HomeMy WebLinkAboutSection 01630 Product Ops and Subsitutions 01630 - 1/2 SECTION 01630 PRODUCT OPTIONS AND SUBSTITUTIONS PART 1 - GENERAL 1.01 SUMMARY: This Section covers the Engineer's review procedures for Contractor's requests of acceptable substitute items of material and equipment. All requests must be received by the City's Procurement Division ten (10) days prior to the scheduled bid opening date. See applicable paragraph of the Instructions to the Bidders of this Contract Document. If the proposed substitution is approved, such approvals will be set forth in an addendum. Requests received after the date established above or after the contract award, will not be considered unless one or more of the following conditions apply: A. The substitution must be required for compliance with final interpretation of code requirements or regulations. B. The substitution must be due to the unavailability of the specified products, through no fault of the Contractor. C. The substitution may be requested when subsequent information discloses the inability of the specified products to perform properly or to fit in the designated space. D. The substitution may be requested when in the judgement of the Engineer a substitution would be substantially to the City's best interests in terms of cost, time or other considerations. 1.02 SUBSTITUTION REQUEST: A. Submit as required in SECTION 01300 Submittals: 1. Complete data substantiating compliance of the proposed substitution with the Contract Document. a. Product identification including manufacturer's name and address. b. Manufacturer's literature including product description, performance and test data, and reference standards. c. Name and address of similar projects on which product was used and dates of installation. 2. Itemized comparison of proposed substitution with product or method specified. 3. Data relating to changes in the construction schedule. 4. For requests submitted after bids are received, accurate cost data on proposed substitution in comparison with product or method specified. B. In submitting the request for substitution, the Contractor makes the following representations: 1. The Contractor has investigated the proposed product and has determined that it is equal or superior in all respects to that specified. 2. The Contractor will provide the same warranty or guarantee for the substitution as for the product specified. 3. The Contractor will coordinate installation of the accepted substitution into the work, making such changes as may be required for the work to be completed in all respects. 01630 - 2/2 4. The Contractor waives all claims for additional costs related to substitution that subsequently becomes apparent. 5. Cost data is complete and includes all related costs under the contract. 1.03 ENGINEER'S REVIEW: The Engineer, in evaluating the request for substitution, will consider all variations of the proposed substitute from that specified to determine the acceptability of the proposal. The Engineer may require the Contractor to furnish additional data about the proposed substitute necessary to make such a determination. The Engineer will be the sole judge of acceptability, and no substitute will be ordered or installed without the Engineer's prior written acceptance. The City may require the Contractor to furnish, at the Contractor's expense, a special performance guarantee or other surety with respect to any substitute. Substitutions will not be considered if: A. Substitutions are indicated or implied on shop drawings or product data submittals without a request submitted in accordance with this section. B. Acceptance will require substantial revision to the Contract Documents. END OF SECTION