E. RESUMES OF KEY PERSONNEL PROPOSED FOR THIS CONTRACT
<br />(Complete one Section E for each key person)
<br /> 12. NAME
<br /> NESTOR SANTANA, PE
<br />
<br /> 13. ROLE IN THIS CONTRACT
<br />Construction Administration Services &
<br />Inspections, Cost Estimates; Structures;
<br />Threshold Inspections
<br />
<br /> 14. YEARS EXPERIENCE
<br /> a. TOTAL
<br />25
<br />
<br /> b. WITH CURRENT FIRM
<br />3
<br />
<br />15. FIRM NAME AND LOCATION (City and State)
<br />R. J. BEHAR & COMPANY, INC.
<br />6861 SW 196th Avenue, Suite 302
<br />Pembroke Pines, Florida 33332
<br />
<br />16. EDUCATION (DEGREE AND SPECIALIZATION)
<br />B.S. Civil Engineering, University of Puerto Rico, 1994
<br />
<br /> 17. CURRENT PROFESSIONAL REGISTRATION (STATE AND DISCIPLINE)
<br />Florida PE License No. 85785
<br />18. OTHER PROFESSIONAL QUALIFICATIONS (Publications, Organizations, Training, Awards, etc.)
<br />Mr. Santana has numerous years of experience in construction management for new construction and remedial projects of existing structures for
<br />the educational, pharmaceutical, sports & recreation, commercial sectors, and water and wastewater modernization programs. He has been
<br />accountable for ensuring quality, safety and schedules according to specifications, reviewing contract plans/specifications covering all building
<br />construction and mechanical and electrical installations, and developing preliminary findings on specifications, estimates, and recommendations
<br />for contract change orders. His additional training includes AHIT Training; United States Army Corps of Engineers Construction Quality
<br />Management for Contractors Training Course; and OSHA 30 Hours, CTQP Final Estimates I&I, QC Manager.
<br />19. RELEVAN T PROJECT S
<br />
<br />a.
<br />(1) TITLE AND LOCATION (City and State)
<br />S-151 Structure Replacement and Automation, Broward County, Florida – South
<br />Florida Water Management District (SFWMD)
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />
<br />CONSTRUCTION (If applicable)
<br />Ongoing
<br />(3) BRIEF DESCRIPTION (Brief scope size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Construction Manager: He is providing observation and documentation of the construction to ensure the work is performed according to the
<br />project drawings and specifications. He supervises construction meetings; reviews shop drawings, RFIs, and coordinates with the DPM. The
<br />project consists of the removal of six 7’ x 98’ corrugated metal pipes, construction of four cast in place concrete 8’ wide x 8’ high x 36’ long box
<br />culverts with wing walls, stop log recesses, remote controlled stainless steel gates, stilling wells, relocation of existing staff gauges, concrete
<br />platforms, LP tank, fencing, gates, new precast control building for system controls and generator. Construction Cost: $5,584,000
<br />
<br />b.
<br />(1) TITLE AND LOCATION (City and State)
<br />Miramar Parkway Streetscape from 68th Avenue to 64th Avenue CEI Services,
<br />City of Miramar/FDOT, District 4/Federal Highway Administration
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />
<br />CONSTRUCTION (If applicable)
<br />Ongoing
<br />(3) BRIEF DESCRIPTION (Brief scope size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Senior Project Engineer assisting the City in complying with all State and Federal Equal Employment Opportunity (EEO) requirements as they
<br />apply to this project, including the provisions of the U.S. DOT, the Federal Highway Administration, and the U.S. Department of Labor. He is
<br />responsible for all construction inspections, overseeing the resident compliance specialist, and performing project clos e-out. Project Length:
<br />0.58 miles
<br />
<br />c.
<br />(1) TITLE AND LOCATION (City and State)
<br />Citywide Pedestrian Safety Project, City of Dania Beach/FDOT/FHWA
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />
<br />CONSTRUCTION (If applicable)
<br />2020
<br />(3) BRIEF DESCRIPTION (Brief scope size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Senior Project Engineer who is coordinating with and providing FOOT with all the required information to ensure compliance wi th all LAP
<br />requirements, oversee the inspection team and the resident compliance specialist, keep the construction contract time established, and perform
<br />Final Construction Close-out. Fees Paid: $91,000 Construction Costs: $1,000,000.
<br />
<br />d.
<br />(1) TITLE AND LOCATION (City and State)
<br />Riverview Pump Station New Generator, Fire Suppression and Main Switch
<br />Disconnect, City of Miami, Florida
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />2019
<br />CONSTRUCTION (If applicable)
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Cost Estimator who prepared cost estimates and specifications for the replacement of the Riverview Pump Station Emergency Generator and
<br />pumps interconnection in the City of Miami. The pump station is part of the city's stormwater system. The project also includes a subconsultant
<br />design of a new Fire Suppressant System and Main Switch Disconnect for the Pump Station.
<br />Cost/Fees Paid: $74,200.00; Construction Cost: $935,000 (Estimated)
<br />
<br />e.
<br />(1) TITLE AND LOCATION (City and State)
<br /> Lakeside Community Hurricane Damage Repair, Miami-Dade County, Florida –
<br />Town of Medley
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES
<br />2018
<br />CONSTRUCTION (If applicable)
<br />
<br />(3) BRIEF DESCRIPTION (Brief scope size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Cost Estimator who was responsible for the cost data to repair the damaged seawalls due to Hurricane Irma. Erosion control methods, pollution
<br />prevention precautions, and earthwork construction are included in the project. He prepared a comprehensive structural assessment report,
<br />identifying any seawall deficiencies along the whole perimeter of the Lakeside Community Center. He participated in preparing the FEMA
<br />documents required to secure funding for the repairs. Cost/Fees Paid: $83,756; Construction Cost: $1,352,042.00.
<br /> STANDARD FORM 330 (1/2004) PAGE 2
<br />
<br />
<br />
<br /> Section E - Page | 25
|