EXECUTIVE SUMMARY
More CAPABILITIES, more value for you
Dear Selection Committee Members:
We understand you have a large number of RFQ responses to
go through to grade and that your time is valuable. Therefore, in
consideration of your time and your direction to "keep it simple, get to
the point, and make your case with facts and good information", we have
provided you with this executive summary to help you clearly identify the
benefits Haskell brings to you for the Heritage Park and Parking Garage
Project. We look forward to telling your more about what we can do for
your project if we are placed on your short list.
Haskell is a large, international construction management and integrated design-build firm headquartered in
Jacksonville, Florida with a local office in Pembroke Pines. We believe in giving our clients more than they expect,
so in addition to standard CM services, we ofter the following unique benefits for you:
1. Fastest Possible Delivery of the Parking Garage - We understand you need your new garage as quickly as
possible to start generating revenue for the City. In partnership with you and your design team, Haskell will evaluate
the fastest structural system for delivering the parking garage with our in-house architects and engineers. You can
be parking cars in your garage by February of 2010. Please see page 12 further schedule information.
2. Parking Garage and Public Park Expertise - Typically, park builders are not parking garage builders. Haskell
has completed in excess of 50 parking garages and several public parks. You can be confident both will be
completed by competent professionals with Haskell. Please see page 10 for some public park and parking garage
projects completed by Haskell.
3. Real Value Engineering Solutions - In addition to our construction management services, Haskell is an expert
designer of parking garages. Our in-house design staft can evaluate your design and make recommendations to
save time and achieve your goal of getting a nice product at a fair price. In fact, we have an excellent design
solution for the "Big V's" on the exterior of the building that will make them inexpensive, great looking, easy
to build, easy to maintain, and as durable concrete.
4. An Excellent Relationship with AECOM (formerly Spillis Candela, DMJM) - Haskell has worked with AECOM
on several projects including the recently completed Blue Cross and Blue Shield of Florida (BCBSF) Parking
Garage. Working in partnership with BCBSF and AECOM, Haskell suggested changing the garage from
cast-in-place to precast concrete, saving approximately $2 million and 2 months. Please see page 11 for
more information regarding Haskell's work with AECOM.
5. A Team Philosophy - In partnership with you, Haskell is prepared to deliver the park and parking garage as
quickly and efficiently as possible, while remaining well below your stated budget of $12.5 million. Please see our
team members and their resumes on pages 3 to 8 for more information.
Once short-listed, we look forward to sharing with you the many ideas we have to make this project a success.
SinCerelY,~
~~artz~V -
,,\V"""'"
lOr
$ ~Af.!BI!~!:.
City 01 SUIlny hlIea Besch
OffICe ollhe C Clerk
1
1) History of the Firm, including ownership and key management.
Haskell is a large, international construction management and integrated
design-build firm headquartered in Jacksonville, Florida with offices in
Pembroke Pines, FL, Dallas, TX, and Mexico City. With over $700 million
in revenue and 800 employees, Haskell is also the largest construction
firm in the state. Haskell stands apart in that we employ 160 licensed
architects and engineers. On CM projects, they provide exceptional help
to our clients during the pre-construction and value engineering phase of a
project.
Haskell specializes in parking garages and public park areas. We have
completed in excess of 50 parking garages and several park projects. In
addition, Haskell has a long standing working relationship with your design
firm, AECOM (formerly Spillis Candela, DMJM). All three key personnel
assigned to your project have worked closely with AECOM on other
projects - including parking garages. An example of this is the AECOM
designed Blue Cross Blue Shield parking garage in Jacksonville. Haskell
helped redesign the garage from a cast-in-place to a pre-cast concrete
parking garage saving the Owner $2 million and 2 months. Working as
a team with you and AECOM, we will help you decide the best structural
system for your parking garage.
The firm is employee owned in the form of an Employee Stock Ownership
Program (ESOP). This aligns our employees' desires with the needs
of our customers improving the value we provide. Our key (executive)
management is:
Preston Haskell - Founder and Chairman
Steve Halverson - Chief Executive Officer
Greg Ferrell - Chief Operating Officer
Brad Slappey - Chief Financial Officer
David Thaeler - Sr. Vice President, HR
J. Paul Tyler - President, Commercial Group
2) A summary of any company changes that are anticipated to occur during the
Project.
While our business is dynamic, Haskell anticipates no significant changes
in our company during the project
~~ !!f.!B!~!:'
Fidelity National Financial
Parking Garage
...................................................
"Your staff of
professionals delivered
as promised, without
the conflicts or
headaches that can
accompany typical
public construction
projects. The fact
that the project was
actually delivered
ahead of schedule
is indicative of how
the overall project
proceeded. "
Robert McCarthy,
Sheriff
Flagler County, Florida
...................................................
CONTACT INFORMATION
....................................................
Don Kartzmark
Haskell
111 Riverside Avenue
Jacksonville, FL 32202
(904) 357-4882 office
(904) 626-2849 cell
don. kartzmark@haskell.com
2
FIRM INFORMATION
3) Location of corporate headquarters and other divisional offices.
Our corporate headquarters is located in Jacksonville, Florida. We also
have offices in Pembroke Pines, Florida, Dallas, Texas, and Mexico City,
Mexico.
Corporate Headquarters
111 Riverside Avenue
Jacksonville, FL 32202
Southwest Regional Office
2591 North Dallas Parkway
Frisco, TX 75034
South Florida Office
8301 Florida Drive, Suite 200
Pembroke Pines, FL 33025
Latin American Office
Prof. Reforma No.1 015
Torre A-403, Co/. Santa Fe
01376 Mexico D.F.
4) Location of office(s) that will be involved in this Project during pre-construction
and potential construction phase services.
The primary office that we will operate your project from will be the
South Florida Office in Pembroke Pines, Florida. We will also have staff
participating from Jacksonville.
5) Description of contractor's project team to include the name, responsibilities,
and resumes of key personnel that will be assigned to this Project.
The best indicator of future success in the design and construction
business is always the team assigned to the project. Most likely, The
City of Sunny Isles Beach has found that teams with repeated experience
with the same building type and experience working together perform the
strongest. In addition, it would be beneficial if the team can:
· Work as a partner with the City and the Architect
· Complete the garage by March of 2010
· Provide time and cost saving value engineering alternatives for
you to choose from
· Reduce your risk
Haskell has assembled such a team for the Heritage Park and Parking
Garage project.
The proposed Project Director and leader of the Haskell team is Don
Kartzmark. He also serves as the Division Leader for Haskell's Parking
Solutions Division. This division of Haskell is dedicated to helping clients
~~ !!!!BI!~~
..................................................
"This project was
completed ahead of
schedule and under
budget and is an
excellent example of
the delivery system. "
Walter Petters
Director of Project
Management
School Board of Brevard
County
..................................................
Did you know that
Haskell tries to achieve
an efficiency of 310 s.f.
per parking space?
3
just like Sunny Isles Beach achieve their structured parking needs
as effectively as possible. As Project Director, Don will have primary
responsibility for customer satisfaction and project execution. As
evidenced by his resume, he has completed several parking garage
projects for Haskell in the past few years and worked with AECOM on the
Nassau County Courthouse project. Don has the experience to provide
options to the City that can reduce cost, speed up the process, and help
you reach your goals. Don's resume is on page 5.
Chris Kruayai is the proposed Project Manager and Rick Craven is the
proposed Superintendent. Chris will manage the day to day contractual
and administrative duties of the project and Rick will build the project at
the site. They will work hand in hand with you to execute the project. As
indicated by their respective resumes, both have completed several parking
garage projects - including three as a team. Additionally, Chris and Rick
recently completed the $100 million, AECOM-designed Blue Cross and
Blue Shield of Florida (BCBS) Southside Campus Expansion. This project
included two large class A office buildings and a 1500 space parking
garage. They worked closely with AECOM to re-design the cast-in-place
concrete structure to a faster, less-expensive pre-cast concrete system.
Chris' resume is on page 6 and Rick's resume is on page 7.
In addition to pairing up on other projects, all three key team members
worked together on two parking garages, the Arena Garage and the Sports
Garage.
During the pre-construction phase, Chris Holmes, AlA, LEED AP, Haskell's
most accomplished parking garage designer, will review the design
documents and provide value engineering assistance to the team. In the
last five years, Chris has designed nine Haskell parking garages. His
suggestions for structural systems, lighting, materials and parking garage
design will save Sunny Isles Beach real money and significant time.
This is a team that has completed parking garages over and over - as a
team. Success for Sunny Isles Beach is guaranteed with this group of
parking garage experts.
~ !!f.!B!~!:'
..................................................
"The Haskell Company
has been successful
in establishing an
attractive facility that
fits within our budget.
Completion has been
accelerated by three
months by improved
scheduling and fast-
tracking. Permitting
and outside reviews,
including wetland
mitigation, went
without a hitch. "
Jack Brede,
Project Manager
Florida Community College
at Jacksonville
..................................................
Blue Cross and Blue Shield of
Florida Parking Garage
Designed by Spillis Candela
4
RESUMES
PROJECT DIRECTOR
DON KARTZMARK I PROJECT DIRECTOR
Joining Haskell in 1998 with a strong combination of management,
construction, and marketing experience, Don serves as the leader of
Haskell's Parking Solution Division. This division specializes in teaming with
clients to solve their parking related issues with innovative solutions.
As Project Director, Don is the owner's primary point of contact during
the course of the project. He handles owner communication and
contract administration. Don orchestrates and remains responsible for
all preconstruction and construction activities, including cost estimating,
submission of GMP, creating project schedule and overall supervision of
project personnel.
REPRESENTATIVE PROJECT EXPERIENCE
Florida Community College of Jacksonville Parking Garage - a 535-
space, four-level parking garage on an active college campus.
City of Ft. Pierce Parking Garage - a 465-space, four-level parking garage
with 30,000 s.f. of mixed-use space attached.
City of Jacksonville Arena Parking Garage - a 480-space, five-level
parking garage.
City of Jacksonville Sports Complex Parking Garage - a 900-space,
four-level parking garage.
City of Jacksonville Downtown Parking Garage - a 1,350-space, seven-
level parking garage.
Fidelity National Financial Parking Garage - a 1, 753-space, four-level
parking garage.
Baptist South Hospital Parking Garage - a 1,050-space, six-level parking
garage.
*Nassau County Judicial Complex - 111,000 square-foot complex
including Class A office space, courtrooms and record storage and parking
designed by Spillis Candela.
EDUCATION / AFFILIATIONS
University of North Florida - Masters of Business Administration
University of Florida - Bachelor of Science in Building Construction
Certified General Contractor - State of Florida (inactive)
Florida Parking Association member
International Parking Institute member
National Parking Association member
* Indicates projects designed by Spillis Candela (now AECOM)
~~ !!f.!B!~~
FCCJ Garage
Jacksonville Downtown Garage
5
RESUMES
CONSTRUCTION MANAGER
CHRISTOPHER KRUAYAII PROJECT MANAGER
In his role of Project Manager, Chris has worked on a variety of parking
structure projects. His experience gives him a broad range to draw from in
solving many parking structure challenges and delivering quality products
that fulfill the needs of our clients.
As Project Manager, Chris will directly manage your project's construction
and is involved from the early development stages to project completion.
Chris prepares estimates, generates schedules, and establishes project
purchase controls. He is directly responsible for operations and sequences,
monitoring the timely procurement of project materials, subcontractor
management, preparing estimates of owner generated scope changes,
generating payment requisitions, and directly supervising the project
superintendent.
REPRESENTATIVE PROJECT EXPERIENCE
*Blue Cross & Blue Shield of Florida Headquarters Parking Garage - a
1 ,500-space, four-level parking structure designed by Spillis Candela.
City of Jacksonville Arena Parking Garage - a 480-space, five-level
parking garage designed to match the existing event arena architecture.
*Blue Cross & Blue Shield of Florida Headquarters Campus Office
Buildings - Multi-phase class A corporate headquarter campus on a 130-
acre site, currently consisting of 7 office buildings totaling over 1 million s.f.
designed by Spillis Candela.
City of Jacksonville Sports Complex Parking Garage - a 900-space,
four-level parking garage designed to match the existing sports complex
architecture.
Falcons Landing Westfalls Center - 61,000 s.f. upscale senior living
facility with 44 residential units, including private underground parking
structure in Potomac Falls, Virginia.
Schultz Center for Teaching & Leadership - 47,000 s.f. design-build
technology and education center located in Jacksonville, Florida.
Baptist Medical Center South - 234,000 s.f. 92-bed hospital located in
Jacksonville, Florida.
EDUCATION
Georgia Southern University, Bachelor of Science in Construction
Minor in Business Administration
* Indicates projects designed by Spillis Candela (now AECOM)
~ !!f.!BI!~!:.
,.....t .....)~.
i~l ili
~'fu'"
--~~
Blue Cross & Blue Shield Garage
6
RESUMES
PROJECT SUPERINTENDENT
RICK CRAVEN I PROJECT SUPERINTENDENT
Rick joined Haskell in 2001 as a Project Superintendent and has over
25 years of experience. Rick has a track record of success managing
parking structure projects within the Parking Solutions Division. Rick also
consistently ranks as one of our top superintendents in project safety.
As Project Superintendent, Rick is responsible for on-site construction
activities, in addition to guiding all trades and subcontractors toward
quality performance and timely completion. He is also accountable for
recruiting and deploying all job personnel, layout of accurate lines and
grades, checking and verifying dimensions within the construction drawings,
and keeping the project manager informed of all construction activities.
In addition, Rick is directly responsible for safety and accident control,
conducting safety meetings and implementing safety programs to ensure
there are no accidents on your site.
REPRESENTATIVE PROJECT EXPERIENCE
*Blue Cross & Blue Shield of Florida Headquarters Parking Garage - a
1 ,500-space, four-level parking structure designed by Spillis Candela.
City of Jacksonville Arena Parking Garage - a 480-space, five-level
parking garage.
City of Jacksonville Sports Complex Parking Garage - a gOO-space,
four-level parking garage.
City of Jacksonville Downtown Parking Garage - a 1,350-space, seven-
level parking garage.
"'Blue Cross & Blue Shield of Florida Headquarters Campus Office
Buildings - Multi-phase class A corporate headquarter campus on a 130-
acre site, currently consisting of 7 office buildings totaling over 1 million s.f.
designed by Spillis Candela.
"'Nassau County Judicial Complex - 111,000 square-foot complex
including Class A office space, courtrooms and record storage and parking
designed by Spillis Candela.
245 Riverside Avenue Office Building - 140,000 square-foot, multi-level
corporate office building with below grade parking garage.
EDUCATION
Florida Community College at Jacksonville
Associate Degree in Building Construction
ACI Certified for Tilt-Up Panel Construction
'" Indicates projects designed by Spillis Candela (now AECOM)
~ !!f..!BI!~.!:.
Blue Cross & Blue Shield Garage
~
.... -
Jacksonville Arena Garage
7
PROJECT TEAM ORGANIZATION
6) Description of how contractor's team will be organized and assigned
responsibility for this project.
( i) '\
i ..\
\'....'lD.~~... ~-'
~"..._....
City of Sunny Isles
\. Beach ~
f ""\
Don Kartzmark
Project Director
'\ ""\
Chris Holmes, AlA, LEED AP Chris Kruayai
Preconstruction Parking
Specialist Project Manager
./ I
""'\
Rick Craven
Project Superintendent ./
I
( ""\
Assistant Superintendent
"- to be nominated ./
~ !!t~BI!~.!:.
"Actual construction
of the project has
proceeded ahead
of schedule, totally
within budget. The
construction site
reflects outstanding
management. It is
organized, clean, and
safety oriented. "
Thomas McClelland,
Assistant County Manager
for Public Works
Volusia County
Blue Cross and Blue Shield of Florida
Designed by Spillis Candela
Did you know that
Haskell is the largest
construction firm
headquartered in the
State of Florida?
8
7) Description of recent project experience, including projects of similar size, and
client references with contact information.
Experience is defined as "the accumulation of knowledge or skill that results
from direct participation in events or activities." The City of Sunny Isles
wants a beautiful new parking garage and park - fast. No one has more
experience than Haskell. Here is why:
1. Sunny Isles can count on Haskell's parking garage experience. We
have completed over 50.
2. The City can count on Haskell's ability to deliver the project quickly.
Haskell completed the 1400 space Fidelity National Financial parking
garage in only 7 months.
3. Our experience with your design firm, AECOM, includes several
successful projects.
4. Our experience with beautiful parks and public gathering space is
outstanding.
..................................................
"It is without
hesitation that I
would recommend
Haskell to any
organization, company
or municipality for
the integrity, value
and proficiency this
company exemplifies."
Alex Fekete,
Former Mayor
City of Pembroke Pines, FL
....................................................
While Haskell has completed hundreds of projects, we present the following
project specific experience for your consideration:
Jacksonville Arena Parking Garage
Similar in size to your proposed parking garage structure, the Jacksonville
Arena parking garage is 482 spaces in the downtown Jacksonville
entertainment district. The scale, proportion, brick, precast and metal work
were designed to match that of the nearby Jacksonville Veterans Memorial
Arena. Built in conjunction with another garage for the City of Jacksonville,
Haskell delivered both garages at a cost savings of $1 ,955,382 below the
original budget. Owner contact: Ken Krismanth, Signet Development
(904) 350-1314
University of Miami Parking Garages
Haskell completed three separate parking garage structures for the University
of Miami. One structure involved a 2-level addition to a parking structure
adding 464 spaces with a 43,000 s.f. attached office. The second structure is
a 4-level, 551-space garage and the third is a 3-level, 634 space garage. All
garages are built of precast. Owner contact: Joseph Folino, University of
Miami (305) 284-6728
Port of Miami Parking Garage
Haskell completed a six-level parking garage at the Port of Miami to
accommodate cruise terminal passengers and Port employees. The precast
structure included four new elevators, a new transformer vault, future office
shell space, parking controls, security systems, landscaping and irrigation.
Maintenance of traffic, coordination with Port users, and passenger safety
at the Port were a primary focus throughout construction. Haskell provided
planning, permitting, design and construction for the 1,350 space structure.
~ HASKELL Owner contact: Bill Johnson, Port of Miami (305) 347-4844
~ America's Design-Build leader"
9
(2)
CJ
c:
(2)
.;:
(2)
c.
><
W
..=.:
...
co
D..
CJ
.-
-
.c
:s
D..
"0
c:
co
(2)
C)
co
...
co
(!)
C)
c:
.-
..=.:
...
co
D..
....
c:
co
>
(2)
-
(2)
~
c
o
.. CI)
CI)..
- nI
~c
o
U
CI)
-
nI
Q
-
...
nI
-
U)
-
I/)
o
U
..
(,)
CI)
'0'
...
0..
u 6
.5..
C nI
<3 E
w.2
-c
<(-
-
(,)
.5 C
C 0
0..
UnI
I/) E
~ ...
;.2
C C
~-
o
C
o
..
C.
'i:
(,)
I/)
CI)
c
-
(,)
CI)
'e-
o..
~
CI)
E 6
nI..
Z nI
- (,)
(,) 0
,!, ...J
e
0..
co
o
o
N
....
0>
.0
E
0>
U
0>
o
co
o
o
N
..r::
~
CIl
:!E
co
~
.....
r-:
o
1'--.
co
~
enO
o>g
--E~
]10~
enIO>
CIlenl'--
I'c~
.co
o~
ai
>.:=
'EE: N
::J00>0
E~-cg
E U ~ '
O~CD~
o...~co
CIlCllU-
-Co>CIl~
.- Ol" 0
00> ~
u::=
o
o
LO
C")
LO ui
..r:: ::J
:!:a.
~ E
0> CIl
OlU
~~
~~
010
c: U
:.i2 0>
ro.:?:
0.(:5
"Q)CIl
> c:
0> CIl
, c:
C")o
, ...
':ri'5
~.o
C")en
C")O>
. U
COCll
NO.
Nen
ro
0>
Ol
~
o
o CIl
Z:' :g
'c .Q
::J Ll.
E .
E~~
,9.. '>'>
"""c:c:
CIl 0 0
:E~~
.QlJlJ
Ll..,.,
co
o
o
N
....
0>
.0
E
0>
U
0>
o
co
o
o
N
>.
....
CIl
::J
c:
CIl
.,
I'--
0>
.....
N
0>
C")
c:t5
.....
~
enO
o>g
--E~
]10~
enIO>
CIlenl'--
I'c~
..r::0
O~
en
O>..r::~
en........
'C c: C")
o.CIl.....
.... E '
O>enO
"E .- 1O
W~~
...c:~
0>0>0
a,~ ~
00
"Q)
>
~
=-g
.~ 6
~c,
~o
~....;
en
g'o
:.i2g
.... .
CIlO
0......
"Q)~
>-c
~.2
c: U a.i
~ .f: U
0> CIl
enuio.
....;~~
en CIl CIl
o 0.0)
oCIJ..!:::
000>
cO~,g
LO ._
~.....O
c:
~
o
"E
~
o
o CIl
~ :g
'> 0>.Q
5 0lLl.
en~ai
~CIl-
lJ(!)'S:
., Ol c:
'O.s: g
>.~ t5
C3~~
enO
o>g
--E~
]10~
enIO>
CIlenl'--
I'c~
..r::o
o~
en
O>..r::~
en........
'C c: C")
o.CIl.....
.... E '
O>enO
"E .- LO
w~C")
....c~
0>0>0
a,~ ~
00
O>..r::
>:!:
li3 ~
en...
o en
...CIl
0> U
Ol~
CIl 0.
....-
CIl 0
Ol...
Ol=
c: ::J
:.i2CD
....
CIl '
o.~
-0.
~ E
~ 0
~ U
::J en
0'"
- ....
ai 8. ...:
U en 0>
CIl c: 0>
o.~c:
enoo>
..J.......>
C")C:~
0> ~.g
<(-c.o
x
0>
0.
E
o
o CIl
~ :g
o 0> 0
0. Ol u::
en ctl .
~ro~
'S:(!)'S:
c: Ol c:
g .s: g
~~~
~ as ~
.,0..,
-
Ctl
(J
'5
~
:S
::J
o
CI)
:t5li5
.;::; .....
g.a5
cao
LO
o
o
N
>.
CIl
:!E
~
o
o
N
>.
"3
.,
o
co
co
..,f
~
C")
ai
~
co
o
o
N
...
en
::J
Ol
::J
<(
I'--
o
o
N
li3
.0
E
0>
U
0>
o
co
I'--
C")
c:t5
o
N
co
.....
~
enO
o>g
=E"I:::t
~o~
enIO>
CIlenl'--
I'c~
..r::o
o~
..:
2
c: >.~
O>....~
o~co
-o>N
CIl_ ,
U OlN
.- c: 0
-gOON
:!E-~
Ciiffio
.- a. 0>
C. ~
CIl
CD
o
LO
O.
.....
=
'~
0>
Ol
CIl
....
CIl
Ol .
Olen
c: ::J
._ 0.
~ E
CIl CIl
o.U
"Q)ro
>:!:
0>0.
, en
X 0
'W..r::
....: CIl
ui c:
00
Oen
LO 0>
. U
LO CIl
COo.
C") en
....
0>
"E
0>
o
ro
U CIl
:a -C
0> 'C
:!EO>.Q
0lLl.
..r:: ctl .
"5ro~
~(!)~
:m,~ g
c.~t5
&l~~
-
CO
c::
~
Ctl
<::-
CO
~.-
..... (J
'- c::
1 Q) CO
:0 . c::
u:u:
I'--
o
o
N
>.
CIl
:!E
I'--
o
o
N
>.
....
CIl
::J
c:
CIl
.,
o
o
O.
o
o
o
ui
~
o
enO
__E~
"Q)CIl,
~-C.....
en <(0)
CIlo>l'--
I~-
.- ~
:!EO
~
~
'w
li3enCO
>C:LO
,_._ 0
c:.ol'--
:J.o'
O>O~
=CDN
'> 0>_
c:~~
0'- 0
en:!Eo>
~ ~
U
CIl
.,
.!!1
~
0l::J
c:'"
._ U
~ ::J
.... ....
CIl'"
0. en
o .
COOl
C") ,s:
..r:: en
...::J .
,- 0 0>
~..r::0)
0> ... ....
OlC:U
CIl 0> c:
.... -C 0
CIl ::J U
Ol'" ...
en en
OlOCll
.S: ... al
~-C....
roO>o.
o...r:: _
, lJ 0
l+-:+-,"'C
~ro51
OenO
00>0.
cOlJE
..... 0. 0
.....enu
Z:'
'W CIl
.... -C
~ 'C
'c 0> .Q
:J ~Ll.
~ro~
'S:(!)'S:
c: Ol c:
g ,s: g
~~~
U .... U
~~~
LO
o
o
N
>.
CIl
:!E
~
o
o
N
....
0>
.0
E
0>
C.
0>
en
~
CO
.....
o
CO
C")
~
.....
~
enO
o>g
--E~
(i)-I
~O.....
enIO>
CIlenl'--
I'c~
..r::0
O~
ro
'(3
c:
CIlenco
c:.........
u::~~
roS..J.
C:CIlLO
Ben CO
ZOO '(3 ~
CIlO
~.=~
"Q)
-c
u::
o
N;
LO 0>
1'--. en
..... ::J
..r:: 0>
:t::: ~
~ 0>
0> ~
Ol.!!l
CIl 0>
.... c:
CIl CIl
Olo.
Ol-
c:-
._ CIl
~ ~
CIl'"
0. en
CIl
"Q) U .
>O>~
0> :t:: ::J
,en-c
~ o.~
<+=7U
....:;:VJ
uif-2
LO . ~
C")eno>
0>0>-
.uo>
O>CIlU
LO 0. U
LOenctl
ro
'(3
c:
CIl CIl
c: -c
u:: 'C
roo>.Q
c: Ol Ll.
o ctl .
~ro~
~(!)'S:
>.0lC:
...c:0
=:.i2~
0> .... U
:ECIlCll
Ll.o..,
I'--
o
o
N
>.
....
ctl
::J
c:
CIl
.,
CO
o
o
N
>.
....
CIl
::J
....
.0
0>
Ll.
o
0-
00>
- 0>
0....
o..r::
0=
cOro
LO ~
~
enO
o>g
--E~
CD-I
~o.....
enIO>
CIlenl'--
I'c~
.co
o~
- LO
vi 0>
. 0> C")
<:(c:co
1-"- ,
<l:O>N
:!EI~
>..r::_
> o.N
0>0
enN
O~
.,
ct
._ 0
.....,0.
.........0.
!<~::J
:!Euen
>-CO
>0>'"
...en
....CIl-
O....ro
~ 8. ~
O>....-C
.... 0 c:
.agCll
U .- en
2 = c:
"'<(0
en ,_
...
Ol . CIl
c:en-C
.- 0> c:
~lJ::J
CIl 0. 0 .
o.en-ro
..... 0 en 'C
~ C") g'2
U 0>._ CIl
~MoE
0.0l0...
o>c:-en
0> .- 0> CIl
....roUU
..r::...CIlO>
f-.90.0.
CIl
0> CIl
.;c- 0>
c:~ .;c
~<l: e
o:!E 0)
g-~ :!E
-a; Z:' ~ cj
:!E '~ ~ ci
c: ..r:: .... c:
.9:5~.9
g':5 Ol g'
:.c 'w .s: :.c
enc:~en
CIl CIl .... CIl
~t=~~
c::
o
:;:;
- Ctl
{gt::
o 0
E ~
Q) c::
..... ~
.!::J.;:
o
o
o
N
..r::
U
....
CIl
:!E
0>
0>
0>
.....
>.
"3
.,
o
o
q
N
I'--
N
c:t5
~
>'0
0>0
enLO
--E~
"Q)CIl'
~O::Oi
~O>I'--
I.!!1~
C:o
0>0>
O~
c:
~~~
c: Ol C")
::J::JO
o CIl ,
O...JN
UI'--
.!!1 :!E I'--
en -
::JC:I'--
-'- 0
~a;~
~
enQ>
O,g
~-g'O
..r::.a8-
:t::.20~
~CIl"'-=
0> 0> en
s.... '- 0>0
::J.E CIl 0
ucn"-o
::J c: CIl .
.... 0 010
en 'en t5 :;
Ol '> 0> 0>
.s: e 2 -c
~ 0.0.2
CIlenUU
0. 0> 0 .s:
"Q)-g;'g
~g~~
x - ~ .
.- . CIl..r::
en eno> ~ ~
"":UCcuQ)
uiCllCll.olJ
~ ~:s 0> ~
N en ..r::
N~~;'ffi
tg.....- ~ ffi ~
c:
o
fij .{g
L 'C
o .Q
0. Ll.
~O>..r::""
CIl Ol U
t=~~
ro~CD
-g Ol CIl
E ,S: 5
Q5 ~ ~
...ctlCll
.f:o.o
.....
o
o
N
Cii
::J
Ol
::J
<(
.....
o
o
N
'c
0.
<(
CO
CO
N
LO
CO
~
N
~
o
c:0
=g~
0> = '
~~Oi
CIlc:1'--
ICIl-
-~
<(0
~
~
'> ~ ~
c: .oN
g..r::""O~
~ULl.1'--
lJCIlOJ~
., 0> OlN
.......c:c'-~
o 00
>. 0>0>
... (!) ~
(3
o
c:0
CIl.- 0
~~ui
en c: CIl
0> 0> en
> > 0>
CBt::-g
en~(3
...c:c:
~ 0- .
...U '5
~-gi3:=
CIl CIl ~ ~
0. Ol CD 0.
en c:
OlE ~ ~
.S: 0> = c:
li3 en E: CIl
..r::-oE
...... co CJ) .....
CIl.:?: ~ 0
C> en (J 't:
... 0> CIl 0>
c:_., 0.
o _...... '-
J::~oo
C:CIl"'O
~ o.roB
UUO>::J
o=..r:: 0
c:.go>....:
<( 0.= ui
~
ro .{g
~ 'C
CIl 0
~ u::
.c ..r::""
U U
CIl CIl
0> 0>
CD CD
~ ~
'> >
c: c: c:
g.Q g
t5'S:t5
ctl CIl ctl
.,0..,
~
rf.
~
~
0.;.;;;
Q)
""')
.E
..::;
I'--
o
o
N
>.
CIl
:!E
CO
o
o
N
li3
.0
o
(:5
o
CO
~
CO
N
LO
.....
CO
~
o
o
=~~
0> >. '
~I"'"
~E~
I'--
.,~
o
~
"E
0>
roE
'-t:: T'""
OctlCllO>
o 0. c: CO
0>0>0>0
0.0 x.J
CIlenCllI'--
O~enLO
....... 0 >a-
0> CIlO>
>.>., C")
;t::: t) ~
0=
.0
::J
a.
vi
-c
c:
::J
e-c
CIl ~ffi
g'~ ~
:a ':.a
::J en CIl
(35~
c: .- 0>
,- = ~
~>CIl
roCll-
o.o.CIl
-c'~ .
05.l!l
0.-::; ,
-E':og'
o Ol U ,-
.0 c: -c 0.
-s,:a c: ~
,_ = CIl en
O>::Jen-C
c:.o-cc:
0>c:"Q)~
b ,Q <+= 0>
ctl ~ Ol.:?:
CO o>.s: ~
~g-g2
<(8~~
CIl
-c
~ 'C
.... 0
CIl-
a. Ll..
enro
.... ....
~o
'Q)O
., OJ
E g.
:':::;0
...
...
~~
C
z
o
..-
Q)
::::
'S
,CI::
'_ 0
I::~
::J (J
E m
E""')
0.....
Um
m Q)
1:10>
'- Q)
1.;:::::
Qo
LL:U
.!1
.....
o
~
Q)
:::::
's ><
I:: Q)
0-
CI) 0..
..lc: E
(J 0
~U
,C
.~
gz
~
Q)
:::::
's
I::
o
~
(J
~
~
~
~
I'--
o
o
N
....
0>
.0
E
0>
>
o
Z
I'--
o
o
N
~
ctl
::J
....
.0
0>
Ll.
LO
.....
o
ui
C")
~
ui
~
o
o
=~~
0> >. '
~I"'"
~E~
I:.:::;~
o
~
"E
0>
ro E
L..t::: T'""
OCllCllO>
o 0. c: CO
0>0>0>0
0.0 x.J
CIlenCll.....
O..><:enLO
'4- 0 >.-
O>CIlO>
>.>., C")
~ t) ~
0=
.0
::J
a.
E vi 0>
0= ,:?:
e CIl en
Cii 0. 55
0> Ol'"
.... c: X
CIl:.i2 0>
Ol ro -c
.S: ~ ffi
-c .0>
::J en ....
--C::J
Uc:...
.S: ::J CIl
~e~
ro ~~
o.CIlCll
-c--
o 0. CIl
ooi.
-€: .E: "E
o -c 0>
-g, '5 E
'Qi .0 .9-
c:0>::Jci>
0l0"c:
0> CIl 0> .-
b.... 0> 0.
CIl .9.!!1 ~
C")enuen
. -c li3 -c
l'--c:xC:
<(CIlO>~
CIl
-c
'C
o
~u::
....
CIl--
a. CIl
....
en 0
'c 0
o 0>
cng.
-;0
'"j",1 80U8!J8dx3 86eJe~)i,6u!>IJed 80U8!J8dx3 >IJed o!lqnd
". ..... 1"1 ""'~ J'::"'"",,1o..IIIIIi~~"I~~uHIIIIIII ~"'.,,~ ""," IU", "-
n 1I'-."J
Y ~ 131,
~ ~,
'......_1
, ;; i
.':.~
. ::
.~
~
rf.
CI)
'c:
.9
CI)
-)
.t::
(J
m I::
Q) .0
m"::::
Q) .~
:::::Q
's ..lc:
1::_
~ ~
~ m
(J Q)
~CI)
PROJECT EXPERIENCE
EXPERIENCE WORKING WITH AECOM (FORMERLLY SPILUS CANDELA)
Blue Cross and Blue Shield of Florida Parking
Garage
As part of a corporate campus expansion
for Blue Cross and Blue Sheild of Florida
(BCBSF), AECOM designed a parking garage to
accommodate additional employees. Originally
designed a cast-in-place concrete structure,
Haskell and AECOM worked together to redesign
the garage to be a precast structure, saving the
owner $2 million and 2 months of construction
time. The garage is approximately 560,000 square
feet with 1,500 spaces. Owner Contact: Steve
Davis, Blue Cross & Blue Shield of Florida (904) 905-6890
AECOM Contact: Lorenzo Cobiella (305) 447-3597
Blue Cross and Blue Shield of Florida Office
Buildings
_~ In an effort to consolidate their operations
I that were housed in numerous locations in
. Jacksonville, FL, BCBSF selected AECOM to
design multiple phases of their headquarters
I campus. Haskell was selected to perform
preconstruction and construction management
services. The development is on a 130-acre
site, currently consisting of seven office buildings
totaling over 1 million square feet, conference
center, multi-purpose training center, and full-
service kitchens and cafeterias. Haskell recently
provided CM services for the expansion of the campus to consist of two addition class A office buildings. The
structure is cast-in-place concrete, post-tensioned. The skin is a combination of APC and glass. Owner
contact: Steve Davis, Blue Cross & Blue Shield of Florida (904) 905-6890
AECOM Contact: Lorenzo Cobiella (305) 447-3597
Nassau County Judicial Complex
The multi-story 111,600 square-foot complex provides office
space for courtrooms, executive suites, and state and county
administration offices. Haskell worked with AECOM and provided
complete preconstruction and construction management
services for the project. The complex was built with a high-tech,
computerized building management system, controlling multiple
systems within the building. The building exterior is constructed of
concrete tilt-up panels with brick veneer and architectural precast
accent elements. Owner contact: Bill Howard, Nassau County
Board of Commissioners (904) 548-4969
AECOM Contact: Don Dwore (561) 236-2870
~ !!!!BI!~.!:.
11
8) Evidence of capabilities for construction scheduling, material procurement, and assurance that plans, specifications,
and schedules are met.
Scheduling
Project schedules are developed by utilizing similar, previous parking garage project experience of the team to list
and apply durations to each activity. Schedules are built activity by activity in Primavera scheduling software using
the critical path method. Relationships between activities, durations, lead times and lag times are all input into the
software. Milestones are input to establish key interim dates that become fixed schedule targets.
Once the schedule is
complete, it is checked
for compliance with the
Owner's completion
objectives. Time is
money so schedules are
scoured for opportunities
to reduce the overall
duration by performing
multiple activities at once,
accelerating through
bottlenecks and critical
path activities, and any
other schedule shortening
(fast-track) techniques.
Once complete, all
schedules are submitted
to the Owner for approval.
For example, Sunny Isles
Beach Heritage Park
and Parking Garage
project has an opportunity
to leverage the rapid
delivery and erection
of pre-cast concrete to
shorten the duration of
its schedule. Haskell,
if awarded the project,
will work as a team with
the City, AECOM, and
pre-cast concrete firms
to determine right away
if switching to pre-cast
makes sense. Please
see the two preliminary
schedules comparing the
two structural methods on
this page.
2009 ~i{. '0
10 th:..u~!",n 0", flr1/ F uiy fIlAV' J~h .Ul "uO SEP OC. NQv DEe JA~. HB ,W. "PR '.'AY
~Lrt <, ,',
,- , ;
1240 SIlo Domo ond Plop 10 01JUN09 12JUN09
11110 ~PIIng 3515JUHOll S 1.1ULOG
1120 PIoCapoond_ 20 O3AllOOQ 28AlJOOQ ~
:
1130 Slab on Grade 15 SIAU<108 18SEP09 C;;
1140 Caot__~""'_ 81 14SEP09 07DECOll ~ :
1150 Exter1or_T_(1llgVs) .co oeoECOll 01FEB10 ;
1180 SIoIm Ono" PIpklg 20 oeoECOO O4JAN10 : t=.. ;
1110 ~_EIedriC:al 30 oeoECOll 18JAN10 ;
:
1200 Iotoo<o<wy-- 20 oeoeCOll O4JAN10 \0
1210 SIoIr_ 20 oeoeCOll O4JAN10 :
; : ",
1180 E_~ 30 O5JAN10 15FEB10 :
1210 -_.~- 40 O5JAN10 01_,0 :
1220 -_.~ 30 lZJAN10 22f'EB10 ::1
1230 ~ond~ 20 18fEB10 15MAR10 :ere
1250 P\n:lt 0uI 51_10 22_10
1280 Tomp~Oocuponcy 0 22MARl0 ; :
Cast In Place Concrete Conceptual Schedule - Complete March 22, 2010
1280 R..-lgn COo lor _ Concrele 20 01JUN09 2$JUNOll
12110 - Shop 0n0M1gI 30 01JUN09 10JlAJl0
11110 ~PIIng 35 15JUHOll 31.1ULOG
1300 -- 20 2lIJUN09 2UJUll1
1310 Pro-ent Shop 0rwM1g__ 101:lJl.1L.08 2UJUll1
1320 PnM:nlCcncreOt_ $3 27JUU1C1 07OClOll
1120 PIoCapoond __ 20 03AU00lI 28AUOOll
1130 SIob""~ 15 SIAU<108 18SEP09
1140 Pro-enlConaol E_ se 10SEP09 280CTllll
1150 Exter1or_T_(IIlgV,) 40 3OOCTOlI 2COECOll
1180 Storm Dnoln PIpklg 20 3OOCT09 28HO\I09 ~.
1110 lJIt<lIngondEJoctrtcol 30 3OOCTOlI 10000COll .
1200 Maoonly -- 20 3OOCTOlI 28NOVIl8 ~
1210 S...._ 20 3OOCTOIl 28NOVIl8
1180 EIova"'_ 3027NO'o'OG 07JAN10
" '"
1210 _~.NtIIc:_ 4027NO\/Oll 21JAN10
: :1
1220 InIenor A1IstM.. ~ 30 04DECOll 14JAN10
1230 S~1ng ond sv- 20 oeJAN10 04FEB10 "~
1250 Punch Out 5 WEB10 l1FEB10 r.
1280 Tompl:eltiflc:ata lla:upM1cy l1FEB10 ~
Pre-cast Concrete Conceptual Schedule - Complete Feb. 11, 2010
$ !!f.!BI!~.!:.
12
PROJECT EXECUTION
Another important consideration for your Heritage Park and Parking
Garage Project is sequencing. Haskell will sequence the project to allow
uninterrupted use of a majority of the surface lot during the construction
of the garage. Once the garage is completed, it will serve the parking
needs of the hotel and Public Works while we complete the park side of the
project.
Material Procurement
Haskell has a large network of subcontractors prepared to provide
competitive pricing for the Heritage Park and Parking Garage project.
During the estimating phase, Haskell will break down the entire project
into appropriate scopes of work and solicit bids from no less than three
qualified subcontractors for each scope of work. The low qualified bid will
be thoroughly interviewed and questioned to ensure completeness. Each
complete low price will be incorporated into the Guaranteed Maximum Price
(GMP) proposal and submitted to the City for approval.
Once approved, Haskell will enter into Subcontract agreements with each
low bidder included in the GMP. This process will be managed by the
Project Manager and supervised by the Project Director using a tool we call
the Purchase Control Log. This continues until all scopes are completely
purchased.
Assurance that Plans, Specifications and Schedules are Met
Adherence to the plans and specifications, or quality assurance (QA), is
a major focus at Haskell. In addition to the day to day quality assurance
provided by the project team, Haskell has a quality assurance department
that reports to the Group President. The QA Department's policies and
procedures are designed to ensure that the plans and specification are met
and include the following:
· Participation in design reviews and make recommendations to improve
quality
Review project specifications and make recommendations to improve
quality
· Review key submittals for compliance with design requirements
· With a parking garage, QA visits the pre-cast concrete plant to ensure
compliance with PCI and the design documents
· Participate and lead key pre-construction meetings with Subcontractors
· Perform site visits to verify compliance with plans and specifications.
· Implement testing programs
Utilize Qualigrams and Best Practices - Experience from previous
issues and solutions including detailed informational sheets on various
envelope and building systems. These include:
~ ~Af.!B!~!:'
"The project was
constructed while
working on an active
campus of around
2,500 students.
Haskell coordinated
the phasing of the
construction activities
to minimize the
impact to the school's
operations. "
Gene Denisar
Superintendent
School Board of Manatee
County
Joe Stonis Park
Cape Coral, Florida
13
PROJECT EXECUTION
· Floor slabs
· Windows
· Roofing
· Joint Sealants
· Flashings
Fluid applied barriers
· Develop Project Specific Quality Inspection Plans (QIP) - These plans
are tailored for each project based upon previous experience with
similar building types. For example, a QIP for a hospital will contain
procedures for window flashing, caulking and testing, while a parking
garage will contain procedures for verifying the pre-cast concrete meets
the standards set by The Pre-cast Concrete Institute (PCI) and the
specifications. QIP establishes minimum necessary steps designated
by AlE, Construction, and management during the various phases to
ensure quality for a specific building type.
Compliance with schedule requirements starts with the bid process.
Subcontractors are provided a schedule with the bid package and are
instructed to bid the work in accordance with the schedule requirements.
The successful bidder is then presented with a subcontract agreement
which incorporates the schedule as a contract document. Once executed,
they are contractually bound to deliver in accordance with the dates
indicated in the schedule. If a subcontractor falls behind, Haskell will take
whatever steps are necessary, at their expense to get them back on track.
These steps can include requiring them to increase their workforce, work
overtime, supplement their workforce, or termination and replacement.
9) A statement of experience summarizing projects constructed under a similar
development process and a summary of what the Firm can "bring to the table" for
the benefit of the City of Sunny Isles Beach.
Haskell has completed several hundred projects including numerous
teaming with municipalities using a similar development process to the
Construction Management development process used by the City of Sunny
Isles Beach for the Heritage Park and Parking Garage project. We have
also used that same process with your selected design firm, AECOM.
Please see our project experience in section 7 on page 11 for more details.
In addition to the everyday items like experience, qualified key team
members, etc. that everyone offers, Haskell also "brings to the table" the
following unique benefits for Sunny Isles Beach:
1. Because of our extensive parking garage design and construction
experience, we are able to help you and AECOM determine the right
structural system (pre-cast concrete vs. cast-in-place concrete) to
deliver the best combination of speed and cost.
~ !!!!BI!~l
"Please accept my
appreciation for you
and your staff in the
completion of this
major garage. It was
indeed a pleasure
dealing with your
team. The JTA is
appropriately proud
of the structure, as
it represents, in my
opinion, the most
attractive parking
structure in the
downtown area. "
Steve Arrington,
Director of Engineering
Jacksonville Transportation
Authority
Jacksonville Downtown Garage
14
PROJECT EXECUTION
2. We are an integrated design-build firm and have parking garage
architects and engineers that work right along side your proposed
construction team. They will review the plans and provide true value
engineering solutions others might not consider. In fact, we have a
solution for the "Big V's" that can save you tens of thousands of dollars,
be more durable and require less maintenance!
3. Our long standing relationship with AECOM (see page 11) including the
BCBS parking garage.
4. Excellent combination of experience with high-end park I public space
and parking garages. See page 10.
5. We have a plan to minimize the footprint we need to construct the
garage, so you get to keep more of the existing parking lot during
construction.
10) A statement addressing the Firm's present and projected workload and how
this Project will be scheduled within that workload.
Like most firms in today's economic climate, Haskell has less workload
projected going forward than we currently have at present. Therefore,
the construction team assigned to your project is available to begin work
immediately and we do not anticipate any occurrence where this project
could be affected by Haskell's workload.
11) Third Party evidence that the Firm has the required license, insurance, and
financial and bonding capabilities necessary to fulfill their responsibilities for the
Project. The City may require supplementary evidence of financial stability prior
to signing a contract for the Project. Note the City is a public body subject to the
State of Florida Public Records Law. Information submitted as part of this RFQ
may be subject to public release.
Please see following enclosed information regarding Haskell's bonding
capacity, licensure, and proof of insurance. Additional information is
available upon request.
~ !!t!BI!~!:.
"At all times, your
corporate and
project staffs, and
most importantly,
your workforce
demonstrated a strong
commitment to safety.
Your safety plan was
of excellent quality.
You did a superior
job assessing the
risks of the project
and mitigating them
to render them safe.
Your day-to-day
management of the
project in a safe and
hazard free manner
was most impressive."
Daniel P. King,
Capt., CEC, USN
U.S. Naval Academy
Annapolis
15
PROOF OF INSURANCE
~ r
ACORD- CERTIFICATE OF LIABILITY INSURANCE Page DATE (MMIODlYYYYI
~ 1 of 2 04/03/2009
PRODUCER 877-945-7378 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMA nON
ONLY AND CONFERS NO RIGHTS UPON THE CERnFICA TE
Willis of Florida, Inc. HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
26 Century Blvd. ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
P. O. Box 3D5191
Nashville, TN 37230-5191 INSURERS AFFORDING COVERAGE NAIC#
INSURED The Haskell Company INSURERA: American Contractors Insurance Com.p~ Ri 12300-001
P.O. Box 441DO INSURERB: Wau.au Busin... In.urenc. Company 26069-001
Jacksonville, FL 322024950
INSURERC: National Union Fire Insurance Company of 19445-001
INSURER D: ACIG Insurance Com~y 19984-001
! INSURER E:
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
I,~JI :Pol''\; TYPE OF INSURANCE POLICY NUMBER "'" ICYEFFE"""'" PO tCYEXPIRA LIMITS
N R M
A ~NERAL LlABIUTY GL08000015 6/1/2008 6/1/2009 EACH OCCURRENCE $ 2-,-OJLQ,.OJ!JL
X D~ERCIAl GENERAL LIABILITY ..&1f~UJt.=err<;eI_ ~10_0.,.0.ll.lL
>-- CLAIMS MADE [X] OCCUR MED EXP lAtri one De""") $ ,5.,,0.0.0_
f- PERSONAL & AOV INJURY $ .2..0.0.0..,O.O,L
>-- GENERAL AGGREGO. TE $ 4,-0.OJ!.&0_L
n'LAGG~nE,LlMIT APnS PER: PRODUCTS. COMPIOP AGO $ 4..,0 0 O,JlJLCL
POlICY P,fR;: LOC
B ~OMOBIU! LlABIUTY ASKZ91440775018 6/1/2008 6/1/2009 COMBINED SINGLE LIMIT $ 2.000.000
X ANY AUTO (Eo ecddent)
>-- ALL OWNED AUTOS BODILY INJURY
S
SCHEDULED AUTOS (Per peroon)
f-
f- HIRED AUTOS BODILY INJURY
(PO' occidenl) $
f- NON.OWNEDAUTOS
X $.1",90 O_~ClDlPJt~4.,- PROPERTY DAMAGE
Iv 1~1.000 ..~" I_'~ft D..d (Per acddenIl $
RRAGELlABIUTY AUTO ONLY. EA ACCIDENT $
ANY AUTO OTHER THAN ~ f!.---
AUTO ONLY; AGG $
C m="~'""~~ BE6564664 6/1/2008 6/1/2009 EACH OCCURRENCE $ s..JUtO.. JLO.O_
X OCCUR 0 CLAIMS MADE AGGREGATE $ 5._0_0_0,,_0_0_0_
$
DEDUCTIBlE $
RETENTION $ 10,001 $
D WORKERS COMPENSATION WC08000050 6/1/2008 6/1/2009 x~tJlfs I IOllt
AND EMPLOYERS' LlABIUTY Y I N
D ~~~~~~~~~~I~~ECUT1VE[E] WC0800004B 6/1/2008 6/1/2009 E.L EACH ACCIDENT $ 1,..o..oJ!..JlJlJL
D (.......to<y In NHI WC08000049 6/1/2008 6/1/2009 E.L DISEASE. EA EMPlOYEE $ .1"O,O_0.._0_OJL
~~~~~N~"""" E.L DISEASE. POlICY LIMIT S 1 000 nnn
OTHER
DESCRIPTION OF OPERATIONS I LOCATIONS I VEHICLES I EXCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS
Title of Job. Heritage Park and Parking Garage project No. RFQ-09-03-01
CERTIFICATE HOLDER CANCELLA nON
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
DATE THEREOF. THE ISSUING INSURER WILL ENDEAVOR TO MAIL ~ DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
IMPOSE NO OBLIGATION OR LlABIUTY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
i~~~oo~o~~~ i:~~~eB..ach REPRESENTATIVES.
~RIZEDREPRESENTAm
Sunny Isl..s Beach, FL 33160 ."LV. ,.
ACORD 2512009/01) Coll.2662354 Tpl.779969 Cert.12356922 @1988-2009 ACORD CORPORATION, All rights reserved.
The ACORD name and logo are registered marks of ACORD
~ !!t'!BI!~.!:.
FLORIDA LICENCES
K2;.,;~~~:@<<Jg'~~~~~~~.~~~S'~T' ~~if"~Ez~.?O'~~F"~~~,'~O~R"~I~D~~~~.~)~;;-'r~~~~(:;;'J~~,f. If '.-J~i'~~. ~ . ~
~~' ~~~~- ~~~-. t:{.~~~, "~~@,' imr~I~~~~1.tI?S'j~~[t~ _.~ .~~; 4"'~~ ~.~:":'_..(" __ ~~~~~:t~IJ.:~~t .~~;J46: ~'''.-~~ ~__ ,J.. _~~l:~,.*'h~ ";': '. 1~~l~!,".1
1;.!.(:ffjl":@ 1(i.d~}-;;;~~~)t ~"1~ .~"",,,"1;.~ ,)>::~f('~I~-;:~'; m-{~),/~.~..,(~)l".~. {,,>>r/..i)"(""I'i:-;iJJ"({W't..H;.,~t~~,\~~. ~(~\'7""'.~.(l.'":7. .... ,!~ ~.~. '~.'~ 'r.".. 't' A . "_. rJ(t.. 1
.!,i;k. ;::<;ii~\~: ~J~)\~~" l?ARTMENW,>'?O~IBUS~N1i:SS5..AND,:;:-PlWFJ:iSSIONAt.~),'REGqL~TION::;:,:~...):~I}',i,:~:;.:' ,~1.3~ .,:~l~~
'*!.~)~~'~~~}~~~ ~"T^il l'g!WACONSTRUC-'1U:ON~:ENDU.-S_TR~.,'Ii~eENSIN~,~B0AlU>,1\~rJ~Z' ~':~SEQ# L9.:70 6';a 8,6 0591
}~W~~;:?:~~~~~.w~%';h"1~_ ..,:~~~~~~tES~:!$l~\&~21.~~,$!-l~~J~~~,~~J#~~W.wJ~I,~)$;;;Jl~,~,~~ ,-y.~~2}Jl~'iJ.,.Jf$Jf.,;,:,,'~~~'MI(~~~
.', : . L.'ICENSEy,NBRr~~~E S"'~::';')",-\@,,(, ~\{i!2/(:-m:(~\''''P'J!I) ~,<..,:;;!., "!, ." "!;:::'" I"""'~': '.'< '~, I'. .'."'.?~
.1 '''.~",\\_.''.~:'.r;'".\'''..~_ ;..~.....,-~-G ~_~a. ....4~,~:.J~~;~,r?-:o-~.,lJf~:~ ~.-;-..,,\"').'~':.. ,I, I-c; .~ '~JJ ;;~\ "'.l'~~'r. ~. ," '_ ."'; '~
,",_-'>6--~'~'~'-'''''~'''~~'~I~'''''_'}~~'_'_~ V' ~V'/~"-'~~'."~("-'~ ~'"'/..; ... I" ,. .
Stl ;(rt~2~'}1(fo7Z O~iMli?g~w:0 '-'iabIl:;r,~SI~ ~ ~ n~I&@~~@)1~~t2)m@<)~~0A~.,*~I:.1~~~&~:?>~~~~,
~1~~'~{W:h:e'{~:BuS:~~'S:$~~1)RGANi:'Z~m6N:\~ij.~ --~ ; ~.: ~\~~mi;~;:j.'i;~' ,~s.!.t'~~l\ ')I~" '''~;~'~~t~~ 'J;~"'~"("<"~'
~@~an.:~, h4E!1'~loi.~~-ISttiUAr::t"F-t:ED'r'~.~)\ ('.j -,' ~-::::. -0. ~ ,.- =~ - ~~i'~4:(i.!Jk~ i\;i~~j"..:i};''' 1"~~ \1~ ;:'~. ;c~~:'
':;r;:,I,.fT" 'a ,",,'X}ll':\t'-t' \..,,,,,'li':.:!~~')~i1't.~ ",. ,,,.:;;t""f. ,lo1-P.CRh"t.':i:, '- " ' <7-.F..S' =--.' LO .{,;)r.'{~\~,,)rc: ;*!' .'j~ ~':~:.\ 'll jf; ',( . )1;'.<,;fr 'r. ': I
'b~,'Un er"''' De~ ....Ov,;1s1ons-.-.v~, ap 'I.' - ,*,,'~':A "'.~, .'1: - ~ -"'- '''1;"
9.,':;..~-."q',<",..,r):\"~d"~t''''r:'~AUG~'I'3'l!~200''9 .....:..... 2f ~~:~~7~~ '-'c)'r \1 ,\1' II ~~' . I.~
~~l,;.~~--:-TfI~~~i~~~6!,t'~A:~'."~C ' '~E{~,"b'"g(- EiRE' 0RK~:"f~i!iJ:~;1~itOWS~(@;!t ~~.~ :' [~" .~';:.-; M.~"-, :h.",-
'"l~ ILt, ~.ft~~,..~ -'~.. ~....,.~tift EiH,.. "ll~' U~\"'_ !i5~.' .. .~~ ~- .'J!:~._ .......)-;i<r( '\t.'.. !l~~* J~r I~~["'l >:)J!f;f'JL.", ,(0, ~ I
~~ ,~~~~~~~g)~~,,~~~~~;~':9mi~X(f:Jt~P. ~ .~ . e.llA~]~"FI~.:.EJjJ~.~ 'i';/' ;.o~''''~ 'tP ;\~ ~:,..." - ~~- ~~i;~ 'lJi ~
.,'~~r:i;fuE':~RK'i.iKJl:LLl:'iI'~bMP';f~';':'~H:'i:)~ti';':9' it':;" f::;). · . · (.,;~:" '" ').g~! ~ I, '~J ...~,~:i ~I;(\.. J:,) ~ '-'-W
~,>;f:) "'"J"";"*: .,~ :'.JI.'_.~. ~~j~~!~~\J:~~g19J~!f~ ~'" ,-d . ~ .')~.;~I,A*~ ,\tt<)~~~~.~~~ ~)@:!~ t,l;.m ~~ ~::.
''?'<)~Jl~ic~a~~fi~~i~~~:')~~iW~~vg2~IO~t!~~~58.0l> WE "t~\.l >/~$)r@f&,t%I'~I~f ~~Y'., ll. .~ ~w; ").' ;:...,\' .)J\&"\:t.
'.~ """""d"~,,"""y'1,;.:",",,,',\\, J', a ,~"p' ,~x'''.J.&''''''~'~r'~~. .. q{ . 1, ~' "
f.-........ I~~'" ~,.1-,'1? ""UI '" <..i .._, ..4~~.;,;~i'" l.r,;::'.T"')~~1 .......'t;l...... ( ... ~~r"'" i., ~~ 'f ._
o;;(?" $i:~' }J?;"~iDf.;ti~f.A\(~:'K..(;ti.. -' ~IJ .!ii:!_:' ~~~~fu,*,_ '3ik,.~ ~ij)'ti:ii 1c)t'l}t ~)li' .A\~)t. {'it'~'!( _ ><,_ ~;:::; It..o.,,. . ':.. r:;,
r..... ~\l'i:. ;;"'i::T'{.'''(.;'0l;>1f[','''i'!~(,'''''- ""'~'7',~y'(.;"'/.~;!;m~ =~(:;:.;~=~ ;:;~~ '..-,~,.r-",,-,-" -iVi- -___ ~. r_ ~~.., ~ )
g% j>>i:!.h,'!;':i~r)l~;~:~!f :...i9.~L.;'ti. :h9'f;;k~11<l).:3r.~\"!!Jgg~a\~~~\E( '~~J ~(W~!&.~\.t.I~'k-d,I~1;:b(.l'l:i-r"i:-'!bl,~;-,9i ~(> .'''e,)t':!t y;.,,L~:; ~).!.I... !t,_~ ~B:;~
;~Y!J;#:. 1{?':~\)/.~:":!.('\'~)~~~'!f(~>)~"~:f<\~~;31~~~~~)~->T~~~l' ...&.~,~, ~"~f:;'j)r~";:-"<f{:;;\t~~~~WQ'P',.>5~\'''',~<r~i' ,~t;2f.," ....,. .J ;1:,. \1. ~Jl':'~, ...,,:::-~ ~,,';. .;~ ~
";'''';;;~I~'''' C9i''''RT.)'''Er.CR'''ClITl:I)~' ')' r:;~ i""~'''''' "~:J::'c~'" 'il;}='\, '," '1&:a11.~~'~ c,,,_ ,- ~r"'i)\'>"'''''';luO'''LY:'l' BENSON"" ;). .... ~ ll.."".
1(.;[J;}fir .or ~1.L=~5 -;&,'I"':~;'(.I,: ~~. 'i *~k~~('1'~i~~ /.(~& ...., \;f';j) ~ i(:f~:\?:';.;::{.~i'~. . In),.~".:..' . - :K~ ~ '-
"r"':~'.i~V~~'lOOVEKN(!)R~~(.~'1 .,nlJi.,.... )y{r..,~~... - ',.. --'f ~ r ~ ~~--~* I l.C... -~ ~oJ-!; JC\: I SE9RET~Y,...~ "'7 ~ ~ ;~I '-;.1
.~ '~''').,;''.. i':"~'),..ut':t-:~
S1 Ate OF. FtORIDA
DEPARTMENT.OF BUSINESS AND PROFESSIONAL REGULATION
" " CON~TRUC:I~~ ~USTRY LICENSING BOARD SEQ# L08080900434
: . LICENSE. R' , '"
.,;::, ............ ... '........ ...... AC. l..
08 09 2008 o 8802'g399' CGCO'62789...,.t..~ "':..
The GBNERAt' CONTRACTOR ,'0; ~ ~~j"r ft
Named below IS CERTIFIED ...~' '-
Under the provi. sions Of. C;hapteJ;': .&.cg_ FS.
Expiration date: AUG 3l;., -~()~O -;,' :(,= '
:;-1"
1lrt
PARMENTER, DANNY SCOTT
THE HASKELL'COMPANY
3981 SUSAN DRIVE'
GREEN'COVE SPRINGS
'", "1
FL 32043
.'- ...~
ACt 3904062
CHARLIE CRIST
GOVERNOR
CHARLES W. DRAGO
SECRETARY
~ !!!!BI!~!:.
SWORN STATEMENT PURSUANT TO SECTION 287. 133(3)(a)
FLORIDA STATUTES, ON PUBLIC ENTITY CRIMES
THIS FORM Iv1UST BE SIGNED AND SWORN TO IN THE PRESENCE OF A NOTARY
PUBLIC OR OTHER OFFICIAL AUTHORIZED TO ADMINISTER OATHS.
1. This sworn statement is submitted
to The City of Sunny Isles Beach
by The Haskell Company
for The City of Sunny Isles Beach Heritage Park and Parking Garage
whose business address is
8301 Florida Drive, Suite 200
Pembroke Pines, FL 33025
and (if applicable) its Federal Employer Identification Number (FEIN)
59-238-7450
(If the entity had no FEIN, i.i1clude the Social Security Number of the individual signing this
sworn statement:
2. I understand that a "public entity crime" as defined in Paragraph 287.133(l)(g), Florida
Statutes, means a violation of any state or federal law by a person with respect to and directly
related to the transaction of business with any public entity or with an agency or political
subdivision of any other state or of the United States, induding, but not limited to, any bid or
contract for goods or services to be provided to any public entity or an agency or political
subdivision of any other state or of the United States and involving antitrust, fraud, theft,
bribery, collusion, racketeering, conspiracy, or material misrepresentation.
3. I understand that "convicted" or "conviction" as defined in Paragraph 287.133(l)(b), Florida
Statutes means a finding of guilt or a conviction of a public entity crime, with or without an
adjudication of guilt, in any federal or state trial court of record relating to charges brought by
indictment or infomlation after July 1, 1989, as a result of a jury verdict, nonjury trial, or entry
of a plea of guilty or nolo contenders.
4. I understand that an "affiliate" as defined in Paragraph 287. 133(1)(a), Florida Statutes, means:
a. A predecessor or successor of a person convicted of a public entity crime; or
b. An entity under the control of any natural person who is active in the management of the
entity and who has been convicted of a public entity come. The term "affiliate" includes
those officers, directors, executives, partners, shareholders, employees, members, and
agents who are active in the management of an affiliate. The ownership by one person of
shares constituting a controlling interest in another person, or a pooling of equipment or
income among persons when not for fair market value under an arm's length agreement,
shall be a prima facie case that one person controls another person. A person who
knowingly enters into a joint venture with a person who has been convicted of a public
entity crime in Florida during the preceding 36 months shall be considered an affiliate.
5. I understand that a "person" as defined in Paragraph 287. 133(l)(e), Florida Statutes, means any
natural person or entity organized under the laws of any state or of the United States with the
legal power to enter into a binding contract and which bids or applies to bid on contracts for
the provision of goods or services let by a public entity, or which otherwise transacts or applies
to transact business with a public entity. The term "person" includes those officers, directors,
executives, partners, shareholders, employees, members, and agents who are active in
management of any entity.
6. Based on information and belief, the statement which I have marked below is true in a
relation to the entity submitting this sworn statement. (Please indicate which one (1) of the
following three (3) statements is applicable.)
~ (1) Neither the entity submitting this sworn statement, nor any of its officers, directors,
executives, partners, shareholders, employees, members, or agents who are active in the
management of the entity, or any affiliate of the entity has been charged with and convicted of a
public entity crime within the past 36 months.
(2) The entity submitting this sworn statement, or one or more of its officers, directors,
executives, partners, shareholders, employees, members, or agents who are active in the
management of the entity, or any affiliate of the entity has been charged with and convicted of a
public entity crime within the past 36 months.
(3) The entity submitting this sworn statement, or one or more of its officers, directors,
executives, partners, shareholders, employees, members, or agents who are active in the
management of the entity, or agents who are active in management of the entity, or any affiliate
of the entity has been charged with and convicted of a public entity crime within the past 36
months. However, there has been a subsequent proceeding before a Hearing Officers of the State
of Florida, Division of Administrative Hearings and the Final Order by the Hearing Officer
determined that it was not in the public interest to place the entity submitting this sworn
statement on the convicted vendor list. (Attached is a copy of the final order.)
I UNDERST AND THAT THE SUBMISSION OF THIS FORM TO THE CONTRACTING
OFFICER FOR THE PUBLIC ENTITY IDENTIFIED IN PARAGRAPH 1 (ONE) ABOVE IS
FOR THE PUBLIC ENTITY ONLY AND, THAT THIS FORM IS VALID THROUGH
DECEMBER 31 OF THE CALENDAR YEAR IN WHICH IT IS FILED AND FOR THE
PERIOD OF THE CONTRACT ENTERED INTO , WHICHEVER PERIOD IS LONGER. I
ALSO UNDERST AND THAT I AM REQUIRED TO INFORM THE PUBLIC ENTITY
PRIOR TO ENTERING INTO A CONTRACT IN EXCESS OF THE THRESHOLD AMOUNT
PROVIDED IN SECTION 287.017, FLORIDA STATUTES FOR THE CATEGORY TWO OF
~HAN INT INFORMATION CONTAINED IN THIS FORM.
U Don Kartzmark
SIGNATU (Printed or Typed Legal Name of Affiant)
'~
State of Florida of County of Miami-Dade . ~
Sworn to and subscribed before me this ~ day of ''Y'UL
It /IJ/tuk Ii &nwZ-
9-/& -/2-
..\\\\\1111111111,.
,'I' G A IiI.
,,;~'\<,.\\>.. . DAJ.I "t
....t. ~,'\, ....... ''14S' ...,....
j/o~...~" StO"~e.ai~-:.~
-'. .'_C'i ~~,.;~ . .-
.:;;- :U'"g; I?,.U>'-t<:'::
~E :ti~ T.J \ ~
_.. 0 CIJ ..... . <" _..
:;;:-/f~ 'a~-':
~. 111'\0 \)~'3~2 : iF.~
,~.. u .a~''':
'~.,~." 8ond~~~ ...~,~~~~
"".... -. r,. . .""'"'
." -1"". ..IOyFaKl' .0' &.-.:;-
~"..'rr p .e..... -:\~ ".~~
"f/.,. ;;8/ Ie ~;'i\>- :-;;.,"
, d!/fliIH\I.\l\\\\'
Notary's Name Printed, Stamped or Typed
Personally Known:
~
or Produced Identification _
Identification Produced
, 2009 by
1A
NON-COLLUSIVE AF FIDA VIT
State of
Florida)
County of
Miami-Dade)
Don Kartzmark
and says that:
being first duly sworn, deposes
(1) He/she is the (Owner, Partner, Officer, Representative or Agent) of the Bidder that has
submiited the attached Bid;
(2) He/she is fully informed respecting the preparation and contents of the attached Bid and
of all pertinent circumstances respecting such Bid;
(3) Such Bid is genuine and is not a collusive or sham Bid;
(4) Neither the said bidder nor any of its officers, partners, owners, agents, representatives,
employees or parties in interest, including this affiant, have in any way colluded, conspired,
connived or agreed, directly or indirectly, with any other Bidder, firm, or person to submit a
collusive or sham Bid in connection with the Work for which the attached Bid has been
submitted; or to refrain from bidding in connection with such Work; or have in any manner,
directly or indirectly, sought by agreement or collusion, or communication, or conference with
any Bidder, firm, or person to fix the price or prices in the attached Bid or of any other Bidder, or
to fix any overhead, profit, or cost elements of the Bid price or the Bid price of any other Bidder,
or to secure through any collusion, conspiracy, connivance, or unlawful agreement any
advantage against the City of SUll.llY Isles Beach, Florida, or any person interested in the
proposed Work;
(5) The price or prices quoted in the attached Bid are fair and proper and are not tainted by
any collusion, conspiracy, connivance, or unlawful agreement on the part of the Bidder or any
other of its agents, representatives, owners, employees or parties in interest, including this
I ant.
Don Kartzmark
(Printed or Typed Legal Name of Affiant)
State of Florida of County of Miami-Dade 11
Sworn to and subscribed before me this r; day of
/) '-l I{ 1'1 /
((/ /lvu VI/V /..J - /-fdi2/771 L--
\f,;t,~/:: /2-
Not:~fti.. ~6a~OAi;""i,,1.,
.,,<~~\ .a......:~8 "#;..
//g::. ..~~"'S\ON€tA... \.;
'.'-,..... .."~' 116 :r.n. -"
::: '-'''_D''''~'<;)ra '<'o'~.. ',,::
.;; :~~ ~(P~1cS.
-::: :::e5f .:::
:..:: . en ... : <;::
-~. nA'l.,2,. Cl_.
~ ~ "I"\\) '0'2:.:1"'" : 9':::::
. . . wIJ,A . o~.
'..~. Kle6~~.<S:"~
Ndr~~~~~led, Stamped or Typed
'-i;~,.PU8lIC (2i\l>-;,,~~' V
{.'iN! :ijH', ;\\,\\..
Personally Riiown: _ or Produced Identification
~
Identification Produced
. 2009 by
WIllis HRH
April 6, 2009
City of Sunny Isles Beach
18070 Collins Avenue
Sunny Isles Beach, FL 33160
Re: Professional Construction Services for the Heritage
Park and Parking Garage City RFQ No. 09-03-01
Dear Selection Committee:
The Haskell Company is a highly regarded and valued client of Travelers Casualty and Surety Company of
America and Fidelity and Deposit Company of Maryland. We hold its management in the highest regard.
The Haskell Company has performed a wide variety of projects including design build, federal work, school
projects, medical facilities, and various other commercial and government work. We have had the privilege
of providing The Haskell Company with bonds in the low nine-figure range, while their work program was in
the moderate nine-figure range.
For qualification purposes, we are favorably considering providing the performance and payment bonds for
the captioned project.
Naturally, Travelers Casualty and Surety Company of America and Fidelity and Deposit Company of
Maryland reserve the right to underwrite each surety obligation individually at the time bid or final bonds are
required. We also expect that the execution of any final bonds would be subject to a review of the final
contract terms, conditions and financing by our client and ourselves.
We confirm that Travelers Casualty and Surety Company of America and Fidelity and Deposit Company of
Maryland carry Best Ratings of A+YJ.V and ~ respectively. In addition, the sureties are listed with the
United States Department of Treasury's Listing of approved sureties and properly licensed to conduct
business in the State of Florida.
The terms of this letter are valid for a period of six months. Should the need arise for this period to be
extended; it must be done so by the surety in the form of written notification.
If you should need further assurances on our fine client, please contact our office.
Sincerely,
Anett Cardinale
Attorney-In-Fact
Florida Licensed Resident Agent
Willis HRH, Inc.
3000 Bayport Drive, Suite 300
Tampa, FL 33607
Telephone: (813) 281-2095
Fax: (813) 281-2234
~
TRAVELERSJ
POWER OF ATTORNEY
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
Farmington Casualty Company
Fidelity and Guaranty Insurance Company
Fidelity and Guaranty Insurance Underwriters, Inc.
Seaboard Surety Company
St. Paul Fire and Marine Insurance Comp~ny
Attorney-In Fact No.
219786
St. Paul Guardian Insurance Company
St. Paul Mercury Insurance Company
Travelers Casualty and Surety Company
Travelers Casualty and Surety Company of America
United States Fidelity and Guaranty Company
Certificate No. 0 0 2 7116 8 4
KNOW ALL MEN BY THESE PRESENTS: That Seaboard Surety Company is a corporation duly organized under the laws of the State of New York, that SI. Paul
Fire and Marine Insurance Company, SI. Paul Guardian Insurance Company and SI. Paul Mercury Insurance Company are corporations duly organized under the laws
of the State of Minnesota, that Farmington Casualty Company, Travelers Casualty and Surety Company, and Travelers Casualty and Surety Company of America are
corporations duly organized under the laws of the State of Connecticut, that United States Fidelity and Guaranty Company is a corporation duly organized under the
laws of the State of Maryland, that Fidelity and Guaranty Insurance Company is a corporation duly organized under the laws of the State of Iowa, and that Fidelity and
Guaranty Insurance Underwriters, Inc. is a corporation duly organized under the laws of the State of Wisconsin (herein collectively called the "Companies"), and that
the Companies do hereby make, constitute and appoint
David H. Carr, James W. Dunn, Anell Cardinale, Linda Horn, Margaret A. Ginem, and Carol H. Hermes
of the City of Tampa ' State of Florida . their true and lawful Attorney(s)-in-Fact,
each in their separate capacity if more than one is named above, to sign, execute. seal and acknowledge any and all bonds, recognizances, conditional undertakings and
other writings obligatory in the nature thereof on behalf of the Companies in theifobusiness of;guaranteeing the fidelity of persons, guaranteeing the performance of
contracts and executing or guaranteeing bonds and undertakings required or .perm, "ittedin anY'a.~Jions Qlp.foceedings allowed by law.
~\..\... ~ ~~. .\,V
1 \1..\~ .~~~\~ ~\-;
~~ o~ ,-<\~ ..~~5'
IN WITNESS WHEREOF. the Comp'anies have caused this instrurri~~tISbesH~n~~dJ~e. ~c;:torate seals to be hereto affixed, this
d f November 2008 -{',:V. \'''. ,-L. 1>.' (". ~ .
ay 0 " (,\.~' . ~ V .~ "-
"'\)~' . {~~ .' ~~~
Farmington Casualty Conl~ny" <\.\\..' ,*"\.
Fidelity and Guaranty\In~rance( Compan)'r.,. 0
Fidelity and Guaranty>Insu1~b~Underwri(ers, Inc.
Seaboard Surety Company
SI. Paul Fire and Marine Insurance Company
~\.'1""
~..~ "f). ."~
(>""'" . ~
~:-t.J' ,po
U"ANC\.
~",.,,"
State of Connecticut
City of Hartford ss.
19th
St. Paul Guardian Insurance Company
SI. Paul Mercury Insurance Company
Travelers Casualty and Surety Company
Travelers Casualty and Surety Company of America
United States Fidelity and Guaranty Company
/;;::?i;-;,",.
{!{~"PORI4;~~~"'"
~' _._ '0
-S~\S'EAL./!
Or..... ....-4
-.il'....;... ,..~
.-
By:
19th November 2008
On this the day of ' before me personally appeared George W. Thompson. who acknowledged himself
to be the Senior Vice President of Farmington Casualty Company, Fidelity and Guaranty Insurance Company. Fidelity and Guaranty Insurance Underwriters. Inc.,
Seaboard Surety Company, SI. Paul Fire and Marine Insurance Company. SI. Paul Guardian Insurance Company, SI. Paul Mercury Insurance Company, Travelers
Casualty and Surety Company, Travelers Casualty and Surety Company of America, and United States Fidelity and Guaranty Company, and that he. as such, being
authorized so to do, executed the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer.
In Witness Whereof, I hereunto set my hand and official seal.
My Commission expires the 30th day of June. 2011.
58440-5-07 Printed in U.S.A.
"f(\w c. j~
'- Marie C. Tetreault, Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of Farmington Casualty Company, Fidelity
and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters, Inc., Seaboard Surety Company, SI. Paul Fire and Marine Insurance Company.
SI. Paul Guardian Insurance Company, SI. Paul Mercury Insurance Company. Travelers Casualty and Surety Company, Travelers Casualty and Surety Company of
America, and United States Fidelity and Guaranty Company. which resolutions are now in full force and effect, reading as follows:
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
RESOLVED, that the Chairman, the President, any Vice Chairman. any Executive Vice President, any Senior Vice President, any Vice President. any Second Vice
President. the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attorneys-in-Fact and Agents to act for and on behalf
of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the
Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a bond, recognizance, or conditional undertaking, and any
of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her; and it is
I
I
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President may
delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such delegation is in writing and a copy
thereof is filed in the office of the Secretary; and it is
FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional undertaking
shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice
President, any Second Vice President. the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the
Company's seal by a Secretary or Assistant Secretary; or (b) duly executed (under seal, if required) by one or more Attorneys-in-Fact and Agents pursuant to the power
prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President. any Vice President,
any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any power of attorney or to any certificate
relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys-in-Fact for purposes only of executing and attesting bonds and
undertakings and other writings obligatory in the nature thereof, and any such power of attorney or certificate bearing such facsimile signature or facsimile seal shall be
valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on the
Company in the future with respect to any bond or understanding to which it is attached.
I, Kori M. Johanson, the undersigned, Assistant Secretary; of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance
Underwriters, Inc., Seaboard Surety Company, SI. Paul Fire and Marine Insurance Company, SI. Paul Guardian Insurance Company, SI. Paul Mercury Insurance
Company, Travelers Casualty and Surety Company, Travelers Casualty and Sun,ty. C~mpany.ofAmerica,.and United States Fidelity and Guaranty Company do hereby
certify that the above and foregoing is a true and correct copy of the Power~of:Ati<rr;;-ey,exebut~~ by\saiJl'c'ompanies, which is in full force and effect and has not been
" ,,,, .. "" '1' ~ "" ~..'
revoked. ,~\:.... N\'J" -\~ \""
"",-N t ~,"l ~ ~ _ -\'\\)
... ..:. ~"-'. ,S ....1: \.........J
IN TESTIMONY WHEHEOF, I have hereunto set my hand and,a[fixed the seals orsaid,Coli;Ip~ll1ies this
,~~~;. . 4"\;) .~ ,\ ~,.
.,,?...\ . i. \'\ .~ ~
,,\'\.:, ... ) "-) . .\'~.~ J
(\ . .... ,\" \..J~'
~. \'\ {)~
',...:;4 \")'--
6th
day of
April
CB
.20 _'
Kori M. Johans
@
~'ED
19~1,
.......~~~.........
/~v~""""".....:1-('I\
I :/~o~PDR..q,.~,,~ 1"'1"
l~i --- io
~~:SE:!JlL./ P
~'s......~.....~~<4b
"..-
~......
"''''''''
'jj~ - \.
a
To verify the authenticity of this Power of Attorney, call 1-800-421-3880 or contact us at www.travelersbond.com. Please refer to the Attorney-In-Fact number, the
above-named individuals and the details of the bond to which the power is attached.
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RFn RnI':mI=Q
j
I
J
I
I
j
Power of Attorney
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
KNOW ALL MEN BY THESE PRESENTS: That the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, a
corporation of the State of Maryland, by FRANK E. MARTIN JR., Vice President, and ERIC D. BARNES, Assistant
Secretary, in pursuance of authority granted by Article VI, Section 2, of the BY-Law. of said ~ny, which are set forth on
the reverse side hereof and are hereby certified to be in full force and effect on the d lbfi:hereby nominate,
constitute and appoint James W. DUNN, David H. CARR, Carol H. ~~E' Margaret A.
GINEM, Linda HORN and Denise TAYLOR, all of Tam , '~~ 0 nt and Attorney-in-
Fact, to make, execute, seal and deliver, for, and on . ~a ~\ : any and all bonds and
undertakings, and the executionofEuc ~ 0 In' ~Pthese presents, shall be as binding upon said
Company, as fully and ampl t let U . t I een duly executed and acknowledged by the
regularly elected Of~U:~~~i~~ f . ore, Md., in their own proper persons. This power of attorney
revokes that issued ~ . l.ThtN, avid H. CARR, Carol H. HERMES, Anett CARDINALE, M.L. GRAY,
Margaret A. GINEM~~~ Ise TAYLOR, dated August 10, 2007.
The said Assistant Sefr'etrnY does hereby certify that the extract set forth on the reverse side hereof is a true copy of Article VI,
Section 2, of the By-Laws of said Company, and is now in force.
IN WITNESS WHEREOF, the said Vice-President and Assistant Secretary have hereunto subscribed their names and
affixed the Corporate Seal of the said FIDELITY AND DEPOSIT COMPANY OF MARYLAND, this 3rd day of March,
A.D. 2008.
ATTEST:
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
~ /),~
By:
Assistant Secretary Frank E. Martin Jr.
-:Jid!it z~tMr-d-'-
Eric D. Barnes
Vice President
State of Maryland }SS'
City of Baltimore .
On this 3rd day of March, A.D. 2008, before the subscriber, a Notary Public of the State of Maryland, duly
commissioned and qualified, came FRANK E. MARTIN JR., Vice President, and ERIC D. BARNES, Assistant Secretary of
the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, to me personally known to be the individuals and officers
described in and who executed the preceding instrument, and they each acknowledged the execution of the same, and being
by me duly sworn, severally and each for himself deposeth and saith, that they are the said officers of the Company aforesaid,
and that the seal affixed to the preceding instrument is the Corporate Seal of said Company, and that the said Corporate Seal
and their signatures as such officers were duly affixed and subscribed to the said instrument by the authority and direction of
the said Corporation.
IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed my Official Seal the day and year first above
written.
-..,\\\\~:'I ~~~ ~tll~1
~t..\'~\'~:""""":{"-("''''
t /" U(')~/(;>~~~
~ td ( c . . !":'
-.;.~\4(, "i:.
~ t:." l: II (# ./(... ,,'
'/,(~r'l.""""~:'\"'"
1IIIi f;(:~': \ ~\\\\
~D~
Maria D. Adamski Notary Public
My Commission Expires: July 8,2011
POA-F 031-3190
~
EXTRACT FROM BY-LAWS OF FIDELITY AND DEPOSIT COMPANY OF MARYLAND
':Article VI, Section 2. The Chairman of the Board, or the President, or any Executive Vice-President, or any of the Senior
Vice-Presidents or Vice-Presidents specially authorized so to do by the Board of Directors or by the Executive Committee,
shall have power, by and with the concurrence of the Secretary or anyone of the Assistant Secretaries, to appoint Resident
Vice-Presidents, Assistant Vice-Presidents and Attorneys-in-Fact as the business of the Company may require, or to
authorize any person or persons to execute on behalf of the Company any bonds, undertaking, recognizances, stipulations,
policies, contracts, agreements, deeds, and releases and assignments of judgements, decrees, mortgages and instruments in
the nature ofmortgages,...and to affix the seal of the Company thereto."
CERTIFICATE
I, the undersigned, Assistant Secretary of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, do hereby certify
that the foregoing Power of Attorney is still in full force and effect on the date of this certificate; and I do further certify that
the Vice-President who executed the said Power of Attorney was one of the additional Vice-Presidents specially authorized
by the Board of Directors to appoint any Attorney-in-Fact as provided in Article VI, Section 2, of the By-Laws of the
FIDELITY AND DEPOSIT COMPANY OF MARYLAND.
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the
Board of Directors of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at a meeting duly called and held on
the 10th day of May, 1990.
RESOL VED: "That the facsimile or mechanically reproduced seal of the company and facsimile or mechanically
reproduced signature of any Vice-President, Secretary, or Assistant Secretary of the Company, whether made heretofore or
hereafter, wherever appearing upon a certified copy of any power of attorney issued by the Company, shall be valid and
binding upon the Company with the same force and effect as though manually affixed."
IN TESTIMONY WHEREOF, I have hereunto subscribed my name and affixed the corporate seal of the said Company,
this
6th
day of
flpril
2{JE
M111f;
Assistant Secretary
~
,
'-
___:- "-- EXECUTIVE SUMMARY
J
..
More CAPABILITIES, more value for you
Dear Selection Committee Members:
Value is that quality of anything which renders it desirable or useful.
Because we promise to team with the City of Sunny Isles Beach
to deliver the best possible project, done right the first time, and at
a good price, value is guaranteed. With a schedule that gets you
parking by March, a price that is fair, with Subcontractors you can
count on, and alternatives to make your building better, Haskell gives
you value.
Haskell believes in giving our clients more than they expect, so in
addition to standard construction services, we offer the following unique benefits for you:
1. Fastest Possible Delivery of the Parking Garage - We understand you need your new garage as quickly
as possible to start generating revenue for the City. In partnership with you and your design team, Haskell
will evaluate the fastest structural system for delivering the parking garage. You can be parking cars in
your garage by March of 2010. Please see section 1 for more detailed information regarding our proposed
schedule and section 3 for our mobilization schedule.
2. The Right Price - Using only competent, proven Subcontractors in our proposal, you can be certain you
will get a quality project, which will run smooth, safe, and done right the first time. You will get this all at a good
price. Best of all, you get the value you want way below your budget. See section 2 for our price proposal.
3. Real Value Engineering Solutions - In addition to our construction management services, Haskell is an
expert designer of parking garages. Our in-house design staff and construction professionals have evaluated
your design and made recommendations to save time and achieve your goal of getting a great product at a
good price. Please see section 4 for our approach and alternatives and section 5 for the base park alternative.
4. Parking Garage and Public Park Expertise - Typically, condominium builders are not parking garage
builders. Haskell has completed in excess of 50 parking garages and several public parks so you can be
confident both will be completed by competent professionals.
5. A Team Philosophy - In partnership with you, Haskell is prepared to deliver the park and parking garage
as quickly and efficiently as possible.
Value is difficult to measure, but if selected for the Heritage Park and Parking Garage, Haskell will ensure the
City of Sunny Isles gets a new landmark it will be proud of for years to come.
Sincerely,
~e<o-
~ t!!,f.!.~~.~.
I SCHEDULE I
~~ ~!!~!~a!:'
SCHEDULE APPROACH
Please find your proposed construction schedule on the next two pages. Haskell
suggests 270 calendar days for Phase I (Parking Garage) as the contract time in the
Agreement and an additional 129 calendar days for Phase II (The Park). Of this, we will
require three weeks of mobilization for Phase I. The activities are schedule in work-
days. Our approach allows for normal inclement weather should it be required.
@
~
3'
Ol
<
Cl>
iil
~
rJI
CD
3
'I'
5"
!"'
..01111
-nen-uen()-um
~:gg3~~~
:::r3(il3~(il~
3-,rJlOlC"rJlOl
=1ilrJI-<OlrJI~
m!a.-gCT""g
8" g S" ~ ...,
~ CD ~
CD "0
"0 0
Q. :i"
~~
I
CD
...,
~
(Q-j
CD:;r
"'UCD
~I
7'tIl
tIl en
:::J7'
a.~
"'Uo
tIlo
~3
:::J"O
(QtIl
G)~
tIl
...,
tIl
(Q
CD
~
-nen
::1 Q)
(ii' ;:l.
:::rOo
o.Ol
Ol ~
_Cl>
Cl>
00
"-.J0l
00
01 ......
-- --
......0
o co
I--
()
o
0"
(il
f-o.
--
en
en Iii
~-6
C" Cl>
o a.
!!l. ()
~ g
2-Q
o Cl>
C CD
(il
en () ;;0 ~
~ooCD
C" Q S
o Cl> :::r 0
!!l.::Gl~
g?cnQ30
.Qia.Q'
5 3 Cl>
2" "0
CD ~
()
o
~
o
(il
CD
I\J I\J ~ ~
000 0
B
;;0 3
0-0
cB 0-
:::r ~
Gl ~
iil Ol
a. rJI
Cl> Cl>
-u .
:::r
Ol
rJI
Cl>
=
=
~~~~~~~@~~~~Q~~~~~~~~
,,"Ol~~<31-u3rJ1Cl> Cl>C o.g a.
5" : <p 5' Q) ~ en g ~ @ -I ~ "'0 ~ . <i en CD ~ ~
lC 0 -ilC Q -u 6l-U-< Dlpo iil -u a ~ ~ 2" llJ"O ()
lC 8 ~ m g C Ol ~ ~ -n 5 (il CD C" U Cl> rJI 3l
~ i Cl> ~ i ~ i ~ ~ 5 ~ @ ~ ;;0 ~ ~ ~ ~ ;
~ ~l ~~'~~~ ~~,~~ Cl>rJli~
! ~~ ~~ ! ~5"~ ~~~
~ ff ~ & (il g ~ '
o ~ iil (il rJI
~ Q a.
"" Cl>
~
-u ......
:::r ~ () ~ m ~ () -n 8 ~ 61
! ~ g ~ ~ ~ t- [ ~ ~ ~
"" -u lC 0_ ~ .S" ::!! 0 ~ lC
OlGlOl~":,,~;~
~~ PO~'en~()Q
~'lC ~ 'allJl ~en
Gl Cl> ~ Q, 5' "0
Ol21~ ~ ~~
Q3 =s =t CD' m
lCOO_' rJI
Cl> :::r Ol po
en
s:
"0
5'
lC
Ol
~
a.
rJI
cO'
~
Ol
lC
Cl>
......
I\)
co
.
~ ~ ~ ~ ~ ~ ~ W I\J I\J ~ I\J ~ ~ ~ ~ I\J m I\J I\J W
o 01 0 0 01 01 01 01 0 01 0 01 "-.J 0001 "-.J 01 0 0 01 0 01 01 01 01 01 01 0 0 0
en en en en
;: ;: ;= ;:
~ ~ ~ ~
'~'~o.3
lC ~' ~' ~ ~
> ~
cE CD
~ ~
~ Q a:
Cl>-rJl-Cl>
- rJI
I\) W ......
01 0 0 "-.J
en
~
~ a.
CD Cl>
Gl g
~ ~
5' -u
lC :::r
Ol
rJI
Cl>
-u
:::r
Ol
rJI
Cl>
I
..,
()
Ql
1il
~
a.
~
o
Ol
'<
rJI
~ -r-- -11.
~, ~ ~ :.....
Q) I\.) g. =
en I == 0
Cl> () N' Cl>
...J. g ~ 6"
g ~ g" ~
~ C 0
~ n 0
C o' ~
U ~ s:
0' 0
~ g o.
N'
!!l.
0'
~
> .
~ .
a. .
Ol .
~
a. .
.
. 8
~
~
C
U
o'
~
()
Ol
1il
~
a.
~
-i
:1,
3
@ -n
"0 0
Gl rJI 5
iil ~ ~
a. a. ~
Cl> 0' 0'
g' 5 ~
~-g.
en g
~
rJI
~
CD
-u
Ol
<
~
lC
()
Ol
1il
~
a.
~
f---
.
I\)
"-.J
o
.
.
()
-u
en
2"
o
2"
llJ (il
cO'
m
1il
() -n C 0
Q) ::;" :J s:
C Cl> a. @
;;= -u ~ - ~
· -u-a-~-;;o
I ~ - Ol
Cl> Cl> C" 5'
II-n -u<@g,;;o~
II ~ ~ ~ ~ ~ ~ ~, ~ ~
I ~ ~; ::!! ~ ~ ~ 5" (il
-u ;;0 Ol C" -, Cl> C
. I -u 0 0 a ~ ~ ~'i &
III · ~-~ -~ - f-~ -~ -g-~ -~-~-(il
-u ~-i~ 5"rJI~rJlOl
II ~;;o -uo~~ '~~f~
()-n>-8 ~oCl>.o OC"OlrJI~
~0"85"~en~QrJlpo~ ~~rJI=:::rGl
-,Oc:-::I-::I 0...,
~ ~ rJI Cl> lC :1, lC ::!! 3 Cl> ~ Ol
· r -~-~-5!-@-Q'-~'-cg-~,-gJ-~-Q-~
() IT! 5'. (ii' - en lC iil :::r - < ~
o Cl>-en:::r()"O OllC !!l. ~
o Um"OCl>Cl>Ol ~Cl> 0
~ :1,~~rJI=~~::: ~
-u ~ gJ, iii' cE rJI cO' ~
~ goQa:: fJ) ~::
5- -u ~ lJl lC ~3'
lC~Cl> po Cl>
Gl ~ ~ m g
Q) -<5 -0) -..0 ,...
iil Gl 2. !:,
~ ~ ~ ~
~ ~ gJ
Cl> 3' -
-u
C
~
o
:::r
-u
:::r
Ol
rJI
Cl>
=
8
~
~
C
U
o'
~
()
Ol
1il
~
a.
~
o
Ol
'<
rJI
......
01 0
z
2-
0'
Cl>
8'
-u
s: a
o 0
c: ~
N'
!!l.
0'
~
..
o
-u
:::r
Ol
rJI
Cl>
()
o
~
rJI
2"
U
0'
~
.
-
.
.0
.
.
I
I
I
I
I
()
o
~
o
~ a;
2_CD
U ~
Il ~ ~ i
a g C"
!!?3c ~.
lC a. 3 0
-3:-Cl>-Cl>-r-~
=.oa,Dl (f)
. lCCen~
-u -u :::r '6' cO' g.
Ol~""3~0
~,,"~Cl> Ol
()21 ~ al
~ g ~
"0 :::r ~
1il cO'
ar ~
5'
~
@
-u
~,
3
Ol
<
Cl>
iil
en
'<
rJI
CD
3
.rJI
~
!"'
-nen
::i Q)
(ii' ;:::l.
:::rOo
o.Ol
Ol -
_Cl>
Cl>
00
"-.J0l
00
f!!~
......0
oeo
-u -u en -u ~ r -u
Q) ~ ca" ,<or Q ~ ~
~ ';tt::"::reo c: Co"
()-U-'a3~en
~5<OC(bQ)2
-og.ga3.-gu
1il lC en po C
ar Z rEi' CD
C ::J :f en
'6' cO'
3 !!l.
Cl> 5'
~ ~
..01111
-nen-uen()-um
~:gg3a:S~
:::r3(il3~(il~
~~~~ C"~ Ol
; 6- "8__ ~ ~ g-
o ::J :J ~ ...,
~ Cl> -
Cl>"O
"0 0
Q,5'
~-
~ -l. tv W ~
o 01 0 01 0001
I
CD
...,
;:+
tIl
(Q-j
CD:;r
"'UCD
~I
7'tIl
tIl en
:::J7'
a.~
"'UO
tile
~3
:::J"O
(QtIl
G>~
tIl
...,
tIl
(Q
CD
I
PRICE
I
~~ ~!s!~!~a!:'
.
BID FORM
PROJECT NAME: SUNNY ISLES HERITAGE PARK AND PARKING GARAGE
BID TO: CITY OF SUNNY ISLES BEACH
19250 Collins Ave
Sunny Isles Beach, FL 33160
BID FROM: Haskell
Attn: Don Kartzmark
111 Riverside Ave
Jacksonville, FL 32082
(904) 357-4882
Pursuant to and in compliance with the Instructions to Bidders, the undersigned,
hereinafter called the "Bidder", having visited the site of the proposed Project and having
become familiar with the local conditions, nature and extent of the work and having
carefully examined the Drawings and Project Manual prepared by Spillis Candela,
DMJM, hereby offers to furnish all labor, materials, supplies, equipment, and other items,
facilities, and services necessary or proper for or incidental to complete Bid items within
the times indicated Section 1 of this proposal and as required by and in strict accordance
with all the requirements and provisions listed in the Agreement.
In submitting this Bid, Bidder agrees that he is familiar with federal, state, and locallas
and regulations. The Bidder understands that the right is reserved by the Owner to
reject or accept any or all of the Bid Alternates, If Bidder is notified of the acceptance of
this Bid within sixty (60) days after the opening thereof, the undersigned agrees to
execute and deliver an Agreement and furnish the required performance and payment
bonds for not less than 100% of the total contract sum, and furnish required evidence of
the specified insurance requirements within (7) days after the Agreement is presented to
him for signature. The Surety providing the Payment and Performance Bond shall be
rate "A" or better by the most recent issue of "Best" rating service, and the surety must
be acceptable to the Owner,
ADDENDA
Bidder agrees he has received the following Addenda receipt of which is hereby
acknowledged:
Date:
Number:
5/15/09
Addendum #1
~~ ~!s!~!~a!:'
.
LUMP SUM PRICING
Recommended Phase 1 Price - Parking Garage & Entry Driveway:
~'}( mILt.. IO~ ':\v~ ~\.IAJ~"t) 'p...>1r'>17Y IVINt!. r"'llO\J :s/IhVD
Lump Sum Bid <5EJ.JrAf1'Fe:JJ fHV D ~ $ to,529, 017. OD
Bidder agrees to complete Item number 1 work 270 calendar days from notice to
proceed.
*Recommended price includes alternates (recommended) by Haskell in Section 4.
Base Pricing:
Item Number 1: Phase 1 Price - Parking Garage and Entry Driveway: cc:2
StX MtL~IAO>N NW(;, J..htNPteP ~ FtvfC -r<#l/)u~~ ~
Lump Sum Bid $ f.LJ, Cf75"; OtJO. 00
Bidder agrees to complete Item number 1 work 270 calendar days from notice to
proceed.
Item Number 2: Phase 2 Price - Heritage Park:
Lump Sum BidIWo 1"'l1f..,U O~ ~ elJaf /4s4A.Jf;>1'bfJ> '"V(o~tf7U)::> .!f;;n
$ 2, 7tJ6J,tJtJO ~ eo
Item Number 3: Phase 1 and Phase 2 - Park and Parking Garage
)\)I~ W1/l.l.-&tl,v .s l)l. IWAI~ 5~A.JT'/ P:IUc:. Q
Lump Sum Bid ~I-V">,A.;.A-AJ t:. hJb o~ $ 1 J ~ 7 ~ ()oO. 00
"'~~
.
~~
HASKELLDAm~ricaB's.ld leader@
eSlgn- UI
Construction Cost Summary
Totals Cost/SF Cost/Space
General Requirements $ 512,519 $ 2,80 $ 1,035
Sitework $ 704,317 $ 3.84 $ 1 ,423
Concrete - Foundations $ 224,342 $ 1,22 $ 453
Concrete - Cast-in- Place (CIP) Structure $ 2,804,017 $ 15,31 $ 5,665
Concrete - Miscellaneous $ 34,383 $ 0,19 $ 69
Masonry $ 110,603 $ 0,60 $ 223
Miscellaneous Steel $ 452,162 $ 2.47 $ 913
Ornamental Metals $ 1,350 $ 0.01 $ 3
Carpentry $ 1,300 $ 0,01 $ 3
W aterproofinalT oooinas $ 24,267 $ 0,13 $ 49
CaulkinQ $ 10,373 $ 0.06 $ 21
RoofinQ & Sheetmetal $ 14,757 $ 0.08 $ 30
Doors & Windows $ 86,930 $ 0.47 $ 176
Finishes $ 277 ,589 $ 1.52 $ 561
Specialties $ 42,180 $ 0.23 $ 85
Equipment $ 16,160 $ 0.09 $ 33
Furnishinas $ - $ - $ -
Fire Protection $ 57,778 $ 0.32 $ 117
Convevina Systems $ 191,129 $ 1,04 $ 386
PlumbinQ $ 176,350 $ 0.96 $ 356
HVAC $ 72,921 $ 0.40 $ 147
Electrical $ 317,790 $ 1,73 $ 642
Construction Overhead/Fee $ 263,514 $ 1.44 $ 532
Construction Total $ 6,396,731 $ 34.92 $ 12,923
LUMP SUM
For
City of Sunny Isles Beach - Heritage Park and Parking Garage
RECOMMENDED PRICE - PHASE 1 PARKING GARAGE AND DRIVEWAY
GARAGE SF 183,200
NUMBER OF SPACES 495
NUMBER OF LEVELS 6 Ground plus Five Elevated
Soft Cost Summary
Description Totals
Permit Fee EXCLUDED $
Builders Risk ALLOWANCE $
Liability Insurance $
Payment & Performance Bond $
Sales Tax Savings Program Allowance $
Soft Cost Totall $
164,500
82,216
68,514
(100,000)
215,230 I
TOTAL $
6,611,961
Note: These prices may be adjusted on bid day, Please refer to the bid form for our actual bid number
.
~~ HASKELL~~r~~-i~ild Leader"
LUMP SUM
For
City of Sunny Isles Beach - Heritage Park and Parking Garage
BASE PRICE - PHASE 1 PARKING GARAGE AND DRIVEWAY
GARAGE SF 183,200
NUMBER OF SPACES 495
NUMBER OF LEVELS 6 Ground plus Five Elevated
Construction Cost Summary
Totals Cost/SF Cost/Space
General Requirements $ 512,519 $ 2,80 $ 1,035
Sitework $ 704,317 $ 3,84 $ 1,423
Concrete - Foundations $ 224.342 $ 1.22 $ 453
Concrete - Cast-in- Place (CIP) Structure $ 2,574.017 $ 14.05 $ 5,200
Concrete - Miscellaneous $ 34.383 $ 0.19 $ 69
Masonry $ 110,603 $ 0,60 $ 223
Miscellaneous Steel $ 747,162 $ 4.08 $ 1,509
Ornamental Metals $ 1.350 $ 0.01 $ 3
Carpentry $ 1.300 $ 0.01 $ 3
W aterproofinQ!T oppings $ 24,267 $ 0.13 $ 49
Caulkina $ 10,373 $ 0,06 $ 21
Roofinq & Sheetmetal $ 12,257 $ 0,07 $ 25
Doors & Windows $ 86,930 $ 0.47 $ 176
Finishes $ 667.231 $ 3.64 $ 1,348
Specialties $ 42.180 $ 0,23 $ 85
Equipment $ 16,160 $ 0.09 $ 33
Furnishinas $ - $ - $ -
Fire Protection $ 57,778 $ 0.32 $ 117
Convevina Systems $ 191,129 $ 1.04 $ 386
Plumbinq $ 176,350 $ 0.96 $ 356
HVAC $ 72,921 $ 0.40 $ 147
Electrical $ 311,581 $ 1.70 $ 629
Construction Overhead/Fee $ 263,166 $ 1,44 $ 532
Construction Total $ 6,842,316 $ 37.35 $ 13,823
Soft Cost Summary
Description Totals
Permit Fee EXCLUDED $
Builders Risk ALLOWANCE $
Liability Insurance $
Payment & Performance Bond $
Sales Tax Savings Program Allowance $
Soft Cost Totall $
164,500
82,108
68,423
(100,000)
215,031 I
TOTAL $
7,057,347
Note: These prices may be adjusted on bid day. Please refer to the bid form for our actual bid number
$ HASKELL~~f~~-~~i'd Leader@
LUMP SUM
For
City of Sunny Isles Beach - Heritage Park and Parking Garage
HERITAGE PARK
Park SF
88,031
Construction Cost Summary
Totals Cost/SF
General Requirements $213,260 $ 2.42
Site Electric $ 383,800 $ 4.36
PavinQ and Hardscape $ 1,048,256 $ 11.91
Landscape and IrriQation $ 251,391 $ 2.86
Site Furnishings $ 754,725 $ 8.57
Construction Overhead/Fee $ 97,527 $ 1.11
Construction Total $ 2,748,958 $ 31.23
Soft Cost Summary
Description Totals
Permit Fee EXCLUDED $
Builders Risk ALLOW ANCE In Garage
Liability Insurance $ 32,988
Payment & Performance Bond $ 16,494
Sales Tax Savings Program Allowance $ (40,000)
Soft Cost Totall $ 9,481 I
TOTAL $
2,758,440
Note: These prices may be adjusted on bid day. Please refer to the bid form for our actual bid number
..
~ HASKELLAmerica'S leader@
Design-Build
UNIT PRICES
For
City of Sunny Isles Beach - Heritage Park and Parking Garage
5/22/2009
Item Units of Units of
No. DesiQnation Measure ~
No.1: Canopy Trees
1 a, Bambusa textilis Each $ 201,96
1 b, Bursera simaruba Each $ 104,00
1 c, Bursera simuraba Each $ 138,67
1 d, Coccoloba uvifera Each $ 86.67
1 e. Delonix regia Each $ 173,34
1 f, Ficus aurea Each $ 69,34
1 g, Lysiloma sabicu Each $ 98.23
1 h, Nolina recurvata Each $ 1,733.40
No.2: Accent Trees
2a, Conocarpus erectus 'sericeus' Each $ 98,23
2b, Guaicum officinale Each $ 260,01
2c. Pandanus utilis Each $ 86,67
2d, Senna polyphylla Each $ 98.23
No.3: Palms
3a, Bismarckia nobilis Each $ 635,58
3b, Cocos nucifera 'Green Malayan; Each $ 1,109.36
3c. Cocos nucifera 'Green Malayan' Each $ 2,223,37
3d, Cocos nucifera 'Green Malayan' Each $ 2,184,08
3e, Ptychosperma elegans Each $ 1,090,04
3f, Sabal Palmetto - 10' CT Each $ 109,78
3g, Sabal Palmetto - 15' CT Each $ 109.78
3h, Sabal Palmetto - 20' CT Each $ 109.78
3i. Sabal Palmetto - 25' CT Each $ 121 ,34
3j, Sabal Palmetto - 30' CT Each $ 132,89
3k, Thrinax radiate Each $ 288.90
~ HASKELL~~?~~~~~ild leader"
UNIT PRICES
For
City of Sunny Isles Beach - Heritage Park and Parking Garage
5/22/2009
Item
No.
Desianation
Units of
Measure
Units of
Price.
No.4: Shrubs
4a, Crinum Angustum
4b, Chrysobalanus icaco 'horizontal'
4c, Clusia guttifera
4d, Crinum asiaticum
4e, Hamelia patens 'Compacta'
4f. Monstera deliciosa
4g, Muhlenbergia capillaris
4h, Myrcianthes fragrans
4i. Nephrolepis falcata
4j, Psychotria nervosa
4k, Serenoa repens 'Silver'
41. Tripsacum dactyloides
4m, Solidago gigantea
Each $ 40.45
Each $ 8,09
Each $ 4,91
Each $ 23,11
Each $ 4.05
Each $ 4,62
Each $ 3,76
Each $ 4,08
Each $ 2,31
Each $ 4.08
Each $ 40.45
Each $ 3,76
Each $ 3,76
No.5:
Ground Covers
5a, Argusia gnahalodes
5b. Asclepias tuberosa
5c. Batis maritima
5d. Ernodea littoralis
5e. Ficus microcarpa 'Green Island'
5f, Flaveria linearis
59, Microsortum scolopendrium
5h, Paspalum vaginatum 'SeaDwarf Seashore'
5i. Philodendron 'Burle Marx'
5j. Stachytarpheta jamaicensis
5k, Zamia pumila
Each $ 23.11
Each $ 4,91
Each $ 4,91
Each $ 2.31
Each $ 4.08
Each $ 2,31
Each $ 2,89
Each $ 0.45
Each $ 7,52
Each $ 4.05
Each $ 12,71
~
HASKELLDAm~ricaBls.ld leader@
eSlgn- UI
UNIT PRICES
For
City of Sunny Isles Beach - Heritage Park and Parking Garage
5/22/2009
Item
No.
Desianation
Units of
Measure
Units of
Price
No.6: Vines
6a. Thunbergia grandiflora
Each $
8,09
No.7: Soils and Soil Amendments
7a, DIEHARD for Shrubs and Groundcovers
7b, DIEHARD for new Trees
7c, DIEHARD for new Palms
7d. DIEHARD for Relocated Palms
7e, Planting Soil Mix
7f, Mulch
7g, Tree removal
7h, Palm removal
7i. Palm Relocation
7j. Existing trees to remain Protection
7k, Aluminum landscape edging
71. Gravel path
Oz $ 0.23
Oz $ 0,23
Oz $ 0,23
Oz $ 0,23
CY $ 19.26
CY $ 37.45
Each $ 112.50
Each $ 112.50
Each $ 122,89
Each $ 253.37
LF $ 3,36
SF $ 0,98
No.8: Irrigation
8a. Unit price to include all components of Irrigation System
All
$ 45,900.00
No.9: Pavement
9a, Standard concrete SF $ 4.25
9b, Integral color concrete SF $ 16,00
9c. Concrete curbs LF $ 17,06
9d. NOT USED N/A
ge. Concrete pavers SF $ 9,79
1
~ HASKELL~~f~~~~i1d leader@
UNIT PRICES
For
City of Sunny Isles Beach - Heritage Park and Parking Garage
5/22/2009
Item
No. Desianation
9f, Engraved concrete pavers
9g, Stainless steel/Terrazzo marine life paving inserts
9h. Stone band and flagging at concrete edge paving
9i. Stone flagging path
9j, Stone curb/edging
9k, Exfiltration pits (in stone flagging)
91. Stone pebble
9m, Trap Sand (sand pits)
9n. Ipe (FCS certified wood)
90, Playground safety surface
9p, ADA detectable warning surface
Units of Units of
Measure Price
Each $ 22,00
Each $ 2,335,00
SF $ 22.10
SF $ 20.10
LF $ 5,00
Each $ 3,197.68
SF $ 0.37
CY $ 1,91
SF $ 34.57
SF $ 10.84
SF $ 23,09
No. 10: Stairs and Ramps
10a, Concrete stairs
10b, Stainless steel stair handrails
10c, stainless steel ramp handrails
SF $
Each $
Each $
48.73
70,00
70,00
No. 11: Walls
11 a. Stone veneer seat wall with overhang
11 b. Stone veneer walls & columns
11 c, Tile veneer walls
11d, Wall sign - Complete Wall
11 e, Concrete wall (at sand play area)
11f. Cut Iimerock boulder walls
11 g, Limerock boulders (+/- 3' x 3')
11 h, Limerock boulders (+/- 4' x 5')
SF $ 103.51
SF $ 96,61
SF $ 101.11
Each $ 43,376.52
SF $ 66,51
LF $ 68,61
Each $ 728,20
Each $ 256.08
1
A~ HASKELLAmericals
~ Design-Build leader'"
UNIT PRICES
For
City of Sunny Isles Beach - Heritage Park and Parking Garage
5/22/2009
Item Units of Units of
No. DesiQnation Measure Price
No. 12: Fencing
12a, 6 ft. high Picket Fence LF $ 45,00
12b, 8 ft. high Gates Each $ 875.00
12c, 10ft. high Gates at ramps Each $ 875.00
No. 13: Site Lighting. Unit price to include all components.
13a, Concrete wall recessed light
13b, Wall light (neon)
13c. Lighting pole
13d. Precast concrete recessed light (path lights & enclosures)
13e, Uplight fixture
13f, Shelter fixture
13g. Bollard
13h, Spotlight on boat mast (pole)
13i. Spotlight on boat mast (ground)
13j, Access road lighting poles
13k, Uplight tensile canopy
131. South area lighting poles
13m, Flagpole uplight
13n, Sundial uplight & precast sundial markers/light enclosures
130. Transformers
13p, Power Receptacles
13q, Code Blue "Pedestal"
13r. Code Blue "Wall mounted"
Each $ 149.43
Each $ 73.03
Each $ 3,889,56
Each $ 149.43
Each $ 196.43
Each $ 516,84
Each $ 859.47
Each $ 752.75
Each $ 954.97
Each $ 2,044,77
Each $ 849,36
Each $ 2,044,77
Each $ 626,91
Each $ 264,02
Each $ 544.89
Each $ 125.00
Each NIC
Each NIC
No. 14: Playground Equipment
14a, Unit price to include all components
All
$ 66,078,00
~
HA5KELLDAm~ricaBls.ld leader@
eSlgn- UI
UNIT PRICES
For
City of Sunny Isles Beach - Heritage Park and Parking Garage
5/22/2009
Item
No.
Desianation
Units of
Measure
Units of
Price
No. 15: Playground Shade Structure
15a. Unit price to include all components
All
$ 30,419,00
No. 16: Fossil Dig-Unit price
16a, Fossil structures
Each $ 1,578,73
No. 17: Sand Play Area (at Sail Structure)
17a, Amusement Nets
Each $ 11,773,00
No. 18: Sail Structure (sails, masts/structure, footings, cables, etc.)
18a. Unit price to include all components
All $ 411,676,00
No. 19: Site Furniture
19a. Cabana/Shelter Structures Each $ 15,713.00
19b, Precast Lugo Mare Bench Each $ 12,447,64
19c, Precast Slope Bench Each $ 5,401,37
19d. Precast Nigra Chair Each $ 2,042.89
1ge. Table with Umbrella Each $ 7,287.56
19f, Table Chairs Each $ 1,000,00
199, Picnic Tables and Benches Each $ 1,367.00
19h, Flag Poles Each $ 5,813,00
19i. Bike Racks Each $ 765,52
19j. Trash Receptacles Each $ 922,00
MOBILIZA liON PERIOD
~~ ~!s!~!~a!:'
,
MOBILIZATION
Haskell is ready to begin immediately, Upon notice to proceed, there will be three weeks
of mobilization for Phase I before demolition begins. This time will be used to finalize the
contracts with the site and demolition contractors. Also, we will use this time to set up
our construction trailer, establish control and bench marks, install storm water control
devices, and secure the site perimeter,
PROJECT ApPROACH & ALTERNATIVES
..
~~ !!!S!~!d~a!:'
PROJECT APPROACH AND ALTERNATIVES
Haskell will approach the project will be to team with you and Spillis Candella to deliver
the best possible job, done right the first time, and at a good price. It all starts in this
price proposal with bids from Subcontractors we know feel the same way. One poor
performing Subcontractor can drag down your entire project and Haskell is committed to
making sure that does not happen.
Therefore, included in our price proposal, are Subcontractor bids from truly qualified
companies you can trust. By using only qualified firms, your cost in the long run will
always be much better since quality, safety and overall value will not be compromised.
Our approach to building the project follows the same general organization as the project
schedule in section 1. Upon mobilization, Haskell will erect a jobsite fence and secure
only enough of the site to construct the building, This will allow you to retain possession
of more than half of the existing parking lot.
We will demolish the paved areas under the garage, install the augercast piling, and
proceed with the structure. Once the structure is up, the exterior architectural
treatments, including the tilt-up concrete Big V's, and the interior building including the
new public works office will be completed,
The garage will be completed and you will be parking cars by March 2010.
Once the garage is complete, and public works has relocated into its new offices,
Haskell will complete the park area,
ALTERNATIVES:
All alternatives are deducts (or adds) to the BASE price.
1, Big V's in Tilt-up Concrete (recommended) - Haskell proposes to construct
the Big V system on the exterior of the building in site cast, tilt-up concrete
panels, The panels will be 2' thick in lieu of the 3' thick shown on the plans,
All other shapes, angles and dimensions remain the same. The concrete will
be coated with Tex-Coat to achieve a finished look comparable to stucco.
The advantages are numerous including MUCH greater durability and
virtually zero maintenance. Deduct $202,000
2. Holeless, Machine Room less Elevator (recommended) - Haskell proposes
to furnish and install a machine room less, traction elevator. This will
eliminate the need for the pre-drilled shaft hole, hydraulic pump and elevator
machinery in the machine room, All that remains outside the shaft is the
control panel, which can be located in a much smaller room. In addition,
motor size is reduced from 40 HP to 6.6 HP. The cost of the two systems is
the same, however your savings come in reduced energy cost and lower
maintenance.
~~ !!!s!~!~!:'
3, Change Stairs from Steel to Concrete (recommended) - Haskell proposed
to change the metal stairs to cast in place concrete. This will be more
durable and corrosion resistant. Deduct $15,000
4, Redesign Route of Entry Road -If selected, Haskell will complete the
design work necessary to re-route the garage entry road to the west at no
additional charQe,
5. Delete Vine Trainer System - (not recommended) Deduct $110,000
6. Delete Fiberglass Mesh and Support (recommended) - Haskell
recommends deleting the fiberglass mesh and allowing us to work with you
and Spillis Candela to select a more cost effective solution. We suggest, and
our deduct includes, a $100,000 allowance for a new system. Deduct
$250,000
7. Smooth Stucco Finish for Exterior of Stair Towers (recommended)-
Haskell recommends adding a stucco finish to the CMU facing the exterior of
the building at the stair towers. This will significantly improve their
appearance from the street. Add $75,000
8. Eliminate Paint in stairwells (recommended) - This is most often not done
in parking garage projects, The advantage is obviously saving the initial cost,
but also reduces maintenance. Deduct $7,400
9. Eliminate TexCoat on Structure (recommended) - Since the structure will
be hidden behind the vines, Big V's and mesh, this seems unnecessary and
adds maintenance cost. Deduct $55,242
10. Metal Cladding to Big V's (not recommended) - ADD $750,000 for 3-sides,
Add $975,000 for all four sides.
Note: Haskell examined the option of converting the garage to pre-cast concrete;
however there was an increase in cost. Therefore, we are not suggesting a change in
the structural system,
CLARIFICATIONS:
1. All prices are firm, fixed, lump sum prices,
2, We do not include the cost resulting from any unforeseen underground
obstructions or conditions,
3. Our recommended price includes all the alternates above indicated to be
(recommended).
4. All demo carried in Phase 1 price
5. We do not include asbestos abatement or hazardous material of any kind,
6. We have included 100' deep drainage wells, Additional depth if required will be
an add of $300/LF
7. Phase 1 price does not include landscaping or irrigation of any kind
.
...
~~ !!!s!!!~a~'
8, All landscaping included in phase 2
9. All power and lighting shown on sheet E1,1.00 is included in the Phase 2 (Park)
price,
10. We include an allowance of $165,400 for Builder's Risk Insurance,
11, We include an allowance for Sales Tax Savings of $100,000 for Phase 1 and
$40,000 for Phase 2.
12. For Augercast Piling, for piles longer than bid length, add $25.00/LF
13, For Augercast Piling, for piles shorter than bid length, deduct $6.00
14. For Augercast Piling, add $1 O.OO/CF for grout in excess of 1.5x theoretical
volume, including returned trucks,
15. Furnishings and appliances by Owner
16. We do not include tension or lateral load tests for Augercast Piles
17. All above ground copper to be type ilL" in lieu of type ilK"
18. Telephone and data are not included
19, We do not include building permit fees in our price
20. We do not include the cost of a threshold inspector
21, We do not include the relocation of unidentified underground utilities
22, We do not include items not shown on the plans or called for in the project
manual
23, Code blue units are by others as indicated on the Drawings
l.-
II:lI
I
BASE PARK OPTION
I
...
. ,J
_.#r
~
_l .
.
~~ ~!!~B!~a!:'
BASE PARK OPTION
Haskell will approach the base park option assuming the Park portion will be the fence
around the perimeter, an irrigation system and sod covering the entire open area. We
are not including the driveway in this option because the driveway will not change
regardless of which Park option is chosen. The cost of the driveway remains in Phase 1
- Parking Garage pricing.
The sod included is the specified Sea Dwarf Seashore. The fence has been revised to
include two (2) gates each at 8 feet. The irrigation design has been revised based on
the new landscaping approach.
Base Park Option I
I
General Conditions 1 LS $ - $ 50,000
Asphalt Pavina 1 LS $ - $ -
6" Concrete Curb 1 LS $ - $ -
Sod only at Park - SeaDwarf Seashore
Sod 1 LS $ 43,700,00 $ 43,700
Irriaation for Base Park 1 LS $ 15,000,00 $ 15,000
Aluminum 6' Picket Fence Welded 920 LF $ 45,00 $ 41 ,400
Aluminum Gate Pair (2) x 4'-0" = 8'-0" 2 EA $ 875,00 $ 1,750
Aluminum Gate Pair (2) x 5'-0" = 10'-0" 2 EA $ 875.00 $ 1,750
$
Dailv Cleanup Crew -2 WK $ 500,00 (1,000)
$
Dumpsters -1 EA $ 350.00 (350)
SUB TOTAL $ 152,250
FEE $ 5,000
SUBTOTAL $ 157,250
PERMIT FEE $
BUILDERS RISK
ALLOWANCE $ 1,600
LIABILITY
INSURANCE $ 1,200
P & P BOND $ 600
GRAND TOTAL I $ 160.650 I