<br />CTA Project No. 19-0035-001-01 01100-1 Golden Shores Street Lighting <br />October 12, 2020 SIB Bid No. 20-09-01 <br />SECTION 01100 - SPECIAL PROJECT PROCEDURES <br /> <br /> <br />PART 1 - GENERAL <br />1.01 EXISTING CONDITIONS <br />A. This Project is in an area with existing improvements consisting of water, sanitary sewer, <br />franchise utilities and storm drains. The Project is located within the City of Sunny Isles <br />Beach, Florida. The work shall be conducted in a manner that will minimize restriction of <br />access to public and private property and facilities, and minimize disruption of traffic. The <br />CONTRACTOR shall exercise extreme care to prevent damage to and interference with <br />existing improvements and to maintain the adjacent areas and travel routes safe for <br />pedestrian and vehicular traffic at all times. <br />1.02 EXISTING IMPROVEMENTS/UTILITIES <br />A. Existing improvements, including utilities, both surface and subsurface, shown on the <br />Drawings were located from existing records. No guaranty is made that all improvements <br />are shown or that those shown are entirely accurate. It is the CONTRACTOR’s <br />responsibility to verify the locations, character and depths of all existing improvements prior <br />to performing any Work. The City and ENGINEER will assume no liability for damages <br />sustained or costs incurred because of the CONTRACTOR's operations in the vicinity of <br />existing improvements. The CONTRACTOR hereby agrees that he shall have no claim for <br />delay or for extra compensation and that he shall have no claims for relief from any <br />obligation or responsibility under the Contract on account of any surface or subsurface <br />improvements or utilities encountered. CONTRACTOR shall notify the ENGINEER of any <br />deviation between existing conditions and the Drawings. The CONTRACTOR shall <br />coordinate all utility related work, of whatever nature, with the utility company or companies <br />whose services are impacted by the proposed construction or any element thereof. <br />1.03 LAND FOR FIELD OFFICES, STORAGE AND CONSTRUCTION PURPOSES <br />A. CONTRACTOR shall obtain and pay all costs in connection with any additional work areas, <br />storage sites, and access to the construction site or temporary right-of-way that may be <br />required for proper completion of the work. <br />B. Responsibility for safety and security of the storage site, including protection and <br />safekeeping of equipment and materials at or near the construction site, shall be solely that <br />of the CONTRACTOR and no claims shall be made against the City by reason of any act of <br />an employee or trespasser. CONTRACTOR shall place no equipment or materials upon <br />public or private property until permission has been received. Any agreement between <br />CONTRACTOR and alternate entity for use of land shall be submitted to City for review and <br />approval. <br />C. Upon completion of the Contract, CONTRACTOR shall remove from the site and storage <br />area all equipment, field offices, fencing, rubbish, etc., and leave the areas clean and <br />restored to its original condition. CONTRACTOR shall fill, compact and resurface all holes <br />or excavations made for fence installation, as directed by the ENGINEER. <br />