HomeMy WebLinkAboutSection 01010 Summary of Work
01010 - 1/3
SECTION 01010 - SUMMARY OF WORK
PART 1 - GENERAL
1.01 SUMMARY: This section summarizes the Work of the Project as covered in detail in the
complete Contract Documents. This is a general summary and is not intended to be
complete and all inclusive of the required Work items.
1.02 PROJECT DESCRIPTION:
A. Description of Project The work includes the CONTRACTOR furnishing all labor,
materials, tools, equipment, incidentals and service necessary for the construction of
approximately 12,000 linear feet of main conduit duct bank, numerous lateral conduit
duct banks, street light conduit, street light concrete bases ,spare conduit for city of
Sunny Isles, concrete pads for FPL transformers and Vista Switch Cabinets, Manholes,
Hand holes, splitter boxes, and testing, surface overlay, traffic control, site restoration
including sod, landscaping and driveway restoration to match existing conditions; and
all other appurtenant and miscellaneous and incidental items and work for a complete,
functional and satisfactory installation of the project as shown on the drawings. The
duct banks contain conduit vary in sizes from 2 inch to 6-inch in diameter. The project
involves work on Collins Avenue from NE 196th Street to Bayview Drive work off Collins
Avenue including 191,185,178 and 175 Streets from Atlantic Boulevard to Collins
Avenue; Atlantic Boulevard from 185 Street to 191 Street and 175 Street to 183 Street
and the easement north of 175 street and south of 172 Street. All Work must be
completed by March 31, 2017
B. The project is located in the street segments as shown on the Key Sheet of the
Drawing Set,. Refer to the Contract Documents for the exact locations of the
construction work.
1.03 RELATED CONTRACT ACTIVITIES:
A. The Contractor shall comply with all Municipal, County, State and Federal laws, rules
and regulations applicable to the work and the execution of the work.
B. The Contractor shall review the existing permits for this project and secure all
necessary additional permits for the execution of the work, including but not limited to
permits from the City of Sunny Isles Beach and FDOT.
C. The Contractor shall employ and pay for a Land Surveyor registered in the State Of
Florida to establish all elevations, lines and levels.
D. The Contractor shall be responsible for prompt notification to the Owner and timely
field repairs in the event that the Contractor damages any of the Owner’s existing
properties or overhead/ underground utilities.
E. The Contractor shall be responsible for obtaining the necessary storage/staging
areas for materials and equipment. The Contractor shall coordinate deliveries in
accordance with the construction schedule and these specifications, so that
materials do not pose an unnecessary long-term nuisance to motorists or residents.
Excavated materials and/or backfill materials shall not be stored in the roadway right-
of-way for more than 24 hours. If suitable for backfill elsewhere, excavated material
must be stockpiled within the staging area. Materials unsuitable for backfill must be
removed and disposed off immediately.
01010 - 2/3
1. Wherever possible, open trenches must be backfilled/plated, and barricades
removed while maintaining adequate safety measures.
2. Streets must be graded/leveled to provide reasonable assurance against
personal injury, vehicle damage, etc.
3. Streets temporarily restored, as described above, must be regularly
maintained. For example, streets must be watered, new potholes filled and
disturbed and adjacent paved streets swept.
F. The Contractor shall employ and pay for the services of an independent testing
laboratory to perform quality control services on work performed by the contractor.
G. There is an available Geotechnical Investigation Report at the City of Sunny Isle
Beach.
1. The above referenced report is no guarantee as to accuracy of completeness.
2. The Contractor is cautioned that this report has been utilized for general
purposes only and may be inadequate for the purposes of bidding on the
Contract items.
3. The availability of this report does not relieve the Contractor from his
responsibility to familiarize itself with the subsurface conditions that may affect
cost, progress and performance of work.
1.04 WORK PERFORMED BY OTHERS:
A. The City of Sunny Isles Beach or other contractors may perform work on the existing
water distribution system or public utilities as part of their maintenance and
operations. The Contractor shall conduct its operations so as to cause a minimum of
interference with the work of such other contractors and/or public utilities, and shall
cooperate fully to provide continuous safe access to their respective portions of the
site to perform their respective contracts.
1.05 CONTRACTOR'S USE OF PREMISES: See General Condition.
1.06 WORK SEQUENCE, COORDINATION ACTIVITIES AND SCHEDULED DATES:
A. General: Work under this contract shall be scheduled and performed in such a
manner as to result in the least possible disruption to driveway access. The
CONTRACTOR will coordinate its work with other adjacent contractors, landowners,
residents and City activities, with specific attention to access and staging areas.
Construction sequence shall be determined by CONTRACTOR subject to the
following needs for continuous access and operation by others.
1. The work will be performed in residential/commercial neighborhoods. The
CONTRACTOR shall reasonable minimize the inconvenience to the residents
and property owners, and reasonably maximize the safety of the residents:
2. construction activities shall take place in the evening in accordance with lane
closure hours approved by the FDOT for the project MOT. All open trenches
and excavations shall be closed or covered, and be in good driving condition
with permanent asphalt, at the end of each work day. CONTRACTOR cannot
proceed with the construction in more than one street at the same time, unless
approved otherwise.
3. The work shall be conducted to maintain access to existing driveways at all
times.
01010 - 3/3
B. Construction Schedule: The CONTRACTOR shall submit a proposed construction
schedule, clearly showing the sequence of the work on a street-by-street and block
by block basis to the City and the ENGINEER for their approval. Refer to Section
01310 Construction Schedules.
1.07 COPIES OF DOCUMENTS: See General Conditions.
1.08 CONTRACT DOCUMENTS:
A. Contract Drawings:
END OF SECTION