Contractor: JG Group of LA, LLC. Dba Infrastructure Solutions Group
<br />Contact Name/Position: David Heroman / LV Manager
<br />Email:dheroman@isg.work
<br />Phone: 225-892-2891
<br />BB, Lateral, PON (This is for HLD estimates, this does not matter for LLD): BB Mileage - Total Passings
<br />Total Design Footage/Miles: 4,212.00 0.80 - Residential
<br />Buried: 4,212.00 0.80 - Business
<br />Aerial: - - - Anchor
<br />Region for unit pricing SouthEast 5%Underground overbuild percentage (If using centerline for PON assume 75%)
<br />Use MST's? (Only changes PON estimates) No MST 0%Rock Percentage
<br />Urban or Rural (Urban increases labor by 75%) Rural Normal Wage Prevailing Wage Requirement? (adds 30% to labor)
<br />Description
<br />IMPORTANT:
<br />Consultant's Estimated
<br />Quantity. Interested
<br />Firms: It is your
<br />responsibility to review
<br />these estimated
<br />quantities and revise if
<br />needed, based on your
<br />professional knowledge
<br />of the industry
<br />Unit Unit Price Total
<br />NOTES:
<br />IF YOUR FIRM'S QTY IS DIFFERENT THAN THE
<br />CONSULTANT'S ESTIMATED QTY IN
<br />"COLUMN C" INSERT YOUR BRIEF
<br />DESCRIPTION AS TO WHY YOU HAVE
<br />REVISED QTY.
<br />UNDERGROUND - BURIED
<br />Directional Bore (1) 1"-LF -$
<br />Directional Bore (2) 1"-LF -$
<br />Directional Bore (1) 2"682 LF $ 18.25 12,447.56$ Original Qty:682
<br />We calculated 329' of this from the drawing, but used supplied number.
<br />Directional Bore (1) 2" and (1) 1"-LF -$
<br />Directional Bore (1) 2" and (2) 1"-LF -$
<br />Directional Bore (2) 2"5 LF $ 18.25 91.26$ Original Qty: 5
<br />Directional Bore (2) 2" and (1) 1"-LF -$
<br />Directional Bore (3) 2"-LF -$
<br />Directional Bore (3) 2" and (1) 1"-LF -$
<br />Directional Bore (3) 2" and (2) 1"-LF -$
<br />Directional Bore (4) 2"-LF -$
<br />Directional Bore (1) 4"-LF -$
<br />Directional Bore (1) 1 1/4"3,742 LF $ 18.25 68,297.32$ Original Qty:3742
<br />We calculated 3,570' of this from the drawing, but used supplied number.
<br />Directional Bore (2) 1 1/4"-LF -$
<br />Directional Bore (3) 1 1/4"-LF -$
<br />Directional Bore (4) 1 1/4"-LF -$
<br />Microtrenching (Narrow Band Trenching) upto 12" deep -LF -$
<br />Microtrenching (Narrow Band Trenching) upto 18" deep -LF -$
<br />Microtrenching (Narrow Band Trenching) upto 24" deep -LF -$
<br />Vibratory Plow 4' deep (1) 2"-LF -$
<br />Vibratory Plow 4' deep (2) 2"-LF -$
<br />Open Cut & Trench (1) 2" at 30" Minimum Depth of Cover -LF -$
<br />Open Cut & Trench (2) 2" at 30" Minimum Depth of Cover -LF -$
<br />Open Cut & Trench (3) 2" at 30" Minimum Depth of Cover -LF -$
<br />Open Cut & Trench (4) 2" at 30" Minimum Depth of Cover -LF -$
<br />Sleeve existing 4" conduit (3) 1 1/4"-LF -$
<br />Pull (4) 2" sdr 11 conduits in 8" casing -FT -$
<br />Bore 6” Casing (Steel)-LF -$
<br />Bore 6” Casing (PVC)-LF -$
<br />Bore 8” Casing (Steel)-LF -$
<br />Bore 8” Casing (PVC)-LF -$
<br />Deep Bore - Water Crossing -LF -$
<br />Install Muletape in New Conduit 30,095 FT -$ Original Qty: 26493.6
<br />This is included with pipe calculations.
<br />Bore Rock Adder -LF -$
<br />Trench Rock Adder -LF -$
<br />Install #12 AWG Insulated Tracer Wire 26,494 LF $ 0.11 2,799.56$ Original Qty: 26493.6
<br />We calculated 25,214' of this from drawing, but used supplied number.
<br />Install 5/8"x8' Copper Clad Ground Rod 29 EA $ 327.57 9,499.54$ Original Qty: 18
<br />We calculated 29 of these from the drawing.
<br />Install 3.5" Dia PVC Round Marker Posts with Orange Dome Top -EA -$
<br />Install 3.5" Dia PVC Round Marker Posts with Orange Dome Top with Test Station -EA -$
<br />Install RFID Ball/Peg Markers -EA -$
<br />Install RFID Rope -LF -$
<br />Proof Existing Conduit - any size -LF -$
<br />Rod Existing Conduit and Install Pull Tape 21,020 LF $ 0.35 7,396.75$ Original Qty: 21020
<br />Remove existing cable - i.e. coax/twisted pair in street light conduits to replace
<br />with fiber -LF -$
<br />Installation, Underground Fiber Cable - Including Slack (2ct Fiber)-LF -$
<br />Installation, Underground Fiber Cable - Including Slack (All other fiber)33,294 LF $ 2.11 70,362.12$ Original Qty: 33294
<br />Installation, MST in Pedestal -EA -$
<br />Installation, Pedestal -EA -$
<br />Installation, Drop Vault, 12" X 12"-EA -$
<br />Installation, Small Vault, 17” x 30” (Now 24" x 36" x 18")18 EA $ 634.01 11,412.13$ Original Qty: 18
<br />Installation, Vault 24" x 36"-EA -$
<br />Installation, Large Vault 30" x 48" (Now 30" x 60" x 30")15 EA $ 1,585.02 23,775.27$ Original Qty: 1
<br />We calculated 15 from the drawings)
<br />Installation, Extra Large Vault 48" x 60"-EA -$
<br />Install 4'x4'x4' Split Concrete Manhole -EA -$
<br />Remove and Replace Handhole - including fixing sweeps into HH 17 EA $ 1,076.39 18,298.55$ Original Qty: 17
<br />Prep and Pour Concrete Pad for POP Site -EA -$
<br />Sawcut, Remove and Replace Asphalt 6" Thick 17 SqrFt $ 191.61 3,257.30$ Original Qty: 17
<br />Sawcut, Remove and Replace Concrete 6" Thick 272 SqrFt $ 191.61 52,116.78$ Original Qty: 272
<br />Remove and Replace Brick Pavers -SqrFt -$
<br />--$
<br />--$
<br />--$
<br />--$
<br />--$
<br />--$
<br />--$
<br />--$
<br />UNDERGROUND - BURIED LABOR TOTAL $ 279,754.16
<br />AERIAL -STRAND/LASH
<br />Lash/Mount Closure -EA -$
<br />Bond Strand/Guy to pole ground + materials EA -$
<br />Install Strand -FT -$
<br />Install Snow Shoes -EA -$
<br />Install Aerial Slack -EA -$
<br />Install / Lash Aerial Cable -FT -$
<br />Tree Trimming -FT -$
<br />Install Pole Risers -EA -$
<br />Install Down Guy & Anchors -EA -$
<br />Pole Transfer / Make Ready (Straight Through)-EA -$
<br />Pole Transfer / Make Ready (Dead-end)-EA -$
<br />Pole Transfer / Make Ready (Double Dead-end)-EA -$
<br />--$
<br />--$
<br />--$
<br />RFP 22-04-01 CITYWIDE FIBER NETWORK DEPLOYMENT
<br />I. Firms must use the Price Sheet below to submit firms price for this Project.
<br />II. Firms shall hold the unit Bid Prices firm throughout the Contract period. Bidder guarantees response time necessary to have a crew return to correct unfinished or unsatisfactory services.
<br />III. The City reserves the right to increase, decrease, and/or choose the items and quantities below for the Project to meet its available budget using the unit prices provided below.
<br />IIII. The not-to-exceed costs must be inclusive of all related expenses including contract administration, technical assistance to the City, travel, and associated actions necessary for the Project by the Consultant as
|