RESOLUTION NO. 2017- Z1s1
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
SUNNY ISLES BEACH, FLORIDA, APPROVING CHANGE
ORDER NOS. 1 AND 2 TO AGREEMENT #3 WITH EBSARY
FOUNDATION CO. FOR THE THIRD PHASE OF THE
CONSTRUCTION OF THE NORTH BAY ROAD PEDESTRIAN
EMERGENCY BRIDGE, IN AN AMOUNT NOT TO EXCEED SIX
: HUNDRED SIXTEEN THOUSAND THREE HUNDRED SEVENTY-
.
- NINE DOLLARS AND FORTY-EIGHT CENTS ($616,379.48),
ATTACHED HERETO, IN SUBSTANTIALLY THE SAME FORM,
AS EXHIBIT "A"; AUTHORIZING THE CITY MANAGER TO
SIGN SAID CHANGE ORDERS; AUTHORIZING THE CITY
MANAGER AND CITY ATTORNEY TO DO ALL THINGS
NECESSARY TO EFFECTUATE THE TERMS OF THIS
P. RESOLUTION; PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, on February 16, 2017, via Resolution No. 2017-2663, the City Commission
approved Agreement #1 with Ebsary Foundation Co. for the North Bay Road Pedestrian
Emergency Bridge for the North Bay Road Pedestrian Emergency Bridge, consisting of
mobilization, MOT, demolition, drilled shafts, cast in place concrete, precast concrete structure,
administration, contingency, and associated fees in an amount not to exceed $3,407,032.45; and
WHEREAS, on February 16, 2017, via Resolution No. 2017-2664, the City Commission
approved Agreement #2 with Ebsary Foundation Co. for the North Bay Road Pedestrian
Emergency Bridge for the North Bay Road Pedestrian Emergency Bridge, consisting of bridge
approaches, MSE walls, road bed support, administration, contingency and associated fees in an
• amount not to exceed $1,796,673.45; and
WHEREAS, on February 16, 2017, via Resolution No. 2017-2665, the City Commission
approved Agreement #3 with Ebsary Foundation Co. for the North Bay Road Pedestrian
Emergency Bridge for the North Bay Road Pedestrian Emergency Bridge, consisting of finish
grade, road bed, asphalt, pavers, decorative fencing, hardscape, permanent safety elements,
electrical system, administration, contingency and associated fees in a total amount not to exceed
$823,010.95; and
WHEREAS, Ebsary Foundation Co. has submitted Change Order No. 1 to include bridge
decorative colored surface material, landscape planters, wooden benches, and associated rigid
pavement slabs required to provide a pedestrian friendly atmosphere; and
WHEREAS, Ebsary Foundation Co. has submitted Change Order No. 2 to include the
addition of storm water drainage for the bridge and improved storm water drainage and pavement
for the roadway abutting the emergency/pedestrian bridge; and
51
WHEREAS, staff has determined that additional services beyond the original scope of
E .
work is needed to remain on schedule and complete the project; and
Page I of 3
R2017 Ebsary Agmt No 3 COs 1 and 2
5:t
WHEREAS,the City wishes to approve Change Order Nos. 1 and 2 to Agreement#3 with
Ebsary Foundation Co. for the North Bay Road Pedestrian Emergency Bridge for the North Bay
Road Pedestrian Emergency Bridge, in a total amount not to exceed Six Hundred Sixteen Thousand
Three Hundred Seventy-Nine Dollars and Forty-Eight Cents ($616,379.48), attached hereto, in
•
substantially the same form, as Exhibit "A", bringing the total amount of Agreement #3 not to
exceed One Million Four Hundred Thirty Nine Thousand Three Hundred Ninety Dollars and Forty
Cents ($1,439,390.40).
•
NOW THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF SUNNY ISLES BEACH, FLORIDA, AS FOLLOWS:
4.+
i`f:
Section 1. Approving Change Order Nos. 1 and 2 to Agreement #3 with Ebsary Foundation
Co. The City Commission hereby approves Change Order Nos. 1 and 2 to Agreement #3 with
Ebsary Foundation Co. for the North Bay Road Pedestrian Emergency Bridge for the North Bay
Road Pedestrian Emergency Bridge,in a total amount not to exceed Six Hundred Sixteen Thousand
Three Hundred Seventy-Nine Dollars and Forty-Eight Cents ($616,379.48), attached hereto, in
substantially the same form, as Exhibit "A", bringing the total amount of Agreement #3 not to
exceed One Million Four Hundred Thirty Nine Thousand Three Hundred Ninety Dollars and Forty
Cents ($1,439,390.40).
Section 2. Authorization of City Manager. The City Manager is hereby authorized to sign
•
Change Order Nos. 1 and 2, attached hereto, in substantially the same form, as Exhibit "A".
Section 3. Authorization of City Manager and City Attorney. The City Manager and City
Attorney are authorized to do all things necessary to effectuate the terms of this Resolution.
Section 4. Effective Date. This Resolution shall become effective upon adoption.
-`` PASSED and ADOPTED this 16th day of No ember 1017.
•
Geol.! - H. Scholl, Mayor
AT . ST
41 I
•
Maur io Bet. ur,CMC, City Clerk
` s
t.
Page 2 of 3
82017 Ebsary Agmt No 3 COs 1 and 2
.
APPROVED • : TO FORM
AND LEGICIENCY:
,D! /4/4Ottinot, City Attorney
3r
Aft:
Moved by: ICC 146,-- Ctvi pl-Ns
ebMVAt
Seconded by: tOv'i Gii-T"a
Vote:
Mayor Scholl " (Yes) (No)
Vice Mayor Goldman (Yes) (No)
Commissioner Aelion I(Yes) (No)
Commissioner Gatto (Yes) (No)
Commissioner Svechin V (Yes) (No)
•
Page 3 of 3
R2017 Ebsary Agmt No 3 COs 1 and 2
r.:
S,31.4
NYis4
,r.- *F s _ . PF
CHANGE;, 4CITY OF
SUNNY ISLES BEACHORDERtiC• FLO
s
Y OF $UN
CHANGE ORDER NUMBER: 1 DATE: October 31,2017
i •
PROJECT:
RFP NUMBER: 14-09-01 North Bay Road Pedestrian Emergency
Bridge
RESOLUTION NUMBER:
r..
ORIGINAL DOLLAR CONTRACT AMOUNT: $ 823,010.95
NET TOTAL DOLLAR VALUE OF ALL PREVIOUS CHANGE ORDERS: $ 0
DOLLAR AMOUNT OF THIS CHANGE ORDER: $ 423,690.20
CREDIT/DIRECT PURCHASES: $ 0
NEW DOLLAR CONTRACT AMOUNT: $ 1,246,701.15
ORIGINAL CONTRACT COMPLETION DATE February 15,2018
TOTAL OF PREVIOUS CHANGE ORDER DAYS: 0 - Zero
AMOUNT OF DAYS PER THIS CHANGE ORDER: 0 - Zero
NEW CONTRACT COMPLETION DATE: February 15,2018
DESCRIPTION OF SCOPE OR WORK CHANGES:
• Add decorative Paveway colored surface material, landscape planters, wooden benches, and
rigid concrete pavement slabs as depicted on CGA documents, Dated June 14, 2017
Sheets SP -201 thru IR - 103
NOTE: Unless specifically stated clearly elsewhere on this page, this contract amendment does NOT Include an
extension of time or grant any additional general conditions amounts. The City and the Contractor agree that the
contract time adjustment and sum agreed to in this document constitute a full and complete settlement of the
s matters set forth herein, including all direct and Indirect costs for equipment, manpower, materials, overhead, profit
and delay relating to the issues set forth in this document.
CONTRACTOR
CITY ATTORNEY:
PROJECT MANAGER:
CITY MANAGER:
S
Ok S �NwwY`l id
. , j ? , CITY OF CHANGE
t
* V F SUNNY ISLES BEACH
- ; P ORDER
y' *FLOC\ S'i•
C,T)'OF SUN PNO
CHANGE ORDER NUMBER: 2 DATE: October 31,2017
PROJECT:
RFP NUMBER: 14-09-01 North Bay Road Pedestrian Emergency
Bridge
RESOLUTION NUMBER:
I
ORIGINAL DOLLAR CONTRACT AMOUNT: $ 823,010.95
NET TOTAL DOLLAR VALUE OF ALL PREVIOUS CHANGE ORDERS: S 423,690.20
DOLLAR AMOUNT OF THIS CHANGE ORDER: S 192,689.28
CREDIT/DIRECT PURCHASES: S 0
NEW DOLLAR CONTRACT AMOUNT: S 1,439,390.43
ORIGINAL CONTRACT COMPLETION DATE February 15,2018
TOTAL OF PREVIOUS CHANGE ORDER DAYS: 0 - Zero
AMOUNT OF DAYS PER THIS CHANGE ORDER: 0 - Zero
NEW CONTRACT COMPLETION DATE: February 15,2018
DESCRIPTION OF SCOPE OR WORK CHANGES:
Add storm water drainage system to bridge approaches, storm water drainage system and '
asphalt paving to Salem House Condominium as depicted on CGA documents, Dated June 14,
2017
Sheets SP -201 thru IR - 103
NOTE: Unless specifically stated clearly elsewhere on this page, this contract amendment does NOT include an
extension of time or grant any additional general conditions amounts. The City and the Contractor agree that the
contract time adjustment and sum agreed to In this document constitute a full and complete settlement of the
matters set forth herein, including all direct and indirect costs for equipment, manpower, materials, overhead, profit
and delay relating to the Issues set forth in this document.
CONTRACTOR
CITY ATTORNEY:
PROJECT MANAGER:
CITY MANAGER:
,z.
Y -
SJp�NY lS�� City of Sunny Isles Beach
18070 Collins Avenue
77, 11.s Sunny Isles Beach, Florida 33160
Ec.9,.•FLoR`O ;4 (305)947-0606 City Hall
'+ Tr of s�K'otC (305)949-3113 Fax
MEMORANDUM
{ • TO: The Honorable Mayor and City Y Commission
FROM: Christopher J. Russo, City Manager
DATE: 11/16/2017
Approving Change Order Nos. 1 and 2 with Ebsary
RE: Foundation Company for the North Bay Road
Emergency/Pedestrian Bridge
RECOMMENDATION:
This Resolution is presented for your consideration.
REASONS:
1. The original bridge design and bid document did not include final
aesthetic finishes including, bridge decorative colored surface material,
landscape planters, wooden benches, and associated rigid pavement
slabs required to provide a pedestrian friendly atmosphere. These
items are included in Change Order No. 1 for the amount of
$423,690.20
2. Additional design study of the bridge approaches by the project
engineer resulted in the addition of, storm water drainage for the bridge
and improved storm water drainage and pavement for the abutting
Salem House Condominium (SHC) necessitated due to the addition of
bridge approach roadways and temporary construction easements
granted by SHC necessary to physically construct the bridge structure.
These items are included in Change Order No. 2 for the amount of
$192,689.28
ADDITIONAL INFORMATION:
�t.
Remaining items not contemplated in the design and bid documents,
39
#F
that will need to be funded include, the improvements to the Salem
House parking lot lighting, paving, new fencing and exit gate. These
improvements where part of the agreement with Salem House by which
they have provided us a temporary construction easement and their full
cooperation in allowing us to stage for construction from within their
property.
The relocation of the FPL transformer, which is currently in the City
bridge easement, may come to fruition on a tract of City-owned land
abutting the Salem House property for which an access easement
would be necessary. The westside of the North bridge landing ramp will
require some concrete work in order to have a finished look to this
exposed area.
Substantial completion is expected by the end of this calendar year.
FUNDING SOURCE:
300-5-5390-465000-83001
ATTACHMENTS:
Description
Resolution
Change Order Nos. 1 and 2