HomeMy WebLinkAboutReso 2012-1942RESOLUTION NO. 2012 - 9
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
SUNNY ISLES BEACH, FLORIDA, APPROVING CHANGE ORDER
NO.6 TO AGREEMENT WITH SHORELINE FOUNDATION, INC.
FOR THE NEWPORT FISHING PIER DEMOLITION AND
CONSTRUCTION PROJECT, INCREASING THE AGREEMENT BY
THIRTEEN THOUSAND TWO HUNDRED NINETY -EIGHT
DOLLARS AND FORTY -SIX CENTS ($13,298.46), FOR THE
INSTALLION OF EIGHT (8) 18" ROUND AUGER CAST PILES,
AND INCREASING THE CONTRACT TIME BY FIFTEEN (15)
DAYS, ATTACHED HERETO AS EXHIBIT "A "; AUTHORIZING
THE CITY MANAGER TO DO ALL THINGS NECESSARY TO
EFFECTUATE THIS RESOLUTION; PROVIDING FOR AN
EFFECTIVE DATE.
WHEREAS, on September 16, 2010 via Resolution No. 2010 -1605, the City Commission
approved an Agreement with Shoreline Foundation, Inc. to provide professional construction
services for the demolition and construction of the Historic Sunny Isles Beach/Newport Fishing Pier
at Pier Park, in an amount not to exceed Three Million Seven Hundred Seventy -Seven Thousand
Eight Hundred Sixty -Six Dollars ($3,777,866.00); and
WHEREAS, on June 21, 2012 via Resolution No. 2012 -1927 the City Commission approved
Change Order Numbers 1 -4 with Shoreline Foundation, Inc., decreasing the Agreement amount by
Eight Hundred Eighteen Thousand One Hundred Fifty -Eight Dollars and Seventy -Nine Cents
($818,158.79), bringing the total Agreement amount not to exceed to Two Million Nine Hundred
Fifty -Nine Thousand Seven Hundred Seven Dollars and Twenty -One Cents ($2,959,707.21); and
WHEREAS, on June 21, 2012 via Resolution No. 2012 -1928 the City Commission approved
Change Order No. 5 with Shoreline Foundation, Inc., increasing the Agreement in an amount not to
exceed Thirty-Seven Thousand Six Hundred Five Dollars ($37,605.00), bringing the total amount
not to exceed to Two Million Nine Hundred Ninety -Seven Thousand Three Hundred Twelve Dollars
and Twenty -One Cents ($2,997,312.21).
WHEREAS, the original contract plans for the approach slab to the restaurant building
called for six (6) 24" x 24" precast piles at a cost of $43,795.64, to be driven via diesel hammer and
would require temporary encroachment onto LaPerla property and would have the potential for
cracking/spalling of the deck/structure due to vibrations; and
WHEREAS, the revised plan relocates the piles, reduces their size and utilizes in installation
methodology which reduces vibrations, and due to the smaller size of these piles, the number of piles
required to support the structure is increased from six (6) to eight (8); and
WHEREAS, the change order for installing eight (8) 18" round auger cast piles was not
considered in the original contract and is resulting in Change Order No. 6 increasing the Agreement
in an amount not to exceed Thirteen Thousand Two Hundred Ninety -Eight Dollars and Forty -Six
Cents ($13,298.46), and increasing the contract time by fifteen (15) days; and
82012- Shoreline CO 6 Pier Page I of 2
WHEREAS, the City wishes to approve Change Order No. 6 with Shoreline Foundation,
Inc., increasing the Agreement in an amount not to exceed Thirteen Thousand Two Hundred Ninety-
Eight Dollars and Forty -Six Cents ($13,298.46); attached hereto as Exhibit "A ", bringing the total
amount not to exceed to Three Million Ten Thousand Six Hundred Ten Dollars and Sixty -Seven
Cents ($3,010,610.67).
NOW THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF SUNNY ISLES BEACH, FLORIDA, AS FOLLOWS:
Section 1. Approval of Change Order No. 6. The City Commission hereby approves Change
Order No. 6 to the Agreement with Shoreline Foundation, Inc., in an amount not to exceed Thirteen
Thousand Two Hundred Ninety -Eight Dollars and Forty -Six Cents ($13,298.46), and increasing the
contract time by fifteen (15) days, attached hereto as Exhibit "A ", bringing the total amount not to
exceed to Three Million Ten Thousand Six Hundred Ten Dollars and Sixty -Seven Cents
($3,010,610.67).
Section 2. Authorization of City Manager. The City Manager is hereby authorized to do all
things necessary to effectuate this Resolution.
Section 3. Effective Date. This Resolution will become effective upon adoption.
PASSED AND ADOPTED this 19`h day of July 2012.
ATTEST:
Jane A. Hines, CMC, City Clerk
APPROVED AS TO FORM
AND hEGIV.,,,SUFFICIENCY:
City Attorney
t
SC�{OLI,
79"'6t,
Moved by: r
Seconded by: �1cQ V y ` 41�t.�1(Z
Vote: S� O
Mayor Edelcup
_(Yes)
(No)
Vice Mayor Thaler
/(Yes)
(No)
Commissioner Aelion
✓(Yes)
(No)
Commissioner Gatto
(Yes)
(No)
Commissioner Scholl
,/(Yes)
(No)
82012- Shoreline CO 6 Pier
Page 2 of 2
DATE OF 155UAPdCa: / /'I U'I L r-rr Gli I I V C Lim 1 G. 11 141 1 G
OWNER: City of Sunny Isles Beach
OWNER CONTRACT NO.: 10 -07 -02
CONTRACTOR: Shoreline Foundation, Inc
ENGINEER CONTRACT NO.: 11 -4239
ENGINEER: Calvin, Giordano & Associates, Inc.
You are directed to make the following changes in the Contract Documents
Description: F &I eight (8) Augercast piles per plan revisions - Remove six (6) Driven piles CO is result of net difference
Reason for Change Order: Plan Revisions
attachments: CGA Memo Dated 7!2112 incl Attachment "A" &
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price
Original Contract Times
$3,777.866.00
Substantial Completion: 330 calendar days
Ready for final payment; 360 calendar days
days or dates
Net changes from previous Change Orders No. -0- No. -5-
Net change from previous Change Orders No. -0- No. -5-
$ 1780.553.791
0
days
Contract Price prior to this Change Order
Contract Times prior to this Change Order
Substantial Completion: 330 calendar days
$2:997.312.21
Ready for final payment: 360 calendar days
days or dates
Net increase of this Change Order
Net Increase of this Change Order
$13.298.46
15
days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
Substantial Completion: 345 calendar days
$3:010,610.67
Ready for final payment: 375 calendar days
days or dates
RECOMMENDED:
By:
Joel Wadsworth
Calvin. Giordano & Associates. Inc.
Date:
APPROVED: ACCEPTED:
By: By
ec io
City of Sunny Isles Beach /Date: foreline Foundation, Inc.
Date: `°f
G�.,.iod- anoeE6t�s,.�j
E% E P,T I! N AL S;O L ll T 1 O N
g�lj1
Furt Eauder4ale Office 1800 Ellet Drive, Suite 600, Fort I.auderdale, Florida 33316
P11- :154 -.. - 1:7791 r 'VAX,•9502 -r
Memorandum 8( i
T Pa1gi Beach Office : 560 Village Blvd, Sulto 340, West Patin Beachl Florida:33409 .
Pho0g,.561184.61gI. • rhx:561.PO4.6300
j
017 2112
,
TIO: Chief Maas, Acting City Manager
1
r 0M: ChrisiGiordano.. Project Manager
_.._.- ........:1......_.a ...i
81 MJI CT: ; Status/Progress Update
i P�,OJuCT. Newport Fishing Pier
C: Sheila Marquez' Executive Assistant to the City Manager
Mans Ottinot, City Attorney
Minal Shah, Assitant City Manager /Finance Division
Dennis Giordano, President
Joel Wadsworth, Project Manager
Chief Maas:
Per Mr. Ottinot's email dated July 2, 2012, please find below a report regarding the attached
change order which I discussed with Mr. Ottinot last week:
Reasons the modification from the original contract work was required:
The original contract plans for the approach slab to the restaurant building called for six (6)-
24" x 24" precast piles to be driven via diesel hammer. The location of these piles is shown
in the diagram below; please note the proximity to the existing condo pool and deck:
1\CGAFSONPROJECTAPROJECTSi201 11114239 NEWPORT FIS14ING P1ER\CONSTRUCTION \CORRCSPONDENCc\MFMO 20120702 AUGERCAST
PILE CO, DOC
As you can see from the diagram above, the location and area of the 24" x 24" precast driven
piles would require temporary encroachment onto La Perla property and would have the
potential for cracking /spalling of the deck /structure due to vibrations. The revised plan, as
shown below, relocates the piles, reduces their size and utilizes an installation methodology
which reduces vibrations. Due to the smaller size of these piles, the number of piles required
to support the structure is increased from six (6) to eight (8).
Deductive Change Order (Credit) for not installing six (6) -24" x 24" Precast Driven
Piles:
The originally contracted 24" x 24" precast driven piles have an established rate per LF as
shown in the contract documents. The breakdown of these costs is shown in Attachment "A"
and total to a credit to the contract of $43,795.64.
Additive Change Order (Increase) for installing eight (8) —18" round auger cast piles:
This scope of work was not originally contemplated in the original contract, thus there is no
set value contained in the contractual documents. Attachment "B" contains Shoreline
Foundation, Inc (SFI) breakdown of the change order request which totals, $57,094.10.
CGA staff has reviewed these change orders with City Staff and a determination was made
that the net increase of $13,298.46 is justified in order to minimize the potential impacts to
the adjacent existing structures while utilizing the same contractor /contract documents,
which ensures that the bonding and insurance is upheld and consistent throughout the project
and contractual warranty period.
\\CGAFS01 \PR01EC'hPROJECrS\2011\114239 NEWPORT FISHING PIER�CONSTRUCfION\CORRFSPONDENCE \MEMO 20120702 AUGERCAST
PILE CO.DOC
If you have any questions or would like to discuss this further, please do not hesitate to
contact me.
Project Manager
\\ CGAESI) 1\ PROJE .C'I' \PItOJEC'I'S\2011\114239 NEWPORT F[SHING PIER \CONSTRUCTION \CORRESPONDENCE \MEMO 20120702 AUGERCAST
PILE CO.DOC
ATTACHMENT "A"
uy
2781 SW 161" Avenue . Pembroke Paris, Florlde 33023
Phone: (954) 985.0460 • Fax: (954) 9£15-0402 . www ,sliorelinefotinClation.00trt
January 22,2012
JOEL WADSWORTH
Project Mtutager (B:roward)
Cnivin, Giordauo fie Associates, lne.
1900 Eller Drive, Suite 600
Trott Ltntdenialc, Florida 33316
Re: Sunny isles Bench /Newport Fishing PierPark- Proposal No, 10 -07 -02
Subject: Credit Fen• Six (06) - 24" Prestressed Concrete Piles for Bents R1, R la, R1 b & R2 tit Newport Pier Project.
Dear Mr. Wadsworth:
ShorclItic Foundation, [tic, is Pleased to provide our civ -diI as per our bid documents ror six (06) - 24" Prt:stressed Concrete Piles at Bents R 1, R I it,
Rib & R2 fit No%gjort Pier Project. The Totul Credit is $ 43,795,64, as describe below:
No,
ilems De eriplion
Unit
Q110111-ily
Unit Cost
Sub Total
I
Pile .Longthnt0ent.R1-- 4BAX43.00'
LF
86100
$142.00*
$12,212,00
2
Pile. Lcn th at Dent Rla - - -1 EA X 41.21' — -
LF
41.21
5.142,00
$5,851.82
3
P.ilar.Len th tit Bont Rlb - - -.I EA X41,21'
LF
41.21
$142 -00
$5,851,82
4
Pilo Length at Bent R2- - - -2EA X70',00' _
LF
140.00
$142..00
$19,A0.00
Sub `t'ohal
$43,795.64
(,Moral Conn-actor OVOICnd & Pro lit
_ lnehulcKl
Grand Total =
$tt3 "195,64
*Per SFl Schedule of Values
'flank you for your Consideration.
Respectfully Submitted,
SHORELINE FOUNDATION, INC,
Jae -aid Kartunat
Prclject Manager
Marnbors of: Doop 1=oundalton1n8tifuto .Kiln Drivors Contractors As,tociation . CASF
ATTACHMENT 11B"
&Si I FL
^i
ttf,.4 1
2781 S.W. 66"' Avoluto . P9mbroko Park, Florida 33023
Phone. (9,154) 985 -0450 . Fax: (954) 986 -0462 - www.shorellnOfoltrtclation.com
Jtnc 14, 201.2
JOEL WADSWORTH
Project lblatlager (Browaml)
Calvin, Giordano & Associates, Inc.
1 SOO .filler Drive, Sltite 000
Fort Lnudcixlulc, Florida 333I-b
Re: Sunny Isles Beach/Newpot.Fishing, Pier Park- Proposal No. 10- 07_ { }2
Subject: Change Ordcr No, 26Rcv -2
Cost frol)osal for light (08) - 40' -0" Long, 18" Diameler Augcreast Piles for Bents RI, RI a, Rlb & 10
Dear IMr. Wadsworth:
Shorcl ale Foundation, hie. (SFI) is plensed to jimsunt our revised cost proposal for Change Order No 2.6. Muse nmvt this linter
as our response to Provide cost proposal for (08) -X40' Long, 18" diameter al►l;ereast p1le for Bents R 1, R it, RI It & R2. The
price for this change order proposal is $57,094, 10.
'flu labor cost rot' Blovated Colnnn shown in the suln.11lary sheet (if C.O.Itev- ldated April, 1901, 2012 is not correct. For sonic
reason this cost has been carried out in Rev -1 rrom i", submission of tlic chlingo order. This cost has been removed in Rev -2 of
the change order.
13dom, is the change or(Icr sn:inllalry. See amubcd Exhibits -"A ", I'D", "C ", "n ", & "L" for Scope of Work .St Pricing.
T 1 e Re Neste 1,.,
The above scope of worts will involve ftRecn (15) additional work (lays. Accordingly, BFI is requesting it 111110 crtensiaa of
Hficen (15) Work days ill conjunction with thisproposal.
No'rE 9 It SFl would like to requost City of sunny Isle .t3.ench it) review our revised cllangc order and make Ilse decision Wore
nugereast pile hista It'll ioil fulls It) critical petit. S171 is offcritlg their best and final offer in (Ills revised Change order. Nowevcr, if
Iho City decl(l.Cs to engage tiny other contractor to Install 1110 augercilst pills, umplion stilted In our letter dated May 25, 2.012
regarding subject uluinge ordci will apply. Plcnsc.scc attaclicsl catty of letter for your calweniellcc.
NOT1? It 2: Third party cerlltied inspection S" Jogging of piles huvc not been included in the chunwo order Cost. In order to
provide the cost, SFi requires complete detail for the inspection & certification required by the City.
'rllnnk You far your consideration.
R.especlikilly Submitted,
SHORE, LINE FOUNDATION, INC.
Jawn K irnnlat
Project Manager
Members of: beep Foundation Institute - P11a, Drivers Contractors Association - CASF ��
Project: Newport Fishing Pier- Augarcast Piles
Owner Contract No.
Owner:
Data: Jane 14, .2012 MUM rm
Location: Augercast Piles for Restaurant
Building,
SFI Contract No. M10 -443 (Exhibit -A)
Contractor; Shoreline Foundation, Inc.
2781 SW 56 Ave
Pembroke Park, Florida 33023
(REVISED) WORK 11 0131FICATION REQUEST
Description Type
Unit of
Maas.
units
Unit Cost
Labor
Equipment
Matorial
Moir
Description of additional work, SUMMARY '(REVISED WORMATION)
Equipment Cost
E
us
1
$21.02.90
21,502.96
Mobilization Cost
H
us
1
$10,000100
$10,000,00
Material Cost
M
US
1
$12,631.70
$12,531.79
Augorcast Labor Cost
L
US
1
$12,099.35
$12,999.3b
*3rd PartyEnglneering
( Inspections /Pile Log Etc.)
5
TOD
TBD
TBD
TBD
TBD
T13D
Subtotal
$12,999,35
$21.662.90
$12,531:79
$10,000,00
Subtotal
$57,094.10
$0.00
Total
$67,094.10
Project; Newport Fishing Pier- AupnmASt Pilao
Owner Contract No. l _,l 1 -" • a
Owner: -1 'N • :i=ce
Date: June 14, 2012
Location: Augercast Piles for Restaurant Bullding.
SFl Contract No. M10 -443 (Exhibit -F!)
Contractor: Shoreline Foundation, Inc,
2781 SW 56 Ave
Pembroke Park, Florida 33023
(REVISED) WORK MODIFICATION REQUEST
Description
Type
Unit of
MQas
Unite
Unit Cost
wloperating
expense
Labor
Equipment
Matorial
Sub -Cent,
ALL EQUIPMENT COSTS FOR AUGERCAST PILING ACTIVITIES "(REVISED INFORMATION)
Equipment Cost
I-Mbelt L81 38 LS SERIES Crane (80 Ton)
E
Mhrs
40.00
$238.76
0470,00
*Llnkbeff LS160 SERIES
EKCAVATO
E
Mhrs
40,00
$57.65
23116,00
Ape 75 Drlil & Motor
E
Mhrs
40.00
$102.24
4089.60
Leads for Drilling equipment
E
Mhrs
40.00
$7.96
318.40
18 inch Flighting
E
Mhrs
40.00
$24.65
986.00
Welding Machino & Misc. Rigging
E
Mhrs
40,00
$20,00
600.00
Standard Grout Purnp (Pilo Bottoms)
E
Mhrs
40,00
$24,61
080.40
Subtotal
$0,00
$18,7b0.40
$0,00
$0.00
Subtotal
$18,750.40
Marls -Up (16 %)
$2,812.56
Total
$21,56196
Page 1 of 1
Project: !Newport Fishing Pier- Augereast Piles
Owner Contract No,
Owner:
Date: June 14, 2012 t�
SFI Contract
Location: Augercast Piles foi• Restaurant Builcling,
SFI Contract No, M10 -443 (Exhibit -C)
Contractor: Shoreline Foundation, Inc.
2781 SW 66 Ave
Pembroke Park, Florida 33023
WORK MODIFICATION REQUEs"r
Description
•ryl)o
Unit of
Was,
units
unit Cost
Re- drives
CRANE MOBILIZATION - (REVISED INFORMATION)
Additbonal Mobilization Costs
*Mobil /zatlon In
Mobe
LS
1.00
$5,000,00
*De- mobilization Out
Mobe
LS
1.04
$5,000.00
Subtotal
$0.00
Subtotal
$10,000,00
Mark -Up ( 00.00 %)
$0.00'
Total
$10,000.00
Project: Newport Fishing Plor- Augercast Mlles
Owner Contract No,
Owner: �w �::
Date: June 14, 2012 +
Location Augereast Piles for Restaurant Building,
SFI Contract No, M10 -443 (Exhibit -D)
Contractor: Sh.orolin4 Foundation, Inc,
2761 SW 56 Ave
Pembroke Park, Florida 33023
(REVISED) WORK MODIFICATION REQUEST
Doscription
TYBo
Ur71t of
Maas.
Units
Unit Cost
Labor
Equq>ment
Matorlal
Sub -Cant,
MATERIAL COST FOR RIGHT (8) 18 "X40- I -ONG AUGERCAST PILES "(Ri~VISED INf ORMATION)
Material Cost
Concrete/Grout
M
CY
34.00
$108.00
3672,00
Rebar
M
TONS
4.10
$909.32
3728.21
Tie & Place Rebar
M
TONS
4.10
$450,00
1845.00
Safety Caps /ContralizerslTEos & Accessories
M
LS
1.00
$256,00
269;00
*Sonatobe
M
LF
60.00
$14.20
862,00
Lumber
M
L/S
1,00
$470.00
479.00
HDW'E and fasteners
M
1.15
1.00
$95,00
05.00
Subtotal
$0.00
$0.00
$9,0.52_.21
$1,045.00
Subtotal
$10,897.2.1
Mark -Up (15 %)
$1,634,•58
Total
$12,531.79
Page 1 of 1
h(ojecl; Newport Fishing Pler- Augorcasl Piles SFI Conlrocl No. M10 -443 (Exltlblt •E)
Owner Contract No,
Owner: v Contractor: Shoreline I "oundation, hic.
2781 SW 88 Ave
Date: Juno 14, 2012 Pembroke Park, Florlda 33023
Location: Auderctrst Piles for Restaurant
Rultding,
Worst Modification Request
pascriplian
Typo
Unit of
Maas,
RoUular
Flours
Overtime
Hours
ReOular
Wa.goiRate
Overtime
WagetRate
Total
Burden %
Rogular
Hours Labor
Cost
Overtlnre
Hours
Labor
Cost
Total Labor
Cost
LABOR COST TO INSTALL AUG ERCAST PILES ` (REVISED INFORMATION)
Augercast Labor Cost
*Job supwIniondollf
L
Mrs
0.00
010
M,20
$40:80
44,20%
S
$
$
Cran.e.Oparator
L
Mrs
40.00
0.0
$57.45
$56,10
14.20%
$ 2,160.12
$
$ 2,160.12
Equipment Operator
L
Mhrs
40.00
0.0
$26:80
$38.70
44,20%
$ 1,488,14
$
$ 1,488.14
Concrete Pump Operator
L
Mhrs
40.00
0.0
$24.70
$37.05
44.20%
$ 11,424.70
$
$ 5,424,70
Form Carpenter
L
Mhrs
40.00
0.0
$24.70
$37,06
44.20%
$ 1,424.70
S
$ 1,424.70
Pile Driving Foreman
L
Mhrs
40.00
0,0
$28.00
$42.00
50.08%
$ 1,600.00
$
$ 1,680.go
Pile Dove Jour(royntan I Skilled
Laborers
L
Mrs
40.00
0.0
$18.00
$27.00
54.53%
$ 1,112.42
$
$ 1,112.62
Pile Drive Journeyman 1 Skilled
Laborer 2'
L
Mrs
49.00
0.0
$18,00
27.
$00
84 63%
$ 1,112.62
$
$ 1,112.82
Piles Layout & As- bullts
(81rb- Contract)
L
LS
1.00
0.0
0.0
0.0
0,0 V
010
OA
$ 500.00
S -
$
SU1)totpl
$10,403:78
$0.00
$11,303.78
Sublote)
$11,303.78
Mark -Up (16,0 %)
$1,QrJG,67
Total
$12,999.35
c,r� of su!+ Ha
City of Sunny Isles Beach
18070 Collins Avenue
Sunny Isles Beach, Florida 33160
(305) 947 -0606 City Hall
(305) 949 -3113 Fax
MEMORANDUM
TO: The Honorable Mayor and City Commission
FROM: Chief Fred A. Mass, Acting City Manager
DATE: 7/19/2012
RE: Shoreline Foundation, Inc Construction Change Order #6 for the
Newport Pier Project
RECOMMENDATION:
It is recommended that the attached Resolution be approved.
REASONS:
The original contract plans for the approach slab to the restaurant building called for six
(6) 24 "x24" precast piles at a price of $43,795.64 to be driven via diesel hammer ane
would require temporary encroachment onto LaPerla property. This would have the
potential for cracking /spalling of the deck/structure due to vibration. The revised plar
relocates the piles, reduces their size and utilizes in installation methodology whicl•
reduces vibrations, and due to the smaller size of these piles, the number of piles requires
to support the structure is increased from six (6) to eight (8).The change order fol
installing eight (8) 18" round auger cast piles was not considered in the original contract
and is resulting in Change Order No. 6 increasing the Agreement in an amount not tc
exceed $13,298.46.
Please note that this Change Order increases the contract time by fifteen (15) days. A report
prepared by Calvin Giordano is attached.
FUNDING SOURCE:
Funding is available in account number 20- 600 -5670.
ATTACHMENTS:
Resolution
Change Order No. 6
Agenda Item No. IOL\nDate 7/19/2012