HomeMy WebLinkAboutReso 2018-2869 RESOLUTION NO. 2018- '2)14)1
A RESOLUTION OF THE CITY COMMISSION OF THE CITY
OF SUNNY ISLES BEACH, FLORIDA, APPROVING CHANGE
ORDER NOS. 20 AND 21 RELATING TO THE AGREEMENT
WITH ROHL GLOBAL NETWORKS, LP FOR THE COLLINS
AVENUE UTILITIES UNDERGROUNDING PROJECT,
ATTACHED HERETO, IN SUBSTANTIALLY THE SAME FORM,
AS EXHIBIT "A"; AUTHORIZING THE CITY MANAGER AND
CITY ATTORNEY TO DO ALL THINGS NECESSARY TO
EFFECTUATE THIS RESOLUTION; PROVIDING FOR AN
EFFECTIVE DATE.
WHEREAS, on February 18th, 2016 via Resolution No. 2016-2525, the City
Commission approved an agreement with Rohl Global Networks, LP ("Contractor"), for the
Construction of the Collins Avenue Utility Undergrounding, in an amount of$4,830,000.00, and
an owner contingency in the amount of $500,000.00, and an additional contingency in the
amount of$1,500,000.00 for additional scope of work for Atlantic Boulevard, for a total amount
not to exceed $6,830,000.00; and;
WHEREAS, on February 16th, 2017, the Contractor submitted Change Order Nos. 1
through 6 which added:
• 11,297 lineal feet of conduits as directed by the City;
• Additional concrete removal and conduit placement in Town Center Park;
• Completed miscellaneous below grade improvements on Collins Avenue and 195th Street;
• Completed miscellaneous below grade improvements along the Atlantic Corridor;
• Completed Collins Avenue due to the added scope of work and unforeseen conditions; and
• Purchased material for the Collins Avenue Street Light Project; and
Change Order Nos. 1 through 6 were in an amount not to exceed $4,967,989.00, bringing the
total contract amount to not to exceed $11,797,989.00; and
WHEREAS, on October 19, 2017 via Resolution No. 2017-2751, the City Commission
ratified Change Order Nos. 7 through 9 and approved Changer Order Nos. 10-14, which:
• Credited the City for direct material purchases in an amount of$528,677.28;
• Credited the City for direct material purchases in an amount of$101,116.22;
• Added 365 days to the length of the original contract thereby extending the completion
date to March 31, 2018;
• Repaired numerous pavement patches along Collins Avenue;
• Repaved an additional 9,394 square feet along Collins Avenue;
• Repaired and replaced the sidewalk on Atlantic Boulevard from 178th Street to 1831d Street
WHEREAS, on February 15th, 2018 via Resolution No. 2018-2788 the City Commission
ratified Change Order No. 15 and approved Change Order Nos. 17 and 18 with Rohl Global
Networks, LP for credits to the City for direct material purchases, extension for project
completion, recognizing a company name change, and decreasing the contract value in the
amount of Seventy-Nine Thousand Five Hundred Dollars ($79,500.00), bringing the total
contract amount not to exceed $13,581,192.50; and
R2018 CO 20&21 w Rohl Networks Page 1 of 3
WHEREAS, on February 15i11, 2018 via Resolution No. 2018-2789 the City Commission
ratified Change Order No. 16 and approved Change Order Nos. 16A and 16B with Rohl Global
Networks, LP for credits to the City for direct material purchases and the rescinding of Change
Order No. 16, decreasing the contract value in the amount of Six Hundred Sixty-Six Thousand
Two Hundred Fifty Dollars ($666,250.00), bringing the total contract amount not to exceed
$12,914,942.95; and
WHEREAS, on May 17th, 2018 via Resolution No. 2018-2816 the City Commission
approved Change Order No. 19 for the addition and relocation of Florida Power & Light and
Atlantic Broadband services equipment, revised Atlantic corridor scope of work, and other
unforeseen conditions on Collins Avenue in the amount of$899,524.00; and
WHEREAS, the Contractor has submitted Change Order No. 20 crediting the City for
direct material purchases in an amount of Thirty Seven Thousand One Hundred Dollars
($37,100.00), bringing the total contract amount not to exceed Thirteen Million Seven Hundred
Seventy-Seven Thousand Three Hundred Sixty-Six Dollars and Ninety-Five Cents
($13,777,366.95), attached hereto as Exhibit "A"; and
WHEREAS, the Contractor has submitted Change Order No. 21 in an amount not to
exceed Thirty Four Thousand Seven Hundred Ninety-Six Dollars ($34,796.00) for work and
material completed to assure that the State of Florida RRR project did not adversely impact the
work previously completed, bringing the total contract amount not to exceed Thirteen Million
Eight Hundred Twelve Thousand One Hundred Sixty-Two Dollars and Ninety-Five Cents
($13,812,162.95),attached hereto as Exhibit "B"; and
WHEREAS, the City Commission wishes to ratify Change Order No. 20 crediting the
City for direct material purchases, and Change Order No. 21 for work and material completed to
assure that the State of Florida RRR project did not adversely impact the work previously
completed, in the amount of Thirty Four Thousand Seven Hundred Ninety-Six Dollars
($34,796.00), bringing the total contract amount not to exceed Thirteen Million Eight Hundred
Twelve Thousand One Hundred Sixty-Two Dollars and Ninety-Five Cents ($13,812,162.95),
attached hereto as Exhibit "A" and "B".
NOW THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF SUNNY ISLES BEACH, FLORIDA, AS FOLLOWS:
Section 1. Ratification of Change Order No. 20. The City Commission hereby ratifies
Change Order No. 20 crediting the City for direct material purchases in an amount of Thirty
Seven Thousand One Hundred Dollars ($37,100.00), bringing the total contract amount not to
exceed Thirteen Million Seven Hundred Seventy-Seven Thousand Three Hundred Sixty-Six
Dollars and Ninety-Five Cents ($13,777,366.95), attached hereto as Exhibit "A".
Section 2. Ratification of Change Order No. 21. The City Commission hereby ratifies
Change Order No. 21 in an amount not to exceed Thirty Four Thousand Seven Hundred Ninety-
Six Dollars ($34,796.00) for work and material completed to assure that the State of Florida
RRR project did not adversely impact the work previously completed, bringing the total contract
amount not to exceed Thirteen Million Eight Hundred Twelve Thousand One Hundred Sixty-
Two Dollars and Ninety-Five Cents ($13,812,162.95), attached hereto as Exhibit "B".
R2018 CO 20&2I w Rohl Networks Page 2 of 3
1
Section 3. Authorization of City Manager. The City Manager is hereby authorized to do all
things necessary to effectuate this Resolution.
Section 4. Effective Date. This Resolution shall become effective upon adoption.
PASSED AND ADOPTED this 20th da, of September 2018.
t, George H Scholl, Mayor
ATT 1i ST: t
14r1/Ifpf
Mauric o Beta cur, CMC, City Clerk
4. \.
APPROVED AS TO FORM AND
LEGAL SUF I GIENCY:
ifdAY: AAl -
A 'OAS
• s 0 riot, City Attorney
•
Moved by: V 1 c t 044 60(..blt
Seconded by: COVINVttcsictonreXZ_ CI 'a
Vote:
Mayor Scholl (Yes) (No)
Vice Mayor Goldman (Yes) (No)
Commissioner Aelion I (Yes) (No)
Commissioner Gatto ✓ (Yes) (No)
Commissioner Svechin f (Yes) (No)
R2018 CO 20&21 w Rohl Networks Pa2e 3 of 3
l
soONY /s46,
�� F
ry_ n CONTRACT
CITY OF
i7.
3 * SUNNY ISLES BEACH
oP Change Order
tiF 1* FLO�\
C/rY OF SUN P°O
CHANGE ORDER NUMBER: 20 DATE: August 21, 2018
PROJECT:
RFP NUMBER: 15-42-02 Collins Avenue Utility Undergrounding
RESOLUTION NUMBER: TBD
•
ORIGINAL DOLLAR CONTRACT AMOUNT: $ 6,830,000.00 .
NET TOTAL DOLLAR VALUE OF ALL PREVIOUS CHANGE ORDERS: $ 6,984,466.90
CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER: $13,814,466.90
DOLLAR AMOUNT THIS CHANGE ORDER: $ -37,100.00
NEW DOLLAR CONTRACT AMOUNT: $13,777,366.95
ORIGINAL CONTRACT COMPLETION DATE March 31, 2017
TOTAL OF PREVIOUS CHANGE ORDER DAYS: 730
AMOUNT OF DAYS PER THIS CHANGE ORDER: 0
NEW CONTRACT COMPLETION DATE: March 31, 2019
DESCRIPTION OF SCOPE OR WORK CHANGES:
The Contract is changed as follows: Deduct Change Order for Purchas Order issued by Sunny Isles Beach to
Power & Tell Supply for direct purchase of material purchased by the City. P.0.16-01192 to P&T adding
$34,688.50 and P.O. 16-00792 to ROHL deducting $37,100.
NOTE: Unless specifically stated clearly elsewhere on this page, this contract amendment does NOT include an
extension of time or grant any additional general conditions amounts. The City and the Contractor agree that the
contract time adjustment and sum agreed to in this document constitute a full and complete settlement of the
matters set forth herein, including all direct and indirect costs for equipme ., manpower, materials, overhead, profit
and delay relating to the issues set forth in this document. / j
ROHL Networks ' Fjpipoo—
CONTRACTOR
Hans Ottinot ,,��
CITY ATTORNEY:
Paul T. Abbott P . /Neer
PROJECT MANAGER:
Chris Russo Gla
CITY MANAGER:
SONNY �S<
CONTRACT
U � iniw 4� s_ S
CITY OF
SUNNY ISLES BEACH
Y oP P Change Order`
tiF , �
* FLO�
C,TY OF SUN Pao
CHANGE ORDER NUMBER: 21 DATE: August 21, 2018
PROJECT:
RFP NUMBER: 15-42-02 Collins Avenue Utility Undergrounding
RESOLUTION NUMBER: TBD
ORIGINAL DOLLAR CONTRACT AMOUNT: $ 6,830,000.00
NET TOTAL DOLLAR VALUE OF ALL PREVIOUS CHANGE ORDERS: $ 6,947,366.95
CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER: $13,777,366.95
DOLLAR AMOUNT THIS CHANGE ORDER: $ 34,796.00
NEW DOLLAR CONTRACT AMOUNT: $13,812,162.95
ORIGINAL CONTRACT COMPLETION DATE March 31, 2017
TOTAL OF PREVIOUS CHANGE ORDER DAYS: 730
AMOUNT OF DAYS PER THIS CHANGE ORDER: 0
NEW CONTRACT COMPLETION DATE: March 31, 2019
DESCRIPTION OF SCOPE OR WORK CHANGES:
The Contract is changed as follows: Increase contract amount by $34,796.00 for work and material completed to
assure that the State of Florida RRR project did not adversely impact the underground conduit lines installed by
ROHL prior to FDOT RRR project. Damaged installations found were repaired and paid by FDOT.
NOTE: Unless specifically stated clearly elsewhere on this page, this contract amendment does NOT include an
extension of time or grant any additional general conditions amounts. The City and the Contractor agree that the
contract time adjustment and sum agreed to in this document constitute a full and complete settlemen •
matters set forth herein, including all direct and indirect costs for equipment, manpower, materi. :'-r ead, profit
and delay relating to the issues set forth in this document.
ROHL Networks
CONTRACTOR {
Hans Ottinot
CITY ATTORNEY:
Paul T. Abbott
et
PROJECT MANAGER: T. ff66o
Chris Russo
CITY MANAGER: 4,41414
9/28/2018 Item Coversheet
t
s,)"uY.s`F City of Sunny Isles Beach
F _ j
p`i r, 18070 Collins Avenue
, r J.- :: = Sunny Isles Beach, Florida 33160
s• ''`.0..4. (305)947-0606 City Hall
FSO
`,r, a,„,„,.N° (305)949-3113 Fax
MEMORANDUM
TO: The Honorable Mayor and City Commission
VIA:
FROM: Christopher J. Russo, City Manager
DATE: 9/20/2018
Approving Change Order Numbers 20 and 21 for Rohl
RE: Networks, LP for Work Associated with the Collins
Avenue Utility Undergrounding Project
RECOMMENDATION:
This Resolution is presented for your consideration.
REASONS:
Change Order Number 20 decreases the Rohl contract amount by
$37,100.00.This reduction is due to a Direct Purchase Order issued to
Power and Tell Supply for the direct purchase of materials purchased
• by the City. This decrease results in a total contract amount for this
project of$13,777,366.95.
Change Order Number 21 increases the Rohl contract amount by
$34,796.00. This increase is for work and material completed to -
assure that the State of Florida resurfacing project did not adversely
impact the underground conduit lines installed by Rohl prior to the
FDOT project commencement. Any damaged installations found were
repaired and paid by FDOT and are not included in this amount. This
increase results in a new contract amount with Rohl Networks of
$13,812,162.95.
ADDITIONAL INFORMATION:
The net result of these two change orders is a reduction of$2,304.00.
FUNDING SOURCE:
Funds are budgeted for and available in the Capital Improvement Plan
Fund in the Utility Undergrounding project account number 300-5-
5390-465000-80004.
ATTACHMENTS:
Description
Resolution
Change Order No. 20
Change Order No. 21