PART 1 -- GENERAL
These local requirements make additions to the Contract Documents which are required by
state and local regulations.
A. Public Entity Crimes: Pursuant to the requirements of Section 287.133, Florida
Statues, pertaining to the sworn statement on Public Entity Crimes and the Convicted
Vendor List, all Bidders shall submit a signed and notarized statement with their Bid on
the form provided in Section 00300, "Sworn Statement Pursuant to Section
287.133(3)(a), FLORIDA STATUTES on Public Entity Crimes."
B. Florida Trench Safety Act: The Bidders attention is directed to the enactment of the
Florida Trench Safety Act, which incorporates OSHA Standards 29 CFR 1926.650,
Subpart P, as the state's trench excavation safety standards. The Bidder shall list
separately on the form provided in Section 00300 - Trench Safety Act Compliance
Statement the cost of compliance with these standards. The Bidder shall determine if
special shoring requirements are needed. Special shoring shall be identified and
included in the cost quoted in the "Trench Safety Act Compliance Statement". The
successful Bidder is fully responsible for the design of the trench safety system and the
compliance with the applicable standards for the Project.
C. Anti-Kickback Affidavit: All Bidders shall submit a signed and notarized Affidavit with
their Bid on the form provided in Section 00300, "Anti-Kickback Affidavit".
D. Indemnification: Pursuant to Section 725.06 of the Florida Statutes, the CONTRACTOR
hereby acknowledges receipt and the adequacy of the specific consideration in the
amount of one hundred ($100) which sum is included in the Total Bid Price, as payment
from the OWNER to the CONTRACTOR for the indemnification given by the
CONTRACTOR to the OWNER and ENGINEER under Section 00700, "General
Conditions", Paragraph 6.13.
E. Time is of the Essence for This Contract: Should the Contractor fail to complete the
Contract by the contract completion date, as amended by any approved Change Orders,
the Contractor will be subject to the liquidated damages as set forth elsewhere in this
contract. In addition to the imposition of liquidated damages, the Owner will not process
any partial payment request, nor make any partial payments to the contractor for such
beyond the contract completion date (e.g., the only payment that will be made beyond the
contract completion date will be a final payment once all the work has been completed
and accepted by the owner).
- END OF SECTION -