Laserfiche WebLink
in FPL completing the underground conversion. Maintaining ROHL, on standby, to complete the <br />miscellaneous tasks noted above was incurring costs to no advantage of the City. The Stout Group, the <br />current utility undergrounding contractor, has agreed to complete these tasks at the same cost ROHL <br />was being compensated without any additional monthly overhead or general conditions expense <br />which would have been due to ROHL. This is simply a transfer of previously allocated funds from onE <br />contractor to another realizing considerable savings of financial resources. <br />ADDITIONAL INFORMATION: <br />The total amount for Change Order Nos. 2 and 3 are for an amount not to exceed .$955,735.63 <br />bringing the total contract amount not to exceed $6,949,363.80. <br />FUNDING SOURCE: <br />Funds have been appropriated in account no. <br />ATTACHMENTS: <br />Resolution <br />Change Order No. 2 <br />Change Order No. 3 <br />Item Number: 10.Q <br />254 <br />