<br />00700 - 4/38 <br />project logs, has caused the contractor to suspend critical path activities during the exceptional <br />adverse weather event for more than fifty percent (50%) of the work period of the day <br />exceptionally adverse weather. Weather delay claim can be made for work day only. No time <br />extension will be allowed for weekend rains. <br /> <br />Work - All matters and things whether completed or partially completed, and includes all other <br />labor, materials, equipment and services provided or to be provided by the Successful Bidder in <br />accordance with the Contract. <br /> <br /> <br /> <br />ARTICLE 2 -- PRELIMINARY MATTERS <br /> <br />2.1 DELIVERY OF BONDS/INSURANCE CERTIFICATES <br /> <br />A. When the CONTRACTOR delivers the signed Agreements to the OWNER, the <br />CONTRACTOR shall also deliver to the OWNER such Bonds and Insurance <br />Policies and Certificates as the CONTRACTOR may be required to furnish in <br />accordance with the Contract Documents. <br /> <br />2.2 COPIES OF DOCUMENTS <br /> <br />A. The OWNER shall furnish to the CONTRACTOR the required number of copies <br />of the Contract Documents specified in the Supplementary General Conditions. <br /> <br />2.3 COMMENCEMENT OF CONTRACT TIME; NOTICE TO PROCEED <br /> <br />A. The Contract Time will start to run on the commencement date stated in the <br />Notice to Proceed. <br /> <br />2.4 STARTING THE PROJECT <br /> <br />A. The CONTRACTOR shall begin to perform the Work within 10 days after the <br />commencement date stated in the Notice to Proceed, but no Work shall be done <br />at the site prior to said commencement date. <br /> <br />2.5 BEFORE STARTING CONSTRUCTION <br /> <br />A. Before undertaking each part of the Work, the CONTRACTOR shall carefully <br />study and compare the Contract Documents and check and verify pertinent <br />figures shown thereon and all applicable field measurements. The <br />CONTRACTOR shall promptly report in writing to the ENGINEER any conflict, <br />error, or discrepancy which the CONTRACTOR may discover and shall obtain a <br />written interpretation or clarification from the ENGINEER before proceeding with <br />any Work affected thereby. <br /> <br />B. The CONTRACTOR shall submit to the ENGINEER for review those documents <br />called for under Section 01330 - Submittals in the General Requirements. <br /> <br /> <br /> <br />