RESOLUTION NO. 2006-~
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
SUNNY ISLES BEACH, FLORIDA, APPROVING CHANGE ORDER NO.
1 TO AGREEMENT WITH SIL TEK GROUP, INC., IN THE AMOUNT OF
THIRTEEN THOUSAND ONE HUNDRED SIXTY-SIX DOLLARS AND
SIXTY-SEVEN CENTS ($13,166.67) FOR THE CONSTRUCTION OF THE
181sT DRIVE ACTIVE PARK; AUTHORIZING THE CITY MANAGER
TO DO ALL THINGS NECESSARY TO EFFECTUATE THIS
RESOLUTION; PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the City of Sunny Isles Beach wishes to develop the 18 I sl Drive Active Park
located at 181 15 North Bay Road and publicly advertised Bid No. 05-04-0 I for the construction
of the 18 I sl Drive Active Park; and
WHEREAS, on July 14, 2005, pursuant to Resolution No. 2005-814, the City
Commission awarded Bid No. 05-04-01 to Siltek Group, Inc. ("Siltek"), who was determined to
have the lowest and most responsive, responsible bid, in the amount of $7,154,303.05, and
authorized the City Manager to negotiate and enter into an agreement with Siltek; and
WHEREAS, on September 8, 2005, pursuant to Resolution No. 2005-825, the City
Commission ratified the execution of an agreement with Siltek Group, Inc., in the amount of
$7,186,423.05; and
WHEREAS, it has been determined that additional testing is required on production piles
and augercast test piles, and the engineer of record Miller Legg and Calvin Giordano, and
Associates, have reviewed and approved Change Order No. I submitted by Siltek Group, Inc., for
the testing, in the amount of $13,166.67, bringing the total contract amount to $7,199,589.72,
attached hereto as Exhibit "A".
NOW THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF SUNNY ISLES BEACH, FLORIDA, AS FOLLOWS:
Section 1. Incorporation of Recitals. The recitals set forth in this resolution are incorporated
herein by reference as if fully set forth herein.
Section 2. Approval of Change Order No.1. Change Order No. I with Siltek Group, Inc.,
for the construction of the 181 st Drive Active Park, attached hereto as Exhibit "A", in an amount
of Thirteen Thousand One Hundred Sixty-Six Dollars and Sixty-Seven Cents ($13, I 66.67), be
and the same, is hereby approved.
Section 3. Authorization of City Manager. The City Manager is hereby authorized to do all
things necessary to effectuate the terms of this Resolution.
Section 4.
Effective Date. This Resolution will become effective upon adoption.
PASSED AND ADOPTED this 16th day of February, 2006.
R2006-885 Sillek Group Co I Active Pk
Page I of2
ATTEST:
.~A-~
Jane A. Hines, CMC, City Clerk
APPROVED AS TO FORM
AND LE L SUFFICIENCY:
Moved by: C1~ 'fH JtH.Ut<.
Seconded by: ~)'t'WN. ~tJW~ G6()Dm~1tJ
Vote: 5-0
Mayor Edelcup
Vice Mayor Brezin
Commissioner Goodman
Commissioner Iglesias
Commissioner Thaler
V(Yes)
t.,.../(Y es)
---V(Y es)
~(Y es)
z:;;7 (Yes)
_(No)
(No)
_(No)
_(No)
_(No)
R2006- Change Order 1, Siltek Group
2
Ci-t~NGE ORDER
AlA DOCUMENT G701
OWNER: 0
ARCHITECT: 0
CONTRACTOR: [Xl
FIELD ORDER: 0
OTHER: 0
PROJECT:
181st Drive Active Park
18115 North Bay Road
Sunny Isles Beach, Florida
TO CONTRACTOR:
SILTEK GROUP, INC.
4403 Dogwood Circle
Weston, FL 33331
CHANGE ORDER No.:
1
CHANGE ORDER DATE:
December 23, 2005
ARCHITECT'S PROJECT No.:
114122
CONTRACT DATE:
October 8, 2005
CONTRACT FOR:
1$7,186,423.05
The Contract is changed as follows:
1. One compression and one tension load test for augercast test piles. $6,475.00
2. Production pile installation monitoring. $5,260.00
(Refer to attached break down from Nutting Engineering)
SUB-TOTAL $11,735.00
10% P & 0 $1,173.50
SUB-TOTAL $12,908.50
2% Bond $258. '17
SUB-TOTAL $13,166.67
TOTAL OF THIS CHANGE ORDER No.1: $13,166.67
--
This Change Order is NOT VALID UNTIL EXECUTED by the OWNER, ARCHITECT and CONTRAC1'OR
Original Contract Sum: I
Net change by previously authorized Change Orders:
Revised Contract Sum prior to this Change Order:
Amount of this Change Order No. 1
Revised Total Contract Sum including this Change Order:
The Contract Time will be changed 0
The revised date of Substantial Completion as of the date of this Change Order:
$7,186,423.051
$0.00
$7,186,423.05
$13,166.67
$7,199,589.72
Days
January 14, 2007
Note: This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have
been authorized by Construction Change Directive.
By:
By:
(Printed Name)
Title: e~~C:c M~
Date: ~. Or,
Printed: 1/3/2006 3:58 PM
GENERAL CONTRACTOR
SlItelt Group, Inc.
4403 Dogwood Circle
Weston, FL 33331
~
By: J t'Y ~.-qs
(Printed Name)
OWNER
City of Sunny Isles
18070 Collins Ave
Sunny Isl each, FL 33160
8'
(Signature)
BY; ~ ~(.brr G()M~~
(P(inted Name) (j)
Title: ~ fiGOlNL (AfI'AL ~
Date: _l= \ ~ ~ 0 '"
Title:
(J{2/D 0 ecJ VYtYt}M)~
d ~ l ~(p
Date:
Page 1 of 1
AlA Change Order Form 13701 181 Change Order 1
J. -:r:U..L J. I.:.J\:JL..
['-0:..1.1
December 21 , 2005
Mr. Jay Zayas
Siltek Group
4403 Dogwood Circle
Weston, Florida 33331
Tel: 954-217-6829
Fax: 954-217-1728
Subject:
Proposal for Pile Load Test and
Pile Installation Monitoring
Proposed Gymnasium at 2- Acre Park
181 st Drive and North Bay Road
Sunny Isles Beach, Florida
Dear 1\1r. Zayas:
Nutting Engineers of Florida, Inc. is pleased to present this proposal for performing augercast
pile load test and installation monitoring for the Proposed Gyninasium and Recreational Park
project in Sunny Isles Beach, Florida.
We understand that approximately 205 augercast piles will be installed for this project. We
understand that a pile load test will be performed in accordance Vv1.th the South Florida Building
Code to twice the design load. Nutting Engineers previously perfonned a geotechnical
exploration for this project, and our findings and recommendations are presented in a report
dated Jillle 16,2004.
Based on our understanding of the project, \ve propose the following scope of work and fee
schedule.
SCOPE OF WORK
We ...vill provide full-time monitoring of the installation of the test/reaction piles and production
augercast piles, provide instrumentation and direct the pile load test. Based on the results of the
pile load test, we will provide final installation criteria for the production piles. A log of each
pile will be kept and will include depth, size, grout take, 'steel reinforcement placed, and other
pertinent information. We have assumed approximately 20 piles per day ,",viII be installed during
production pile installation.
12-13-'05 17:38 FROM-nutting engIneers
3058248827
T-404 P002/004 F-756
December, 2005
Mrs. Susan Simmons
City of Sunny Isles Beach
18070 Collins Avenue
Swmy Isles Beach., Florida 33160
Tel: 305.792-1706
Fax: 305-792-1566
Subject:
Proposal for Pile Load Test and
Pile Installation Monitoring
Proposed Gymnasium at 2- Acre Park
181 st Drive and North Bay Road
Sunny Isles Beach, Florida
Dear Mrs. Simmons:
Nutting Engineers of Florida, Inc. is pleased to present this proposal for performing augercast
pile load test and installation monitoring for the Proposed Gymnasium and Recreational Park
project in Sunny Isles Beach; Florida
We understand that approximately 205 augercast piles will be installed for this project. We
understand that a pile load test will be performed in accordance with the South Florida Building
Code to twice the design load. Nutting Engineers previously performed a geotechnical
exploration for this project, and our findings and recommendations are presented in a report
dated June 16,2004"
Based on our understanding of the project, we propose the following scope of work and fee
schedule.
SCOPE OF WORK
We will provide full-time monitoring of the installation of the test/reaction piles and production
augercast piles, provide instnunentation and direct the pile load test. Based on the results of the
pile load test, we will provide final installation criteria for the production piles. A log of each
pile will be kept and will include depth, size, grout take, steel reinforcement placed, and other
pertinent information.
1~-1~-'~~ IJ;~~ fHUM-nuttlng engIneers
~~~1)~q1)1)[(
l-q~q r~~~/~~q ~-J~b
FEE SCHEDULE - TEST PILE INSTALLATION AND LOAD TEST
We understand that one compression and one tension load ~t Will be ~rformed as part of the
project. This will be performed for an estimated cost o~ $6,475.00 ~ased on the following
quantities and unit rates.
Engineering Services 30 @ $80.00 hr $2400.00
Test Pile Installation Monitoring
Set Up Pile Load Test, LoadlUnload Pile
Load Test Report and Installation Criteria 8 @ $80.00 hr $640.00
T echnician/Inspector 35 @ $50.00 hr $1750.00
Monitor Pile Load Test
Technician Overtime 25 @ $65.00 hr $1625.00
Grout Cubes - Cast, test, and report 1 @ $60.00 set $60.00
FEE SCHEDULE - PRODUCTION PILE INSTALLATION MONITORING
The production pile installation monitoring will be performed for an estimated cost of $5,260.00
based on the following unit rates and quantities:
T echnician/Inspector
Project ManagementIReport
Grout Cubes
80 @ $50.00 hr
12 @ $80.00 hr
5 @ $60.00 set
$4000.00
$960.00
$300.00
The above fee schedules are provided to give an estimate of the costs associated with the
monitoring/reporting of the installation of the production piles. The actual costs will be based on
the time required to install the piles, behavior of the pile load test, and other factors beyond ow:
control.
Thank you for providing us the opportunitY to present this proposal. We look forward to
working with you on this project.
Sincerely,
NUTTING ENGINEERS OF FLORIDA, INC-
Catalin Berindean
Geotechnical Engineer
Richard R. Wohlf(Uth, P.E.# 50858
Director of Engineering
OF SU'"
TO:
FROM:
DATE:
RE:
City of Sunny Isles Beach
18070 Collins Avenue
Sunny Isles Beach, Florida 33160
(305) 947-0606 City Hall
(305) 949-3113 Fax
(305) 947-2150 Building Department
(305) 947-5107 Fax
City Commission
Norman S. Edelcup, Mayor
Roslyn Brezin, Vice Mayor
Gerry Goodman, Commissioner
Danny Iglesias, Commissioner
Lewis J. Thaler, Commissioner
Police Chief Fred Maas, Interim City Manager
Hans Ottinot, City Attorney
Jane A. Hines, City Clerk
MEMORANDUM
Susan Simpson, Cultural & Human Services Director
Priscilla Walker, Deputy City Clerk"?uJ~
February 23, 2006
SiUek Active Park Construction Agreement - Change Order No.1
At its regular meeting of February 16, 2006, the City Commission adopted Resolution No.
2006-885, which approved Change Order No. I to the Active Park Construction Agreement with
Siltek. Attached are two (2) original agreements and two (2) copies of the approving resolution
to assist you in processing this item.
The remaining original has been placed with the original resolution.
Thank you.
:pw
Attachments
cc: Police Chief Fred Maas, Interim City Manager (memo only)
Hans Ottinot, City Attorney (memo only)
Jean Watson, Finance Director
Shaun Gelvez, Contracts Administrator
Siltek Acti\'e Park Agrmt Change Order 1 Reso Trans