable to any
suspension if the CONTRACTOR makes an approved claim therefor as provided
in Articles 11 and 12.
15.2 TERMINATION OF AGREEMENT BY OWNER (CONTRACTOR DEFAULT)
00700 - 36/38
A. In the event of default by the CONTRACTOR, the OWNER may give ten (10)
days written notice to the CONTRACTOR of OWNER's intent to terminate the
Agreement and provide the CONTRACTOR an opportunity to remedy the
conditions constituting the default. It shall be considered a default by the
CONTRACTOR whenever CONTRACTOR shall: (1) declare bankruptcy, become
insolvent, or assign its assets for the benefit of its creditors; (2) fail to provide
materials or workmanship meeting the requirements of the Contract Documents;
(3) disregard or violate provisions of the Contract Documents or ENGINEER's
instructions; (4) fail to prosecute the Work according to the approved progress
schedule; or, (5) fail to provide a qualified superintendent, competent workmen,
or materials or equipment meeting the requirements of the Contract Documents.
If the CONTRACTOR fails to remedy the conditions constituting default within the
time allowed, the OWNER may then issue the Notice of Termination.
B. In the event the Agreement is terminated in accordance with Paragraph 15.2A,
herein, the OWNER may take possession of the Work and may complete the
Work by whatever method or means the OWNER may select. The cost of
completing the Work shall be deducted from the balance which would have been
due the CONTRACTOR had the Agreement not been terminated and the Work
completed in accordance with the Contract Documents. If such cost exceeds the
balance which would have been due, the CONTRACTOR shall pay the excess
amount to the OWNER. If such cost is less than the balance which would have
been due, the CONTRACTOR shall not have claim to the difference.
15.3 TERMINATION OF AGREEMENT BY OWNER (FOR CONVENIENCE)
A. The OWNER may terminate the Agreement at any time if it is found that reasons
beyond the control of either the OWNER or CONTRACTOR make it impossible
or against the OWNER's interests to complete the Work. In such a case, the
CONTRACTOR shall have no claims against the OWNER except: (1) for the
value of Work performed up to the date the Agreement is terminated; and, (2) for
the cost of materials and equipment on hand, in transit, or on definite
commitment, as of the date the Agreement is terminated, which would be needed
in the Work and which meet the requirements of the Contract Documents. The
value of Work performed and the cost of materials and equipment delivered to
the site, as mentioned above, shall be determined by the ENGINEER in
accordance with the procedure prescribed for the making of the final application
for payment and payment under Paragraphs 14.8 and 14.9.
15.4 TERMINATION OF AGREEMENT BY CONTRACTOR
A. The CONTRACTOR may terminate the Agreement upon ten (10) days written
notice to the OWNER, whenever: (1) the Work has been suspended under the
provisions of Paragraph 15.1, herein, for more than ninety (90) consecutive days
through no fault or negligence of the CONTRACTOR, and notice to resume Work
or to terminate the Agreement has not been received from the OWNER within
this time period; or, (2) the OWNER should fail to pay the CONTRACTOR any
monies due him in accordance with the terms of the Contract Documents and
within 60 days after presentation to the OWNER by the CONTRACTOR of a
request therefor, unless within said 10-day period the OWNER shall have
remedied the condition upon which the payment delay was based. In the event
00700 - 37/38
of such termination, the CONTRACTOR shall have no claims against the
OWNER except for those claims specifically enumerated in Paragraph 15.3,
herein, and as determined in accordance with the requirements of said
paragraph.
ARTICLE 16 -- MISCELLANEOUS
16.1 GIVING NOTICE
A. Whenever any provision of the Contract Documents requires the giving of written
notice, it will be deemed to have been validly given if delivered in person to the
individual or to a member of the firm or to an officer of the corporation for whom it
is intended, or if delivered at or sent by registered or certified mail, postage
prepaid, to the last business address known to the giver of the notice.
16.2 TITLE/OWNERSHIP TO MATERIALS FOUND ON THE WORK
A. The OWNER reserves the right to retain title to all soils, stone, sand, gravel, and
other materials developed and obtained from excavations and other operations
connected with the Work until released by the OWNER. Any material desired to
be retained by the OWNER shall be delivered by the CONTRACTOR to a
designed area within a six (6) mile radius of the project, at no extra cost to the
OWNER, as directed by the OWNER, unless otherwise specified in the Contract
Documents. Neither the CONTRACTOR nor any subcontractor shall have any
right, title, or interest in or to any such materials. The CONTRACTOR will be
permitted to use in the Work, if approved by the OWNER and ENGINEER in
writing, without charge, any such materials which meet the requirements of the
Contract Documents. Once the OWNER releases ownership of the material, it
shall become the property of the CONTRACTOR, who shall dispose of it in
manner satisfactorily to the ENGINEER, as provided for by the CONTRACTOR,
at no extra cost to the OWNER.
16.3 RIGHT TO AUDIT
A. If the CONTRACTOR submits a claim to the OWNER for additional
compensation, the OWNER shall have the right, as a condition to considering the
claim, and as a basis for evaluation of the claim, and until the claim has been
settled, to audit the CONTRACTOR's books to the extent they are relevant. This
right shall include the right to examine books, records, documents, and other
evidence and accounting procedures and practices, sufficient to discover and
verify all direct and indirect costs of whatever nature claimed to have been
incurred or anticipated to be incurred and for which the claim has been
submitted. The right to audit shall include the right to inspect the
CONTRACTOR's plants, or such parts thereof, as may be or have been engaged
in the performance of the Work. The CONTRACTOR further agrees that the right
to audit encompasses all subcontracts and is binding upon subcontractors. The
rights to examine and inspect herein provided for shall be exercisable through
such representatives as the OWNER deems desirable during the
CONTRACTOR's normal business hours at the office of the CONTRACTOR.
The CONTRACTOR shall make available to the OWNER for auditing, all relevant
00700 - 38/38
accounting records and documents, and other financial data, and upon request,
shall submit true copies of requested records to the OWNER.
- END OF SECTION -