Q. Please provide the existing pavement system section detail; some areas were found to have over <br />4 -in. of asphalt. <br />A. DEPTHS TO BE VERIFIED IN FIELD—SIGNIFICANT VARIANCES WILL BE ADDRESSED VIA <br />CONTINGENCY <br />Q. On sheets C39-057 <br />Conduit Alignment <br />Plans, <br />please <br />clarify and <br />explain the two note items: <br />NOTES: <br />1. CITY DIRECTIVE: ALL 1.5" CONDUIT & 3" CONDUIT <br />SHOWN ON PLANS TO BE BID & CONSTRUCTED <br />A5 2" & 4" CONDUIT, RESPECTIVELY. <br />A. FOLLOW 'REVISED" BID FORM NO 1.5" OR 3" CONDUIT INCLUDED IN PROJECT <br />2. NUMBER OF ATLANTIC BROADBAND CONDUITS SHOWN ON PLAN IS DOUBLE THE <br />AMOUNT OF CONDUITS REQUIRED.Q. <br />A. FOLLOW QUANTITY SHOWN ON "REVISED BID FORM" ADDENDUM # 1 <br />Q. The City will provide a Staging Area for materials and equipment? <br />A. YES <br />Q. Regarding the insurance division ,the City is requiring the Builder's Risk . Is this correct? <br />A. BR IF REQUIRED WILL BE PROVIDED BY CITY, <br />Q. Regarding the Storm Water Pollution Protection Plan (Sheet GN -1) ,the Contractor has to <br />design and install it, correct ? <br />A. FILTRATION INPUT INTO CITY STORM WATER SYSTEM BY CONTRACTOR —SEE ADDENDUM # 1 <br />Q.Is the intention of the City to place the Top Duct Bank at the elevation shown in the tables of <br />the Proposed Conduit Alignment? <br />A. NO SEE ABOVE QUESTION AND ADDENDUM # 1 <br />Q.If this is the case dewatering will be require . We understood in the prebid meeting that for <br />Dewatering, the Contractor can use the existing drainage, but in another project that we did for <br />the City, to get the Dewatering Permit with SFWMD they do not accepted that. Because most of <br />the Sunny Isles Beach drainage goes to the Intercostal. We had to build some Temporary Wells <br />and it does not work well . That could be the case here. Please advise <br />A. ASKED AND ANSWERED. <br />