City of Sunny Isles Beach 18070 Collins Avenue, Sunny Isles Beach, Florida 33160 <br />(305) 947-0606 phone (305) 949-3113 Fax <br />10.8 Construction Change Directive <br />10.8.1 If the City and the Contractor cannot agree on the cost of a change in the Work, <br />the City may issue a written Construction Change Directive ordering a change in the <br />Work prior to reaching agreement with the Contractor on the adjustment, if any, in the <br />Contract Price and/or the Contract Time. <br />10.8.2 The City and the Contractor shall negotiate expeditiously and in good faith <br />for appropriate adjustments, as applicable, to the Contract Price and/or the Contract Time <br />arising out of a Construction Change Directive. Within 15 days of issuance of the <br />Construction Change Directive, the City will issue a Change Order based upon the City's <br />Representative's estimate for the cost of the Work and any additional agreed upon time <br />extension in accordance with Article 10.3. When a resolution has been reached on the <br />total cost of the Work and the cost of the Work is more or less than the City's <br />Representative's estimate, a final adjusting Change Order will be issued for the difference <br />in both cost and time as is applicable. <br />ARTICLE XI <br />UNCOVERING AND CORRECTING WORK <br />11.1 Uncovering Work <br />11.1.1 If any of the Work is covered contrary to the City's Representative's request <br />or to any provisions of this Contract, it shall, if required by the City's Representative or <br />the City, be uncovered for the City's Representative inspection and shall be properly <br />replaced at the Contractor's expense without change in the Contract Time. <br />11.1.2 If any of the Work is covered in a manner not inconsistent with Subparagraph <br />11.1.1 above, it shall, if required by the City's Representative or the City, be uncovered for <br />the inspection of the City's Representative or the City. If such Work conforms strictly <br />with this Contract, costs of uncovering and proper replacement shall by Change Order be <br />charged to the City. If such Work does not strictly conform with this Contract, the <br />Contractor shall pay the costs of uncovering and proper replacement. <br />11.2 Correcting Work <br />11.2.1 The Contractor shall immediately proceed to correct Work rejected <br />by the City's Representative or the City as defective or failing to conform to this <br />Contract. The Contractor shall pay all costs and expenses associated with correcting <br />such rejected Work, including any additional testing and inspections, and <br />reimbursement to the City for the City's Representative services and expenses made <br />necessary thereby. <br />11.2.2 If within one (1) year after Final Completion of the Work any of the Work is <br />found to be defective or not in accordance with this Contract, the Contractor shall correct <br />it promptly upon receipt of written notice from the City. This obligation shall survive <br />final payment by the City and termination of this Contract. With respect to Work <br />completed after Final Completion, this one (1) year obligation to specifically correct <br />29 <br />