HomeMy WebLinkAboutSection 01720 As-Builts 01720 - 1/3 SECTION 01720 AS-BUILT DOCUMENTS PART 1 - GENERAL A. CONTRACTOR shall maintain and provide the ENGINEER with record documents as specified below, except where otherwise specified. B. Maintenance of Documents: 1. Maintain in CONTRACTOR'S field office in clean, dry, legible condition complete sets of the following: Drawings, Specifications, Addenda, approved Shop Drawings, Samples, photographs, Change Orders, other modifications of Contract Documents, test records, survey data, Field Orders, and all other documents pertinent to CONTRACTOR'S Work. 2. Provide files and racks for proper storage and easy access. File in accordance with filing format of Construction Specification Institute (CSI), unless otherwise approved by ENGINEER. 3. Make documents available at all times for inspection by ENGINEER and OWNER. 4. As-built documents shall not be used for any other purpose and shall not be removed from the CONTRACTOR'S office without ENGINEER'S approval. C. Marking System: Provide colored pencils or felt tipped pens for marking changes, revisions, additions and deletions, to the record set of Drawings. Use following color code unless otherwise approved by the ENGINEER: 1. Process and Mechanical: Red 2. Other Printed Notations: Black D. Recording: 1. Label each document "PROJECT AS-BUILTS" in 2-inch high printed letters. 2. Keep record documents current. 3. Do not permanently conceal any Work until required information has been recorded. 4. Drawings: Mark-up actual installations, which vary substantially from the work as originally shown. Mark whichever drawing is most capable of showing the as-built condition fully and accurately; however, where shop drawings are used for mark- up, record a cross-reference at the corresponding location on the contract drawings. Mark-up new information, which is recognized to be of importance to the OWNER, but was not shown on either the contract drawings or shop drawings. Give particular attention to concealed work, which would be difficult to measure and record at a later date. Note related change order numbers where applicable. Organize as-built drawing sheets into manageable sets, bind with durable paper cover sheets, and print suitable titles, date and other identification of the cover of each set. The following minimum information shall be included, as applicable: a. Depths of various elements of foundation in relation to datum. b. Horizontal and vertical location of underground utilities and appurtenances referenced to permanent surface improvements. c. Location of internal utilities and appurtenances Concealed in construction referenced to visible and accessible features of structure. 01720 - 2/3 d. Field changes of dimensions and details. e. Changes made by Change Order or Field Order. f. Details not on original Drawings. g. information to be shown for potable water mains, reuse water mains, and sanitary force mains shall include the location of valves, tees, bends and crosses dimensioned to the baseline survey or monument, including the station and offset. Elevations at top of pipe shall be provided every 50' and at locations where design elevations were shown on the plans. For situations where the pipeline is being adjusted to avoid conflicts with other utilities (less than 50' in total length), then elevations shall be provided at the beginning of the deflection (i.e. the first bend), middle of the deflection (i.e. the point where the conflict would have occurred with the utility), and the end of the deflection (i.e. the last bend). h. Information to be shown for gravity sanitary sewer mains shall include invert elevations at manholes. i. information regarding all trenchless technologies horizontal and vertical location including bore/jacking, micro tunneling, and directional drilling. All as- built drawings shall show the geometry, horizontal, and vertical location of the directional drill path including the starting point, end point, and resulting curvatures. 5. Specifications and Addenda: Legibly mark up each Section to record: a. Manufacturer, trade name, catalog number, and supplier of each product and item of equipment actually installed. b. Changes made by Change Order or Field Order. c. Other matters not originally specified. E. Submittal: 1. Upon Substantial Completion of the Work, deliver record drawings to ENGINEER. Final payment will not be made until satisfactory "as-built' drawings are received by ENGINEER. 2. Accompany submittal with transmittal letter containing: a. Date. b. Project title and number. c. CONTRACTOR'S name and address. d. Title and number of each record drawings. e. Certification that each document as submitted is complete and accurate. f. Signature of CONTRACTOR, or his/her authorized representative. 3. Final Surveys -The CONTRACTOR shall provide the ENGINEER with two signed and sealed copies by a registered land surveyor and a CD of the final survey in a digital format compatible with Auto CAD 2000 software. 4. CADD Files -The CONTRACTOR shall provide a CD of the "as-built" drawings in a digital format compatible with AutoCAD 2000 software. 5. The CONTRACTOR must submit partial plot files or hard copies of As-Built drawings showing completed work with each partial payment requisition. F. The CONTRACTOR shall be held responsible for the accuracy of such data and shall bear any costs incurred in finding utilities as a result of incorrect data furnished by the CONTRACTOR. 01720 - 3/3 PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION