HomeMy WebLinkAboutReso 2012-1927RESOLUTION NO. 2012 - Jq2nrl
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
SUNNY ISLES BEACH, FLORIDA, APPROVING CHANGE ORDER
NUMBERS 1, 2, 3, AND 4 TO AGREEMENT WITH SHORELINE
FOUNDATION, INC. FOR THE NEWPORT FISHING PIER
DEMOLITION AND CONSTRUCTION PROJECT, DECREASING
THE AGREEMENT BY EIGHT HUNDRED EIGHTEEN THOUSAND
ONE HUNDRED FIFTY -EIGHT DOLLARS AND SEVENTY -NINE
CENTS ($818,158.79), ATTACHED HERETO AS EXHIBIT "A ";
AUTHORIZING THE CITY MANAGER TO DO ALL THINGS
NECESSARY TO EFFECTUATE THIS RESOLUION; PROVIDING
FOR AN EFFECTIVE DATE.
WHEREAS, on September 16, 2010 via Resolution No. 2010 -1605, the City Commission
approved an Agreement with Shoreline Foundation, Inc. to provide professional construction
services for the demolition and construction of the Historic Sunny Isles Beach/Newport Fishing Pier
at Pier Park, in an amount not to exceed Three Million Seven Hundred Seventy -Seven Thousand
Eight Hundred Sixty -Six Dollars ($3,777,866.00); and
WHEREAS, the City has a sales tax incentive program in place which allows the City to
recognize additional savings after a construction project has been awarded to a contractor, and
WHEREAS, the savings are recognized when the City purchases materials directly from the
subcontractor on behalf of the contractor for the benefit of the public project, the City is exempt from
paying sales tax, where the contractor is not, and the authority to make these purchases is under the
master contract; and
WHEREAS, as a result of these direct purchases, the City has prepared Change Order
Numbers 1— 4 recognizing the decrease in the direct contractual obligation to the vendor as follows:
Change Order No. 1 decrease of $250,000.00, Change Order No. 2 decrease of $408,474.00, Change
Order No. 3 decrease of $42,789.20, and Change Order No. 4 decrease of $116,895.19, for a total
decrease amount of Eight Hundred Eighteen Thousand One Hundred Fifty -Eight Dollars and
Seventy -Nine Cents ($818,158.79), the City will recognize a savings on these change orders of Forty
Thousand Five Hundred Fifty -Seven Dollars and Ninety -Two Cents ($40,557.92); and
WHEREAS, the City wishes to approve Change Order Numbers 1 -4 with Shoreline
Foundation, Inc., decreasing the Agreement amount by Eight Hundred Eighteen Thousand One
Hundred Fifty -Eight Dollars and Seventy -Nine Cents ($818,158.79), attached hereto as Exhibit "A ",
for a total Agreement amount not to exceed of Two Million Nine Hundred Fifty -Nine Thousand
Seven Hundred Seven Dollars and Twenty -One Cents ($2,959,707.21).
NOW THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF SUNNY ISLES BEACH, FLORIDA, AS FOLLOWS:
82012 - Shoreline CO 1-4 Pier Pagelof2
Section 1. Approval of Change Order Nos. 1 -4. The City Commission hereby approves Change
Order Numbers 1, 2, 3, and 4, decreasing the Contract with Shoreline Foundation, Inc. by Eight
Hundred Eighteen Thousand One Hundred Fifty -Eight Dollars and Seventy -Nine Cents
($818,158.79), attached hereto as Exhibit "A ", for a total Agreement amount not to exceed Two
Million Nine Hundred Fifty -Nine Thousand Seven Hundred Seven Dollars and Twenty -One Cents
($2,959,707.21).
Section 2. Authorization of City Manager. The City Manager is hereby authorized to do all
things necessary to effectuate this Resolution.
Section 3. Effective Date. This Resolution will become effective upon adoption.
PASSED AND ADOPTED this 21" day of June 2012.
ATTEST:
c
Jane,A. Hines, CMC, City Clerk
Vote: S_ 0
Mayor Edelcup
Vice Mayor Thaler
Commissioner Aelion
Commissioner Gatto
Commissioner Scholl
(Yes)
_V(Yes)
__(Yes)
Yes)
(Yes)
82012- Shoreline CO 1 -4 Pier Page 2 of 2
Moved by: �ACe inAUUr�I- i14L4Y?
Seconded by: SC.µOLL_
_(No)
_(No)
(No)
(No)
_(No)
[4 r.Wre X$ : 1
No.1
PROJECT: Newport Fishing Pier Demolition & Construction
DATE OF ISSUANCE: 3/1112 EFFECTIVE DATE: 3/1/12
OWNER: City of Sunny Isles Beach
OWNER CONTRACT NO.: 10 -07 -02
CONTRACTOR: Shoreline Foundation, Inc
ENGINEER CONTRACT NO.: 11 -4239
ENGINEER: Calvin, Giordano & Associates, Inc.
You are directed to make the following changes in the Contract Documents
Description: City to direct purchase items outlined in PO #11- 0001187 -100 - Coreslab
Reason for Change Order: To obtain tax saving credit
Attachments: SIB PO # 11- 0001187 -100
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price
Original Contract Times
$3,777,866.00
Substantial Completion: 330 calendar days
Ready for final payment: 360 calendar days
days or dates
Net changes from previous Change Orders No. -0- No. -0-
Net change from previous Change Orders No. -0- No. -0-
$ 0.00
0
days
Contract Price prior to this Change Order
Contract Times prior to this Change Order
Substantial Completion: 330 calendar days
$3,777,866.00
Ready for final payment: 360 calendar days
days or dates
Net increase of this Change Order
Net Increase of this Change Order
$(250,000.00)
0
days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
Substantial Completion: 330 calendar days
$3,527,866.00
Ready for final payment: 360 calendar days
ays or dates
:�xKi]uluL�� � � t1 »:Zi�ggrr
By: By: L5E --y By:
Joel Wadsworth Alan Co en j -J(? 1i 1j
Calvin, Giordano & Associates, Inc. City of Sunny Isles Be , �9 �� reline F undatippn, Inc. �, P
Date: Date: ate: j iz z I
CHANGE ORDER
r. r,
PROJECT: Newport Fishing Pier Demolition & Construction
DATE OF ISSUANCE: 3/1/12 EFFECTIVE DATE: 3/1/12
OWNER: City of Sunny Isles Beach
OWNER CONTRACT NO.: 10 -07 -02
CONTRACTOR: Shoreline Foundation, Inc
ENGINEER CONTRACT NO.: 11 -4239
ENGINEER: Calvin, Giordano & Associates; Inc.
You are directed to make the following changes in the Contract Documents
Description: City to direct purchase items outlined in PO #11- 0001186 -001 — Florida Rock & Sand -Piles
Reason for Change Order: To obtain tax saving credit
Attachments: SIB PO # 11- 0001186 -001
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price
Original Contract Times
$3,777,866.00
Substantial Completion: 330 calendar days
Ready for final payment: 360 calendar days
days or dates
Net changes from previous Change Orders No. -0- No. -1-
Net change from previous Change Orders No. -0- No. -0-
$ (250,000.00)
0
days
Contract Price prior to this Change Order
Contract Times prior to this Change Order
Substantial Completion: 330 calendar days
$3,527,866.00
Ready for final payment: 360 calendar days
days or dates
Net increase of this Change Order
Net Increase of this Change Order
$(408,474.40)
0
days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
Substantial Completion: 330 calendar days
$3,119,391.60
Ready for final payment: 360 calendar days
days or dates
RECOMMENDED:
APPROVED
By: By: X v /
Joel Wadsworth Alan C99heR
Calvin, Giordano & Associates, Inc. City of Sunny Isles Be�Ql7� /
Date: Date: 6� / �%
CHANGE ORDER
No.3
PROJECT: Newport Fishing Pier Demolition & Construction
DATE OF ISSUANCE: 3/1/12 EFFECTIVE DATE: 3/1/12
OWNER: City of Sunny Isles Beach
OWNER CONTRACT NO.: 10 -07 -02
CONTRACTOR: Shoreline Foundation, Inc
ENGINEER CONTRACT NO.: 11 -4239
ENGINEER: Calvin, Giordano & Associates, Inc.
You are directed to make the following changes in the Contract Documents
Description: City to direct purchase items outlined in PO #11- 0001185- 001 -G. Proulx, LLC - Reber
Reason for Change Order: To obtain tax saving credit
Attachments: SIB PO # 11- 0001185 -001
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price ..
Original Contract Times
$3,777,866.00
Substantial Completion: 330 calendar days
Ready for final payment: 360 calendar days
days or dates -
Net changes from previous Change Orders No. -0- No. -2-
Net change from previous Change Orders No. -0- No. -0-
$ (658.474.40)
0
days
Contract Price prior to this Change Order
Contract Times prior to this Change Order
Substantial Completion: 330 calendar days
$3,119,391.60
Ready for final payment: 360 calendar days
days or dates
Net increase of this Change Order
Net Increase of this Change Order
$(42,789.20)
0
days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
Substantial Completion: 330 calendardays
$3,076,602.40
Ready for final payment: 360 calendar days
days or dates
RECOMMENDED: APPRQ\T2D
By: By: 1
Joel Wadsworth - A an Cohen
Calvin, Giordano & Associates, Inc. City of Sunny Isles Bea
Date: Dale:
CHANGE ORDER
No.4
PROJECT: Newport Fishing Pier Demolition & Construction
DATE OF ISSUANCE: 3/1/12 EFFECTIVE DATE: 3/1/12
OWNER: City of Sunny Isles Beach
OWNER CONTRACT NO.: 10 -07 -02
CONTRACTOR: Shoreline Foundation, Inc
ENGINEER CONTRACT NO.: 11 -4239
ENGINEER: Calvin, Giordano & Associates, Inc.
You are directed to make the following changes in the Contract Documents
Description: City to direct purchase items outlined in PO #11- 0001184- 001 - Saffron- Railing
Reason for Change Order: To obtain tax saving credit
Attachments: SIB PO # 11- 0001184 -001
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price
Original Contract Times
$3,777,866.00
Substantial Completion: 330 calendar days
Ready for final payment: 360 calendar days
days or dates
Net changes from previous Change Orders No. -0- No. -3-
Net change from previous Change Orders No. -0- No. -0-
$ (701.263.60)
0
days
Contract Price prior to this Change Order
Contract Times prior to this Change Order
Substantial Completion: 330 calendar days
$3,076,602.40
Ready for final payment: 360 calendar days
days or dates
Net increase of this Change Order
Net Increase of this Change Order
$(116,895.19)
0
days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
Substantial Completion: 330 calendar days
$2,959,707.21
Ready for final payment: 360 calendar days
days or dates
RECOMMENDED:
Joel Wadsworth
Calvin, Giordano & Associates, Inc.
Date:
A P VED:
By: By:
Ian Cohen
City of Sunny Is es Bea
Date:
86akeo vOl,� Il�1eC
Inc. Cv � J
'r* or sWd F'
TO:
FROM:
DATE:
RE:
City of Sunny Isles Beach
18070 Collins Avenue
Sunny Isles Beach, Florida 33160
(305) 947 -0606 City Hall
(305) 949,3113 Fax
MEMORANDUM
The Honorable Mayor and City Commission
Alan J. Cohen, City Manager
6/21/2012
Shoreline Foundation, Inc Construction Change Order #1 through #5 for
the Newport Pier Project.
RECOMMENDATION:
Staff is recommending Commission approve the attached resolution.
REASONS:
Due to time constraints, the City instructed Shoreline Foundation, Inc. to start
construction prior to obtaining all permits. As a result of delays in receiving the permits,
the project was halted, and Shoreline demobilized. Upon obtaining the necessary permits
to resume work, Shoreline remobilized to continue the project. The remobilization costs
were not considered in the original contract and is resulting in a $37,605 change order.
The City has a sales tax incentive program in place which allows the City to recognize
additional savings after a construction project has been awarded to a contractor. The
savings are recognized when the City purchases materials directly from the subcontractor
on behalf of the contractor for the benefit of the public project. The City is exempt from
paying sales tax, where the contractor is not. The authority to make these purchases is
under the master contract. As a result of these direct purchases, the City prepares a
deductive change order (for the gross amount) to recognize the decrease in the direct
contractual obligation to the vendor. Attached includes deductive change orders #14 for
a total of $818,158.79, the City will recognize a savings on these change orders for
$40,557.92.
FUNDING SOURCE:
Funding is available in account number 35- 600 -5670.
ail.