E. RESUMES OF KEY PERSONNEL PROPOSED FOR THIS CONTRACT
<br />(Complete one Section E for each key person.)
<br />12. NAME
<br />Jeffrey O’Connor, PE
<br />13. ROLE IN THIS CONTRACT
<br />Underwater Inspection Leader/Inspector
<br />14. YEARS EXPERIENCE
<br />a. TOTAL
<br /> 34 b. WITH CURRENT FIRM
<br /> 7
<br />15. FIRM NAME AND LOCATION (City and State)
<br />Underwater Engineering Services, Inc., Fort Pierce, FL
<br />16. EDUCATION (DEGREE AND SPECIALIZATION)
<br />B.S.C.E. / 1985 / Iowa State University
<br />17. CURRENT PROFESSIONAL REGISTRATION (STATE AND DISCIPLINE)
<br />1996 / Professional Engineer / FL / #50914
<br />18. OTHER PROFESSIONAL QUALIFICATIONS (Publications, Organizations, Training, Awards, etc.)
<br />FHWA/NHI Certified Instructor for Underwater Bridge Inspection, Safety Inspection of In-Service Bridges & Bridge Inspection Refresher
<br />19. RELEVANT PROJECTS
<br />a.
<br />(1) TITLE AND LOCATION (City and State)
<br />Structure Inspection Program – Underwater Component, SFWMD
<br />South Florida
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />2020
<br />CONSTRUCTION (If Applicable)
<br />NA
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE [X] Check if project performed with current firm
<br />Project Assignment: Underwater inspection of water control structures. Three task work orders included 23, 36 and 38 structures for
<br />FY17-18, FY18-19 and FY19-20, respectively, including culverts, spillways, pump stations, boat locks, and weirs. Fee to date $1M.
<br />Inspections performed with surface-supplied air. All inspection video and audio were recorded. Mr. O’Connor was the Project Manager and
<br />on-site engineer for this work. He also signed and sealed all of the reports.
<br />b.
<br />(1) TITLE AND LOCATION (City and State)
<br />Prof. Services for Topside & Underwater Routine and Fracture Critical
<br />Bridge Inspections, Bolton Perez (BPA – Prime)
<br />Miami, FL
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />2017
<br />CONSTRUCTION (If Applicable)
<br />NA
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE [X] Check if project performed with current firm
<br />Project Assignment: Underwater structural assessments of five bridges as part of the Miami-Dade Transit Metromover train system.
<br />UESI provided a three-person dive team led by a registered Florida Professional Engineer-diver. The scope included all underwater
<br />elements, including piles, piers, footings, and fenders. Prepared report with elements and ratings similar to that used by FDOT. The contract
<br />amount was $14K. Mr. O’Connor was the Project Manager and performed the inspections.
<br />c.
<br />(1) TITLE AND LOCATION (City and State)
<br />FDOT Dist. 5 Local Gov’t. Bridge Inspections, Ayres Associates (Prime)
<br />East Central, Florida
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />2018
<br />CONSTRUCTION (If Applicable)
<br />NA
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE [X] Check if project performed with current firm
<br />Project Assignment: Underwater structural assessments of three movable bridges located in and north of Daytona Beach, FL. The project
<br />also included performing underwater quality assurance inspections of three bridges. The contract amount was $9K. Mr. O’Connor was the
<br />Project Manager and performed the inspections of two of the movable bridges.
<br />d.
<br />(1) TITLE AND LOCATION (City and State)
<br />FDOT SR-206 / Crescent Beach Bridge Cathodic Protection, GPI (Prime)
<br />Crescent Beach, FL
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />2020
<br />CONSTRUCTION (If Applicable)
<br />NA
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE [X] Check if project performed with current firm
<br />Project Assignment: Underwater construction engineering inspection services for piles on the SR-206 Bridge over the Matanzas River.
<br />Thirty-six piles required cathodic protection jackets. UESI inspected all piles prior to the work to verify the plans; then inspected each pile
<br />at least twice – once prior to jacket install to check the cleanliness, the rebar, and anode connection - and once after jacket install. The
<br />contract amount was $39K. Mr. O’Connor was the Project Manager and led approximately 50% of the inspections.
<br />e.
<br />(1) TITLE AND LOCATION (City and State)
<br />Design Services for City Marina Pier Replacement
<br />City of Vero Beach, FL
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />2017
<br />CONSTRUCTION (If Applicable)
<br />2018
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE [X] Check if project performed with current firm
<br />Project Assignment: Design of repairs to the main pier at the City Marina. This project followed the inspection project also performed by
<br />UESI. Repairs were comprised of hardware replacement, stringer replacement, beam replacement, one bent replacement, and pile repairs.
<br />The fee was $16K. Mr. O’Connor was the Project Manager and lead designer of the repairs.
<br /> STANDARD FORM 330 (1/2004) PAGE 2
<br />
<br />Section E - Page | 81
|