My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Gateway Park Technical Specs Volume 1 (3)
SIBFL
>
City Clerk
>
Bids-RFQ-RFP
>
ITB
>
(19-01-01) Gateway Park Center
>
Gateway Park Technical Specs Volume 1 (3)
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
1/31/2019 1:53:00 PM
Creation date
1/31/2019 1:35:01 PM
Metadata
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
724
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Gateway Park Center PERKINS+WILL <br /> 810495.000 <br /> 12/06/18 <br /> <br /> <br />CONTRACT MODIFICATION PROCEDURES <br /> 01 26 00 - 1 <br /> <br /> <br />SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES <br />PART 1 - GENERAL <br />1.1 SUMMARY <br />A. Section includes administrative and procedural requirements for handling and <br />processing Contract modifications. <br />1.2 MINOR CHANGES IN THE WORK <br />A. Architect will issue supplemental instructions authorizing minor changes in the <br />Work, not involving adjustment to the Contract Sum or the Contract Time, on form <br />included in Project Manual. <br />1.3 PROPOSAL REQUESTS <br />A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of <br />proposed changes in the Work that may require adjustment to the Contract Sum or <br />the Contract Time. If necessary, the description will include supplemental or revised <br />Drawings and Specifications. <br />1. Work Change Proposal Requests issued by Architect are not instructions either <br />to stop work in progress or to execute the proposed change. <br />2. Within ten (10) days after receipt of Proposal Request, submit a quotation <br />estimating an equitable cost adjustment to the Contract Sum and the <br />Contract Time necessary to execute the change. <br />a. Include a list of quantities of products required or eliminated and unit <br />costs, with total amount of purchases and credits to be made. If <br />requested, furnish survey data to substantiate quantities. <br />b. Indicate applicable taxes, delivery charges, equipment rental, and <br />amounts of trade discounts. <br />c. Include costs of labor and supervision directly attributable to the <br />change. <br />d. Include an updated Contractor's construction schedule that indicates the <br />effect of the change, including, but not limited to, changes in activity <br />duration, start and finish times, and activity relationship. Use available <br />total float before requesting an extension of the Contract Time. <br />B. Contractor-Initiated Proposals: If latent or changed conditions require modifications <br />to the Contract, Contractor may initiate a claim by submitting a request for a <br />change to Architect. <br />1. Include a statement outlining reasons for the change and the effect of the <br />change on the Work. Provide a complete description of the proposed change. <br />Indicate the effect of the proposed change on the Contract Sum and the <br />Contract Time.
The URL can be used to link to this page
Your browser does not support the video tag.