HomeMy WebLinkAboutReso 2010-1551
-
RESOLUTION NO. 2010 - ----LS5.L
A RESOLUTION OF THE CITY COMMISSION OF THE CITY
OF SUNNY ISLES BEACH, FLORIDA, APPROVING CHANGE
ORDER NO. 1 AND 2 TO AGREEMENT WITH TENEX
ENTERPRISES FOR CHANGE IN LANDSCAPING AND FOR
ADDITIONAL SIDEWALK AND LANDSCAPE WORK IN AN
AMOUNT NOT TO EXCEED SEVENTY -FIVE THOUSAND SIX
HUNDRED SIXTY-EIGHT DOLLARS AND SEVENTY-FIVE
CENTS ($75,668.75), ATTACHED HERETO AS EXHIBIT "A";
AUTHORIZING THE CITY MANAGER TO DO ALL THINGS
NECESSARY TO EFFECTUATE THIS RESOLUTION;
PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the City Commission has long desired to have a consistent streetscape
theme along Collins Avenue.
WHEREAS, on October 29,2009 via Resolution No. 2009-1495 the City entered into
a contract with Tenex Enterprises for the construction for the 183rd Street streetscape
improvement and 175th Street median closing for an amount not to exceed Four Hundred
Eighty-Seven Thousand Six Hundred Thirty-Four Dollars ($487,634.00); and
WHEREAS, the City now desires to expand the scope of work in the contract to
increase the height of the Mejool Palms and to continue the paver sidewalk from the end of the
183rd Street streetscape project to 178th Street; and
WHEREAS, Tenex Enterprises, has expressed its ability and desire to provide these
services and provided the City with a proposal for these services in an amount not to exceed
Seventy-Five Thousand Six Hundred Sixty-Eight Dollars and Seventy-Five Cents
($75,668.75); and
WHEREAS, the City wishes to approve Change Order No. 1 and 2 to the Agreement
with Tenex Enterprises to provide these services for the construction of the streetscape
improvements in an amount not to exceed Seventy-Five Thousand Six Hundred Sixty-Eight
Dollars and Seventy-Five Cents ($75,668.75), attached hereto as Exhibit "A", bringing the
total contract amount not to exceed Five Hundred Sixty-Three Thousand Three Hundred Two
Dollars and Seventy-Five Cents ($563,302.75); and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF
THE CITY OF SUNNY ISLES BEACH, FLORIDA, AS FOLLOWS:
Section 1. Approval of Change Order No. 1 and 2 to Agreement. Change Order No. 1
and 2 to Agreement with Tenex Enterprises, to add Seventy-Five Thousand Six Hundred
Sixty-Eight Dollars and Seventy-Five Cents ($75,668.75) to the 183rd Street streetscape
improvement and 175th Street median closing project, in an amount not to exceed Five
Hundred Sixty-Three Thousand Three Hundred Two Dollars and Seventy-Five Cents
($563,302.75) for the additional construction to the 183rd Street streetscape improvements,
attached hereto as Exhibit "A", be and the same, is hereby approved.
Section 2. Authorization of City Manager. The City Manager is hereby authorized to do
all things necessary to effectuate this Resolution.
Section 3.
Effective Date. This Resolution will become effective upon adoption.
PASSED AND ADOPTED this 15th day of April 2010.
'~ i i
,.
ATTEST:
:.:'~~
Jane A. Hines, CMC, City Clerk
"
., "
Vote: oS - 0
Mayor Edelcup
Vice Mayor Thaler
Commissioner Brezin
Commissioner Goodman
Commissioner Scholl
Moved by:
('b~ Sc:.~OLL-
y\U ~~V ~AL'i.R
Seconded by:
V(Yes)
V(Y es)
V (Yes)
-----LL(Y es)
~(Yes)
_(No)
_(No)
_(No)
_(No)
_(No)
CITY OF
SUNNY ISLES BEACH
CHANGE
ORDER
CHANGE ORDER NUMBER: ,
BID NUMBER: 09-09-01
RESOLUTION NUMBER:
DATE: 02/23/2010
PROJECT:
Median Closure at NE 175th Terrace on
Collins Avenue/SR AlA
ORIGINAL DOLLAR CONTRACT AMOUNT: $487,634.00
NETTOTAL DOLLAR VALUE OF ALL PREVIOUS CHANGE ORDERS: $0
DOLLAR AMOUNT OF THIS CHANGE ORDER: $32,397.75
THIS: o INCREASES o DECREASES 0 DOES NOT CHANGE THE CONTRACT AMOUNT
NEW DOLLAR CONTRACT AMOUNT: $520,031.75
ORIGINAL CONTACT COMPLETION DATE 06/12/2010
TOTAL OF PREVIOUS CHANGE ORDER DAYS: 0
AMOUNT OF DAYS PER THIS CHANGE ORDER: 0
NEW CONTRACT COMPLETION DATE: 06/12/2010
I DESCRIPTION OF SCOPE OR WORK CHANGES:
. - . . InGreased the- height-of- the- MedjGGI. Date .Palms-fmm-l1' CT.- tG 14'.C-T.
NOTE: Unless specifically stated clearly elsewhere on this page, this change order does NOT include an extension
of time or grant any additional general conditions amounts. The City and the Contractor agree that the contract
time adjustment and sum agreed to in this document constitute a full and complete settlement of the matters set
forth herein, including all direct and indirect costs for equipment, manpower,. materials, overhead, profit and delay
relatin to the issues set forth in this document.
CONTRACTOR: --,e"e
CITY ATTORNEY:
Hans Ottinot
PROJECT MANAGER:
CTIY OFFICIAL:
Jor e Vera
-
11.1Itlf~~~~
8.S0 S. VV. 14th Courl . l'ompmlO Beach, FIOIida 33060
Phone: (954) 788-8100 . Fax: (954.) 788-0005
REQUEST FOR CHANGE ORDER # 2
TO: Mr. Jorge Vera
City of Sunny Isles Beach
18070 Collins Avenue
Sunny Isles Beach, FL 33160
DATE: February 23,2010
OWNER: City of Sunny Isles Beach
PROJECT: Medlen C/ruure (NE 17~th Terr/183rd SO Cell/ns Ave
PROJECT No: 09.09-01
SCOPE: I Landscape Revision
Description
Per Owner Directive, Upgrade * of Thirty (30) Phoenix dactylifera "Medjool date palm" from 11' C. T. to 14'
C. T. (Complete In Place + Warranty)
*Includes a replanting fee of $300. 00 for each 11' CT tree that has been purchased.
Total Amount Requested for Change Order #2
$
32,397.75
Note: Except as qualified above, all changes to work to be performed under the same terms and conditions
as the base contract.
WE AGREE to modify the original contract by the following CHANGE ORDER amount:
$ 32,397.75
with -_- additional days to complete this work
Signature:
Date:
Authorized Tenex Enterprises, Inc.
-Representative . -
ACCEPTED: The above prices and specifications of this Request for Change Order are satisfactory and
are hereby accepted. Tenex Enterprises, Inc., will perform above stated work under the same terms and
conditions as specified in original contract unless oterhwise noted. Additional work is to be paid for under
the same terms and conditions of the existing contract.
Signature:
Date:
Authorized Owner
Representative
-
Ilt~l~f~~~~
850 S. 'V. 14th Court. Pompano Bellch, 1110rida 33060
Phonc; (95,1) 788.8100 . F:l": (95-1) 788-0005
.. .......;:...'1?:9" ({:.... . .....:..... >i .....i-..:,;-:..;: :'''..
';:.
A LABOR $ -
B MATERIALS & SUPPLIES $ -
C EQUIPMENT $ -
D SUBCONTRACTOR WORK $ 28,050.00
ISUBTOTAL A) THROUGH D) $ 28 050.00
E) CONTRACTOR OVERHEAD (SUBCONTRACTOR) (5%) $ 1 402.50
F) CONTRACTOR PROFIT (10%) $ 2,945.25
G) GENERAL LIABILITY INSURANCE AND BOND (1%) -
TOTAL COST OF INCREASE, DECREASE $ 32,397.75
OR ALTERATION IN WORK
REQUEST FOR CHANGE ORDER # 2
COST ESTIMATE FOR INCREASE, DECREASE OR ALTERATION IN THE WORK
A) LABOR
LABOR SUBTOTAL
LABOR MARKUP 15%
LABOR TOTAL
NOTE:
· Includes Labor Cost & Burden
B) MATERIALS & SUPPLIES
MATERIALS & SUPPLIES SUBTOTAL
MATERIALS & SUPPLIES MARKUP 15%
MATERIALS & SUPPLIES TOTAL
C) EQUIPMENT
EQUIPMENT SUBTOTAL
EQUIPMENT MARKUP 15%
EQUIPMENT TOTAL
$
$
$
$
D) SUBCONTRACTOR
LUKES.'~}SAWGRASS LANDS'CARING:<:;:".:{':- ::..-::&{iTt#l~:!ftf::,:~.;<':'::::: ~:""::i";:".."..:. :::':'i,;:~;:<;~.} ...,?:::?<t;~~:hn:"tt:ir?~:>.
fVfATERJAL'.<.',:::'T"'-'S':, .. .::':>~'".j.:i:':.i,' QUANTITY" .: .:.:UNIT>.'!:W' ':UNITCOSD
Upgrade' of Thirty (30) Phoenix dac~ifera
'Medjool date palm' from 11' C.T. to 14'
C.T. (Complete In Place & Warranty)
30
EA
$
935.00 $
28,050.00
SUBCONTRACTOR SUBTOTAL $ 28,050.00
SUBCONTRACTOR MARKUP (-) $ -
SUBCONTRACTOR TOTALI $ 28,050.00
Change Order 2
20f2
CO #2labor
...
CITY OF
SUNNY ISLES BEACH
CHANGE
ORDER
CHANGE ORDER NUMBER: a
BID NUMBER: 09-09-01
RESOLUTION NUMBER:
DATE: 03/25/2010
PROJ ECT:
Median Closure at NE 175th Terrace on
Collins Avenue/SR AlA
ORIGINAL DOLLAR CONTRACT AMOUNT: $487634.00
NETTOTAL DOLLAR VALUE OF ALL PREVIOUS CHANGE ORDERS: $32,397.75
DOLLAR AMOUNT OF THIS CHANGE ORDER: $43,271.00
THIS: o INCREASES o DECREASES 0 DOES NOT CHANGE THE CONTRACT AMOUNT
NEW DOLLAR CONTRACT AMOUNT: $563,302.75
ORIGINAL CONTACT COMPLETION DATE 06/12/2010
TOTAL OF PREVIOUS CHANGE ORDER DAYS: 0
AMOUNT OF DAYS PER THIS CHANGE ORDER: 0
NEW CONTRACT COMPLETION DATE: 06/12/2010
DESCRIPTION OF SCOPE OR WORK CHANGES:
- - - - - - -Additional-er-iGk-paver-wor-k-to extend-the-pr-ojeGt-south-to-1-78tllStreet.-AII-pr-iGing-at-the- unit-- - - - - - - -
costs pursuant to the contract.
NOTE: Unless specifically stated clearly elsewhere on this page, this change order does NOT include an extension
of time or grant any additional general conditions amounts. The City and the Contractor agree that the contract
time adjustment and sum agreed to in this document constitute a full and complete settlement of the matters set
forth herein, including all direct and indirect costs for equipment, manpower, materials, overhead, profit and delay
relatin to the issues set forth in this document.
CONTRACTOR:
CITY ATTORNEY:
Hans Ottinot
PROJECT MANAGER:
CITY OFFICIAL:
Jor e Vera
l Page 1 of 1 J
Untitled Message
~
Bill Evans
Sent: Wednesday, March 17, 2010 7:56 AM
To: jvera@sibfl.net
Cc: Hamid Fouladi
Jorge,
The price breaks out as follows for the additional work requested on Collins Ave. up to 178th street. Keep In mind
these are only estimated quantities.
1. MOT @ LS = $15,000.00
2. Clearing and Grubbing @ LS = $5,000.00
3. Removal of concrete 389 SY @ 6.00 = $2,334.00
4. Required base 389 SY @ 8.00 =$ 3,112.00
5. Pavers set on sand 3500 SF @ 4.75 = $16,625.00
6. Pavers set on concrete 200 SF @ 6.00 = $1,200.00
Total = $ 43,271.00
These prices are based on line item prices in the current contract. Let me know if you have any questions.
Thanks
Bill Evans
Tenex Enterprises, Inc.
850 SW 14th Court
Pompano Beach, FL 33060
954.788.8100 Office Phone
- - - - --954-.788~0005-Fax------------ ------------
This message contains confidential infonnation and is intended only for the individual named. If you are not the named
addressee you should not disseminate, distribute or copy this e-mail. Please notifY the sender immediately bye-mail if you
have received this e-mail by mistake and delete this e-mail from your system. E-mail transmission cannot be guaranteed to be
secure or error-free as infonnation could be intercepted, corrupted, lost, destroyed, arrive late or incomplete, or contain
viruses. The sender therefore does not accept liability for any errors or omissions in the contents of this message, which arise
as a result of e-mail transmission. If verification is required please request a hard-copy version.
https://mail.hostaccount.com/owa/?ae=Item&t=IPM.N ote&id= RgAAAABmkG2pNhS7Sb... 3/25/2010
City of Sunny Isles Beach
18070 Collins Avenue
Sunny Isles Beach, Florida 33160
(305) 947-0606 City Hall
(305) 949-3113 Fax
MEMQJiAND_UM
TO:
The Honorable Mayor and City Commission
FROM:
Jorge L. Vera, Assistant City Manager Service Division
DA TE:
4/15120 I 0
RE:
Change Orders #1 and #2 to Tenex Enterprises contract
RECOMMENDA TION:
Staff recommends approval of the attached resolution.
REASONS:
The City Commission entered into a contract for the construction for the 183rd Street
streetscape improvement. The City desires to expand the scope of work under the
contract. Tenex Enterprises has expressed its ability and desire to provide the additional
services and has provided a proposal to perform the services.
This resolution is composed of 2 change orders. Change order number I is for the cost of
the increase in height to the mejool palms on the 183rd Street streetscape
project. Change order number 2 is to continue the paver sidewalk from the end of the
183rd Street streetscape project up to 178th Street. The cost for the additional work is
for an amount not to exceed $75,668.75, bringing the total contract to an amount not to
exceed $563,302.75.
FUNDING SOURCE:
Funding for this project comes from account no. 20-600-5621.
ATTACHMENTS:
. Resolution
. Change Order
Agenda Item No.1 OF
Date 4/15/20 I 0
90