SECTION 00900
Addendum No.1
to
Contract documents
CITY OF SUNNY ISLES BEACH
172ND STREET ROADWAY IMPROVEMENTS
CGA PROJECT NO. 03-4197
CITY BID NO. 07-05-01
To All Bidders:
Bidders for the above-referenced project shall take note of the following changes,
additions, deletions, clarifications, etc. to the Plans and Specifications. which in
accordance with the Contract Documents shall become a part of and have precedence
over anything shown or described otherwise.
IN THE CONTRACT DOCUMENTS:
1. Attached Pre-bid minutes to be added to contract docLunents.
2. Section 00300, Pages 00300-2, 00300-3 and 00300A to be replaced in its entirety.
3. In response to bidders RFT"S:
RFI from Development FL:
1) In the Drawings (Demolition Plans) ClOD and elOl shown about the Power
Poles to be relocated by Others, but in the Bid Schedule has the Item No. 12
Relocate power/light poles? What is Correct?
Response: Pole removal wi/l be undertaken by FPL.
2) Is there an Engineer Cost?
Resp01ue: ApproximCltely 1 million
RFI from Tenex:
3) On sheet C200 of the bid set of Plans it indicates "Contractor to clean existing
well and structures, contractor to core exist. StTucture and COIDlect Prop. 24"
RCP." We do not have a bid item, please indicate HOW SHALL WE PROCEED?
Response: See attached revised Bid Schedule, additional items added.
All other documents, specifications, drawings, terms and conditions remain the same.
Bidders must acknowledge receipt of Addendum on Page 00300-6.
END OF SECTION
J;in~1 \/pro:inn Rtn7
00900-1
03-4197
JUL-12-2007 THU 09:16 AM CALVIN GIORDANO
FAX NO, 9549218807
p, 03
\;..11' f Calvin. Giordano & Associates. Inc.
.~ -==- m.EXCEP1'IONAI. SOLLITIONS
:.... ].
L.._.____ n._~ c
r=n~inl'!erinf.\
C()Il~lrur.linll ~ni\in(,!urillll
& Inspectioll
Ivlunicip:d EI1Binl~I.!rilli\
Tr~n~p()rIMiCln Plllllning
&. Tr:rffic Fllgjll0.0.rin~
5LJrVp.yillf\ ,,\: M"ppinbl
1~lannin~
l<lrld;c,lpL.! Ar'chitec::l.ure
,'Ii ~lwir()nm('!lll,d Service;
Cumlrucliun Scrvice,
Induol Air Quality
Dala TechlloIQgip.~
& Oevl!l()pmCI'l
El11clf.\(;ncy M,lll:\Ap.melll
Scrvice;
l3uildillg Cnrle Services
lll()() 1:11121' Drive, Suite 600
fori LaudcrdJle. 1:1','n 16
Phone: 954,<}:n .7781
fJx: 954,9~Ulll()7
www.calvin-giordal1o.com
MEETING MINUTES
DATE:
PROJECT:
June 27, 2007
CLIENT:
ATTENDEES:
DISTRIBUTION:
PRE-BID MEETING
172nd Street Roadway Improvements
CGA Project No. 03-4197
City of Sunny Isles Beach
See Attached Listing
Attendees
File
A mandatory pre-bid meeting for the above-referenced project was held on June
27, 2007 at 10:00 AM at the City of Sunny Isles Beach City Hall. The items
discussed were as follows:
1. Liquidated damages of $1500 per calendar day until substantial completion;
then after that $1000 per day until final.
2. Unit bid project: paying for installed and approved items only
3. Project will commence at 17211d Street and Collins Avenue
4. W ASA will be doing major sewer reconstmction: several deep manholes and
this project will be completed in the same time that W ASA starts their
constmction
5. Contractor should be prepared to install cross-drains
6. Water encroached on roadways will be eliminated
7. Other utilities are at a shallow depth (generally 4 feet) ~U1d may have to go
deeper in cases where we have conflicts
8. An entirely new drainage system, eX1sting drainage will be demolished
9. FPL is undergrOlUld and will have to be coordinated as well as telephone and
cable TV
10. 172nd Street will have to be closed and there will be no thru street, except to
apt buildings
] 1. Asphalt is not salvageable - aU new base and new asphalt
12. Construction easement parallel with right-of-way provided; can encroach
into adjoining properties so that you can put fiJJ adjacent to raised grade
13. Existing Contractor will clean drainage well aud core one catch basin, no
outfall
14. Only attendees to this mandatory pre-bid meeting will be allowed to bid.
15. Questions must be made in writing and no later than five days before bid
opening in order to guarantee a response.
JUL-12-2007 THU 09:17 AM CALVIN GIORDANO
FAX NO, 9549218807
p, 04
16. Contractor questions:
a. Question: When is the WASA portion slated TO start?
AVlSwer: Assistant City Manager/Service Jorge Vera advised that it will possibly
start by tbe end of July 2007 or beginning of August 2007.
b. Question: Is the idea to have tho road contractor start the job after W ASA?
Answer: Yes. W ASA will be going the deepest and therefore starting the work
first. It will be the 17211d Street contractor's choice to install cross drains or
whatever is necessary at the time that W ASA has the ditcbes open Of wait until
tbey have bacl,-filled to grade. Tbis contract is going to be nwarded around
August 16th, 2007 so that we llre not really loo),ing of the 17211l! Street contractor
to start until the end of August or the beginning of September. The 172m! Street
contractor will not be present at W ASA's preconstruction meeting.
c. Question: Since you mentioned laterals, will WASA get the head start and then the
172rJd Street contractor would have to coordinate?
Answer: Yes
d. Question: It is not their laterals hut ours that we would have to put in for our
drainage .~ystem?
Answer: Cross-drains arc shallow compared to the sanitary sewer.
e. Question: Will they have much restoration in their contract?
Answer: Yes. Their original contract provides for the resurfacing of the road
and they indicated that it would include a change order on their part. It would
be tal{en out of the sanitary sewer contractor's contract. Vou should bid on
what we have nnd that would be the 8" of base rock and 1 y,," of whntevcr it is.
You will be doing the paving. The road will be closed. When they get in there
,down the center of that road, they will close off sections of that. People will
have to come in.through North Bay Road to have access to the property. If you
are at Collins Avenue, there will be no turning into 172"d Street.
f Question: The 172nd Street contractor will have to do it in segments because we don '/
have a wide roadway there?
Answer: Assistant City Mnnager/Service Jorge Vera advised that WASA will try
to }ieep one (1) one-way lane always open. Their concern is at Collins Avenue
where tbe manholes are so deep that, without shoring, it will be a very large hole.
This area has sugar sand. You will not have to be digging that deep. By the
time you arrive, the first section will be ready at grade to install the various
components of this job. They will be shallow so that you can maintain that one-
way in.
g. Question: Do they have extensive work west of/he connectingpoint of Collins Avenue
on 172nd Street?
Answer: Yes. They have the center of that road all tbe way to the end.
h. Question: What is the budget for this project?
Answer: Tbe budget will be included witb the minutes.
t. Question: Sugar sand was mentioned, is that what is mostly there?
Answer: Yes. As you know, most of Sunny Isles Beach was created by dredging
so there could be a conglomerate of material. It has been dredged and filled;
_J
JUL-12-2007 THU 09:17 AM CALVIN GIORDANO
FAX NO. 9549218807
p, 05
therefore, difficult to say wbat you will run into. You will definitely run into
sand and muck, a variety of material.
j. Question: Do you have borings?
Answer: Yes. We bave some borings. We will provide you with borings.
Assistant City Managcr/Service Jorge Venl ndvised that by the time that the
contractor starts, he will have IfPL's design and make the dropping of tbe pipes
nn add-on. He advised that FPL will not drop the pipes, the contractor will.
FPL will not furnish thc pipes either. They will tell us how much they necd. He
will be having a meeting with IfPL and advise you through an addendum.
k. Question: You mentioned FPL. Have the utilities been moved out of the way?
Answer: No. We have gathercd as much information of the underground as
possible (i.e. field survey, contacted utilities companies, etc.). It is not an
extremely busy street beneath the surface but they would not be able to design a
straight F,PL line. There will have to be some offsets because there are items that
are not made parallel. Once FPL gives us their plans, a design will be included
and forwarded to you as an addendum.
/. Question: Do we have all the permits?
Answcr: Yes.
m. Question: Will the contractor be reimbursed/or the permit fees?
Answer: If you are talking about Building Department permit fees, we suggest
that you put it in your bid as it will be the contractor's responsibility.
n. Question: There is a quantity discrepancy be/ween bid item and actual plans. under
drainage pipes.
Answer: That may have occurred if DERM hnd instructed us to do something
different. There is probably less on the plans then on the bid. We will review it
and get you an addendum right away.
o. Question: Is this work to be done in accordance with FDOT spec!fications?
Answer: Yes, in accordance with FDOT.
p. Question: What about the service to light poles'! Where is the main service
connection,from FPL?
Answer: Therc is aJrendy n service plate at North Bay Road because they just
completed it.
17. The Engineer of Record for this project is Calvin, Giordano & Associates, Inc. Please
forward all engineeling related correspondence (in writing) not later than 7 days prior bid
opening to the attention of:
Sabrina M. Baglierj
Calvin, Giordano & Associates, Inc.
1800 Eller Drive, Suite 600
Fort Lauderdale, Florida 33316
sbaglieri@calvin-giorando.com
The meeting was adjourned atIII :00 A.m.
JUL-12-2007 THU 09:17 AM CALVIN GIORDANO
FAX NO. 9549218807
p, 06
City of Sunny Isles Beach
1720d Street Roadway Improvements
CGA Project No. 03-4197
Meeting Date: June 27, 2007
ATTENDEES
Name Firm Phone/Fax
SabrinaM. Baglieri------Ca1vin~ Giordano & Associates, Inc. ------------- 954-921-7781/921-8807
Joanne Maglietta---------Calvin, Giordano & Associates, Inc. _________n__ 954-921-7781/921-8807
Tammy Cook ------------ Calvin~ Giordano & Associates, Inc. _____u______ 954-921-7781/921-8807
Tyrone Westcarth -------- Calvin, Giordano & Associates, Inc. ------------- 954-921-7781/921-8807
John Messerian----------- Calvin, Giordano & Associates, Tnc. ------------- 954-921-7781/921-8807
Jane Hines ---------------------------Stumy Isles Beach ------------------------ 305-957-1303/792-1563
Shaun Gelvez------------------n--- Sunny Isles Beach. -----------------------305 792-1703/949-3113
Jorge Vera --------------------------- Sunny Isles Beach _________n_____________ 305 -947 -0606/949- 3 ] 13
Randy Pierson----------------------- Solo Construction ------------------------ 305-944-3922/944-0037
Fred Asbaghi --------------------- Tenex Enterprises, Inc. --------------------- 954-788-8100/788-0005
Rauz Cabrera -------------- Development and Communication -------------- 305 - 596-0611/596-0615
JUL-12-2007 THU 09:18 AM CALVIN GIORDANO FAX NO, 9549218807
p, 07
172NO STREET ROAD IMPROVEMENTS
UNIT PRICE BID SCHEDULE
Item Estimated Estimated
No. Description Quantity Unit Unit Price Amount
I. GENERAL
1. Mobilization per FDOT (<5%) 1 LS
2. Maintenance of traffic per FOOT including
temporary striping and signage,
barricades, barriers, arrow panels, etc. as
required. 1 LS
3. Clearing and grubbing 1 LS
4. Pollution prevention and sediment control 1 LS
5. Earthwork 1 LS
6. Relocation of existing mail box 1 EA
GENERAL SUBTOTAL $
II. CIVIL
A Demolition/Site Preparation
7. Asphalt pavement demolition (removal & 4936 SY
hauling)
8. Concrete sidewalk demolition (removal 1210 SY
and hauling)
9. Catch basin to be abandoned in place and 15 CY
filled with flowable flow
10. Existing drainage pipes to be filled with 80 CY
flowable fill
11. Relocate or adjust existing street signs 3 EA
12. Relocate existing mailbox 1 EA
B Paving
13.1 W' Asphalt, Type S-3 550 TN
14. 12" Stabilized subgrade 5376 SY
15. 8" Limerock base 1076 CY
16. 4" Concrete sidewalk 1522 SY
17.6" Concrete driveway 379 SY
18. Drop curb 422 LF
19. Type F curb and gutter 2415 LF
Final Version 6/07 00300-2
03-4197
Addendum 1
JUL-12-2007 THU 09:18 AM CALVIN GIORDANO FAX NO, 9549218807
p, 08
C Striping and Signs
20. Thermoplastic STD white solid 6" 0.60 NM
21. Turn arrows 8 EA
22. RPM amber/amber 106 EA
23. RPM colorless/red 7 EA
24. R2-1 24" x 3D" speed limit sign 3 EA
25. R3-5R Right turn lane sign 1 EA
26. R3-5L Left turn lane sign 1 EA
27.6" Double yellow .60 GM
28. Pavement message (ONL Y) 2 EA
29. R3-7L Left lane must turn left 2 EA
30. W1-1a (R) Right turn and speed 1 EA
31. W1-1 a (L) Left turn and speed 1 EA
32. 10' - 30' Skip white line .30 GM
33. Erosion and Sediment Control 1 LS
0 Drainage
34. Ditch Bottom Inlet Type "P" 3' - 6' 1 EA
(Alternate A)
35. Curb inlet (6) Type "P" 3' - 6' 8 EA
36. 15" Yard drain by ADS 5 EA
37. 15" HOPE pipe 486 LF
38. 15" RCP 48 LF
39.18" RCP 385 LF
40. 24" RCP 1,091 LF
41. Clean existing drainage well and core 1 LS
existing structure
42. Sodding (81. Augustine) 3350 SY
CIVIL SUBTOTAL $
Final Version 6/07 00300-3
03-4197
Addendum 1
JUL-12-2007 THU 09:18 AM CALVIN GIORDANO
FAX NO, 9549218807
P. 09
III ELECTRICAL
43. Luminaires 14 EA
44. Luminaire pales 14 EA
45. PVC Conduit 3000 LF
46. Copper wiring 3000 LF
47. Trenching 3000 LF
48. Backfill 3000 LF
49. Luminaire wiring labor 14 EA
50. Luminaire mounting labor 14 EA
ELECTRICAL SUBlOT AL $
IV LANDSCAPE
51. Landscape and irrigation (Allowance) 1 LS $108,500.00 $108,500.00
GRAND TOTAL (Items 1~51)
$
(Written)
(Authorized Signature)
(Date)
Final Version 6/07
00300-4
03-4197
Addendum 1