2 <br /> <br />Q7. In various locations - The existing 11x18 HH located in the center median of Collins Ave has <br />a aluminum fence over the lid. Will the City be responsible for the fence removal and <br />replacement? <br />A7. City will remove fencing and landscaping prior to work. <br /> <br />Q8. Sheet 36 – Drawings call to pull fiber in existing fiber in conduit coming out of an 11x18 HH <br />going into sheet # 34 but its not highlighted. Is this part of this RFP? <br />A8.: That conduit route is for “PELICAN COMMUNITY PARK” but it was removed. There is no <br />fiber needed to be pulled into that location. <br /> <br />Q9. Sheet 51 & 52 – Drawings indicate an existing HH but is says (NONE), Is there an HH? <br />A9: There is no data of the size of this HH. <br /> <br />Q10. Sheet 55 – Will the conduit going West into Parking Garage (Sheet 54) be part of this RFP? <br />If so; is the construction footage included in Exhibit C – Price Sheet? <br />A10. Sheet 55 shows 143’ of (1) 1.25” conduit to be installed to edge of building. The pricing <br />sheet includes qtys for this bore along with core bore into the building and an estimate to pull <br />fiber in building and install patch panels at all the sites. <br /> <br />Q11. Sheet 55 – What is the method of installation and materials to be used? <br />A11.: Sheet 55 shows 143’ of (1) 1.25” conduit to be installed to edge of building. The pricing <br />sheet includes qtys for this bore along with core bore into the building and an estimate to pull <br />fiber in building and install patch panels at all the site. <br /> <br />Q12. Can the City provide a list of locations building entrances are expected to be completed <br />under this RFP? <br />A12. HERITAGE PARK , GOLDEN SHORES COMMUNITY PARK, PELICAN COMMUNITY PARK <br />(Already Connected), DATA CENTER, SENATOR GWEN MARGOLIS PARK, SAMSON <br />OCENAFRONT PARK, TOWN CENTER PARK, PIER PARK, GATEWAY PARK, OCEANIA PARK <br />INTRACOASTAL PARK 1, INTRACOASTAL PARK 2. <br /> <br />Q13. Can the City provide pictures of the locations it expect the vendor to complete the 4” Core <br />Bores? <br />A13. Per addendum # 2, the City held a site-visit on April 27, 2022 to allow interested firms to <br />inspect the sites. <br /> <br />Q14. What size Nema Enclosure will be required for this RFP? <br />A14. We did not specify. The splicing is to be done inside so a box that would allow a proper <br />bend radius of the fiber is all that is needed. <br /> <br />Q15. Can the City provide a list of locations that will require 2” building risers? <br />A15. Per addendum # 2, the City held a site-visit on April 27, 2022 to allow interested firms to <br />inspect the sites. <br />