Laserfiche WebLink
<br />CONSTRUCTABILITY <br />H&H’s design approach is integrated with practical construction techniques and the maintenance of traffic <br />approach. We have visited the Bridge Park site, developed site access alternatives, reviewed easement <br />documents, and a conducted lane closure analysis to minimize construction risk. <br />Foundation Installation <br />Installation of the 5 foot thick concrete pile cap requires a <br />cofferdam for dewatering. The permanent easement can <br />accommodate the footing with the western edge of the <br />cofferdam installed in the temporary easement. It is <br />anticipated that concrete trucks will line up in a lane closure <br />along 174th Street and access the cofferdam through the <br />temporary easement to deliver concrete for the augercast piles <br />and pile caps. <br /> <br />H&H-Designed SW 1St Street Bridge: Cofferdam Installation <br />Augercast Piles Installed with Cofferdam <br />D-19