HomeMy WebLinkAboutSection 01310- Construction Schedules
01310 - 1/6
SECTION 01310 CONSTRUCTION SCHEDULES
PART 1 - GENERAL
1.01 SCOPE:
A. Construction Progress Schedule: The Contractor shall submit a detailed work
progress schedule showing all work in a graphic format suitable for displaying
scheduled and actual progress. The Engineer will review and comment on the
schedule. Upon agreement, the Contractor shall furnish the Engineer prints of the
accepted schedule. The Contractor shall not change the accepted work progress
schedule without prior concurrence of the Engineer. The schedule shall show actual
progress and any proposed changes in the schedule of the remaining work.
B. The WORK under this contract will be planned, scheduled, executed, and reported
by the CONTRACTOR using a cost-loaded CPM (Critical Path Method) schedule
with a coding structure specified by the CITY. The CONTRACTOR will adhere to
established technical standards for CPM scheduling using a computerized
precedence diagram method. The CONTRACTOR is required to provide baseline
and status data using in hard copy and electronic (CD disk) format as specified
herein.
C. The CONTRACTOR is responsible for coordinating its own schedules (including
subcontractors) as well as the construction activities of others as required to fully
execute the Work. The CITY’S goal is to maintain the overall Construction Program
Schedule, of which the CONTRACTOR’S Construction Schedule will be a part.
1.02 SOFTWARE/INTERFACE REQUIREMENTS:
A. The CONTRACTOR shall use CPM scheduling software to produce the contract
schedules and reports as specified herein. This software shall be Primavera
Enterprise Scheduling Software (P3e/c) or a compatible format such as Primavera
Contractor, or approved equal.
B. Within ten calendar (10) days of the Notice of Award, the CONTRACTOR shall
submit, for review and approval by the CITY, descriptive information on the proposed
CPM software to be used.
1.03 QUALITY ASSURANCE:
A. The CONTRACTOR shall perform the work covered by this Section with personnel
having substantial experience in the use of computer based scheduling programs on
construction projects for the development and maintenance of the schedule
throughout the project duration.
B. It is the responsibility of the CONTRACTOR to work with each subcontractor and
supplier to obtain information pertinent to the planning and updating of their
respective activities in the schedules.
1.04 DEALING WITH SUBSTITUTES:
A. All versions of the CONTRACTOR’S schedule (including Construction Schedule
Revisions) shall be based solely on the WORK as awarded, and shall exclude any
substitute proposals, even if the CONTRACTOR pursues a substitution in
accordance with the provisions of the Contract.
01310 - 2/6
B. The CITY’S final determination on any proposed substitutions may not be made until
after the CONTRACTOR’S Construction Schedule is prepared and accepted.
Accepted proposed substitutions shall be handled in the schedule as change orders.
1.05 USE OF FLOAT:
A. Total Float is the amount of time a scheduled activity can be delayed without
delaying the completion of the Work beyond the contractually required end date.
Contract Float is the number of days between the CONTRACTOR’S anticipated date
for early completion of the WORK, or specified part and the corresponding Contract
Time. Total Float and Contract Float belong to the project and are not for the
exclusive benefit of any party. They shall be available to the CITY, their consultants,
or the CONTRACTOR to accommodate changes in the WORK or to mitigate the
effect of events which may delay performance or completion. The CITY will monitor
and optimize the use of float for the benefit of the Program.
B. The CONTRACTOR shall adjust or remove any float suppression techniques (e.g.,
preferential sequencing, crew movements, equipment use, form reuse, etc.),
extended durations, imposed dates and others, as a prerequisite to a request for an
increase in Contract Price or Contract Time. Use of constraints should be minimized
and require approval by the CITY.
1.06 EARLY COMPLETION:
A. An early completion schedule is one which anticipates completion of all or specified
part of the work ahead of the corresponding Contract Time. Since Contract float
belongs to the project, the CONTRACTOR shall not be entitled to any extension in
Contract Time or recovery for any delay incurred because of extensions in an early
completion date until all contract float is used or consumed and performance or
completion of the WORK extends beyond the Contract Time.
1.07 NON-COMPLIANCE:
A. The CITY shall refuse to recommend/authorize progress payment if, in the CITY’S
opinion, the CONTRACTOR’S failure, refusal or neglect to provide the required
schedule information precludes the proper evaluation of the CONTRACTOR’S
progress. Remedies for the CONTRACTOR’S failure, neglect or refusal to comply
with the requirements of this Section are in addition to, and not in limitation of, those
provided under other sections of the Contract.
PART 2 - PRODUCTS
2.01 GENERAL CRITERIA:
A. All Construction Schedules shall be prepared by the CONTRACTOR and reflect the
CONTRACTOR’S plans, means and methods, techniques and sequences for
performing of the work.
B. The Contract Schedules shall break down the work into distinct activities with
interdependencies to the extent required to clearly depict the planned approach for
completion of the WORK and to effectively manage the execution of the Work. The
contract Schedules shall divide the WORK into manageable and logical segments
and specify the progression from the Notice to Proceed to Final Acceptance within
Contract Time. The Construction Schedule is to include appropriate time allowances
for submittals, procurement, coordination with others, construction, start-up and
01310 - 3/6
performance testing. Site-related activities shall not reflect a combination of work
located in separate structures, work corresponding to different divisions of the
specifications, work performed by first and second tier subcontractors or rough in
and finish work of the same trade.
C. The CONTRACTOR’S Construction Schedule shall reflect the timely delivery of all
permanent materials. Procurement activities should include preparation, review and
acceptance of shop drawings, material fabrication and material deliveries.
D. The CONTRACTOR shall schedule any requirements (such as submittal reviews) of
the CITY, the DESIGN CONSULTANT and others (performing work for the CITY)
indicated in, or required by the Contract Documents. The Construction Schedule
shall incorporate appropriate activities and work sequences based on the Contract
Documents.
2.02 COST LOADING:
A. Each activity in the Contract Schedules shall be assigned a dollar value in
accordance with the physical value of that work in relationship to the Schedule of
Values. The total budget value of all activities shall equal the Contract Price as
broken down by the Schedule of Values per Section 00300. The CONTRACTOR
shall also indicate the estimated duration for each construction activity and material
quantities for all activities.
B. If the WORK includes items covered by allowances, the CONTRACTOR shall cause
that work to be done within the limits of the Contract Time. The Construction
Schedule shall incorporate the CONTRACTOR’S best estimate of the activities and
logic associated with the allowances.
2.03 CONSTRUCTION SCHEDULE SUBMITTAL:
A. The Construction Schedule submittal is to consist of a Detailed Construction
Schedule Graphic Report, Schedule Narrative report, and an electronic copy of the
schedule data.
B. Construction schedule shall include the City holidays as holidays and no major work
should be scheduled for these holidays.
C. The Schedule Narrative Report shall consist of a written description of how the work
will be accomplished in accordance with the planned Construction Schedule. The
Schedule Narrative accompanying each Schedule Update shall, at a minimum,
compare current early dates against baseline dates for all milestones and
discussions of progress and/or delays. It shall provide sufficient detail to allow the
CITY to verify the progress of the WORK, compare actual versus planned activities,
identify assumptions made in scheduling change order work, describe actual or
potential delays and related causes, define steps taken to mitigate delay impacts and
itemize any proposed changes in network activities and logic. The CONTRACTOR
shall direct specific attention, in writing, to adjustments or corrections made, either in
response to the CITY’S comments on the previous submittal or otherwise.
D. The Schedule Narrative shall include cost data on monthly and cumulative totals for
all items depicted in the Schedule of Values as statuses in the current revision of the
Construction Contract Schedule. There shall be an additional report required to
account for stored materials utilizing the specified Stored Materials Report form.
01310 - 4/6
E. The Construction Schedule Graphic Report shall be in bar chart format, plotted on a
time-scaled calendar. This report will expressly identify Contract Time, milestones,
critical path(s), and all activities not completed as of the previous report submission.
Activities shall display early dates and total float. Whether on the same sheet or on
different sheets, this report shall identify both predecessor and successor driving or
critical relationships. Activity data shown on the graphic report shall include a short
description of the work, activity duration, remaining duration (for monthly schedule
updates), activity start and finish dates, budget and actual earned value, and be
sorted in an order that facilitates reading and following the progress of the scheduled
work.
F. Prior to each schedule update submittal the CITY and the CONTRACTOR will agree
upon the physical progress of the WORK (Percent Complete of each activity) and the
value of the scheduled work in place.
G. The CONTRACTOR shall provide six copies of each Construction Schedule
Submittal. The CONTRACTOR’S Construction Schedule shall bear the
CONTRACTOR’S stamp of approval signed by the CONTRACTOR. The
CONTRACTOR’S stamp of approval shall constitute a representation to the CITY
that the CONTRACTOR has determined or verified all data on that CONTRACTOR’S
Construction Schedule and assumes full responsibility for having done so. The CITY
will review and return to the CONTRACTOR two copies of the CONTRACTOR’S
Construction Schedule stamped as either “Revise and Resubmit”, “Accepted as
noted”, or “No Exceptions Taken”. The CITY’S review shall not extend to the
CONTRACTOR’S means, methods, or techniques, the correctness of which shall
remain the sole responsibility of the CONTRACTOR.
H. All schedules shall be in accordance with the Contract Time requirements of the
contract. Neither the CITY’S review of a schedule, nor the CITY’S statement of “No
Exceptions Taken”, will relieve the CONTRACTOR from responsibility for complying
with Contract Time requirements, adhering to those sequences of work indicated in
or required by the contract documents, or from completing any omitted work within
the Contract Time.
I. Acceptance by the CITY of the Construction Contract Schedule and Construction
Schedule Updates shall be a CONDITION PRECEDENT to the processing of
Applications for Payment after the first 30 days of the Contract.
2.04 INITIAL AND REVISED CONSTRUCTION CONTRACT SCHEDULE:
A. Within 10 days of Notice to proceed, the CONTRACTOR shall submit their Initial
Construction Contract Schedule Submittal to the CITY for review and acceptance. It
will be reviewed for constructability and conformance to the requirements of the
Contract Documents. If the schedule is not accepted and requires revisions, the
CONTRACTOR will, within 5 calendar days, revise this Initial Construction Contract
Schedule and resubmit it for review and acceptance.
B. Once the Initial Construction Contract Schedule is reviewed and accepted, it
becomes the CONTRACTOR’S Revision 0 Construction Contract Schedule and it
becomes the baseline schedule for the WORK and is the basis for monitoring the
CONTRACTOR’S progress against milestones and Contract Time, and the
evaluation and reconciliation of extensions in Contract Time. From then on, all
activities and their relationships may not be changed, added, or deleted without the
prior consent of the CITY. The CONTRACTOR’S Revision 0 Construction Contract
01310 - 5/6
Schedule must be revised when it is no longer useful as a status and control
mechanism as determined by the CITY. All changes must be coordinated with and
approved by the CITY. Contract Time (including all contracted milestones) cannot be
changed without a formal Change Order approved by the CITY. Each subsequent
accepted Revised Construction Contract Schedule will be numbered sequentially
higher by one (1), with the first revision being the Revision 1 Construction Contract
Schedule
C. When the time comes that Revision # Construction Contract Schedule is required, a
new revised Construction Contract Schedule will be submitted in accordance with
change procedures, for review and acceptance by the CITY. Construction Schedule
Revisions shall accurately reflect all approved Change Orders including the exact
duration and cost. It will be reviewed for constructability and conformance to the
requirements of the Contract Documents as amended by Change Orders. If the
schedule is not accepted and requires revisions, the CONTRACTOR will, within 10
business days, revise this Initial Construction Schedule and resubmit it for review
and acceptance. Re-submittals shall use the same revision number followed by
letters as “A”, “B”, etc., as needed to distinguish the submittal as revised from the
previous...
2.05 SCHEDULE UPDATES:
A. A Schedule Update is submitted by the CONTRACTOR each month based upon the
current accepted revision of the Construction Contract Schedule. It will indicate
actual performed work and work forecast through project completion. The actual
schedule data shall record when work was performed. Forecast data will be
calculated by the schedule and indicate how the CONTRACTOR intends to complete
the remaining Work within Contract Time. The Schedule Update submittal will be in
the form explained above.
PART 3 - EXECUTION
3.01 MONTHLY UPDATE CYCLE:
A. Schedule Update Submittals are due monthly on the 28th day of the month with a
data date of the 27th and are to be attached to each Application for Payment.
3.02 CHANGES:
A. Within ten (10) days after a schedule problem is identified by either contractor or
CITY, or at any time the percentage of the dollar value for completed work is 10
percent or more or less than the value of the scheduled work, the CONTRACTOR
shall submit a Construction Contract Schedule Revision that identifies the cause of
the Change and any actions required by the CONTRACTOR to recover the schedule
and complete the Work within Contract Time. The CONTRACTOR shall promptly
undertake appropriate action, at no additional cost to the CITY, to recover the
schedule whenever the current schedule shows that the CONTRACTOR did not or
can not achieve a milestone established in the Contract.
B. Appropriate recovery actions include, but are not limited to, assignment of additional
labor, subcontractors, equipment, shift or overtime work, expediting of submittal or
deliveries, or any combination of thereof. Overlapping of activities or sequencing
changes shall be deemed appropriate only if properly substantiated in the submittal.
01310 - 6/6
Recovery plans that require a change in the Construction Contract Schedule must be
submitted as a Revision in accordance with this specification.
C. The CONTRACTOR’S refusal, failure or neglect to take appropriate recovery action
or to submit a written recovery statement shall constitute reasonable evidence that
the CONTRACTOR is not prosecuting the WORK, or separable part, with the
diligence that will ensure its completion within the Contract Time. Such lack of action
shall constitute sufficient basis for the CITY to recommend the withholding of some
or all of any payment due and/or shall be considered grounds for termination of the
contract by the CITY in accordance with Article 15 of the General Condition.
END OF SECTION